Ref:874 Date: 23.10.

2024

QUOTATION for Road Construction


To
XYZ Bangladesh Ltd.
DEPZ (Ext. Area), Ganakbari, Ashulia
Savar, Dhaka.

Sl. Particulars Qty Unit rate Material Unit rate Service H.R.C
No. Unit Material Cost Service Cost Comments
Dismantling of existing road of carpeting & 218.7 0 4800 1049760 Cost of shift by
1
subbase course, dispose from Bepza. Truck included
Cum
Earth Excavation after existing subbase course 72.88 0 1100 80168 Cost of shift by
2
removal. Dispose from Bepza. Truck included
Cum
Preparation of sub grade with proper camber by 109.32 10500 1147860 1400 153048 Sub-grade
excavating earth equal to depth of pavement Base Type-I
thickness, consolidation with roller. Compaction
3
with Sand(Minimum F.M=0.8) & 40mm
downgraded brick chips. Compacted by Roller
Machine. Sub-base Thickness=150mm. Cum
Providing and laying double layer polythene 729 45 32805 15 10935
4
sheet under reinforced concrete. sqm
Reinforcement cement concrete works having 145.76 14500 2113520 1400 204064 Ready Mix-
specified compressive strength minimum Shah Cement
f'c=3500 psi or 25 MPa (*for normal concrete) at RMC
5 28 days cylinder strength. All complete
including cost of testing materials and concrete
& other charges as per direction of the engineer Cum
in charge.
Roller Machine rental & compaction works for 4 0 32000 128000
6
sub-base preparation. Days
Supplying, fabrication, and fixing to details as 13355 103 1375565 19 253745 Rod Brand:
per design M.S deformed bar as reinforcement
of required size and length for all RCC work in/c Made by EAF
straightening the rod, removing rusts, cleaning, technology like
7 cutting, hooking, bending, binding with 24 no. AKS, GPH
GI wire, placing the bars in position, in/c
lapping, spacing and securing them in position
by concrete blocks, metal chairs, etc. (Grade 500 Kg
(Rd 500/ 500W)
Total Bill(S/N=01-07) = Materials 4669750 Service 1879720

Total Bill (Products+Service) = 6,549,470


In Word: Sixty-five lakh forty nine thousand four hundred seventy Taka only.

Payment Terms & Conditions:


*Quotation prepared as per Visit & meeting.
*Considered, Material VAT=0% & Service cost includes VAT & AIT as per Govt. rules.
*50% Advance with Work Order.
*50% Payment after all Work Complete.
*Total Bill to be Paid within 30 Days after Work complete.
*Payment should be Paid by Cash or Cheque.

Completion Time:
Total 45 days (if can work continuously after work order. 60 days if cannot work on Friday & other holidays

Yours Faithfully

Mohaiminul Islam
Project Manager

_______ ______
For: M/S. H.R. Construction

Nobinagar, Ashulia, Savar, Dhaka-1344