Laying of CC Road in Kotakonda (V) of Narayanpet Mandal: DATA 2021-22
Laying of CC Road in Kotakonda (V) of Narayanpet Mandal: DATA 2021-22
Laying of CC Road in Kotakonda (V) of Narayanpet Mandal: DATA 2021-22
DATA 2021-22
Laying of CC Road in Kotakonda (V) of Narayanpet Mandal
1 Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5meter in width as
well as 10 sqm on plan including getting out and disposal of excavated earth as directed by
Engineer-in-charge for land leveling and land development (disposed earth to be neatly dressed and
leveled) with initial lead of 10 mts and initial lift of 1.5 mts (RSSR)
S.No
Ordinary soil, Lead upto 10 mts and lift upto 1.5 m (RSSR) 171.6 /Cum
11.I
Engaging Unskilled Labour for Labour charges for Spreading of Sand / Gravel in
2 the field as per RSSR 2019-20
1.04x245.
16.99
00/15
Rate as per 1 Cum 16.99 /Cum
Cement Concrete Pavement
3 Construction of un-reinforced plain cement concrete pavement, thickness as per design, over a
prepared sub base,with Nominal Mix of VCC (1:2:4) equivalent to M20 grade as per IS 456-2000
with 330 kgs of cement per cubic meter of concrete for internal roads with 43 grade cement or any
other type, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not
less than 0.2 cum capacity and appropriate weigh batcher using approved mix, laid in approved
fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges,
t l plates
steel l t including
i l di l
levelling
lli th formwork
the f k as per drawing),
d i ) spreading
di th concrete
the t with
ith sholvels,
h l l
rakes, compacted using needle and plate vibrators and finished in continuous operation including
provision of contraction and expansion, construction joints with High performance expansion joint
filler board / using concrete cutting machine with diamond studded saw, applying debonding strips,
primer, sealant, admixtures as approved, curing of concrete pavement for 14- days/curing
compound (where specified) finishing to lines and grade as per drawing but excluding cost of High
performance expansion joint filler board/ concrete groove cutting charges with daimond studded
saw including all applicable taxes.
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 545.00 2725.00
Mason (2nd class) day 5.00 515.00 2575.00
Mazdoor (unskilled) day 150.00 490.00 73500.00
Mazdoor(skilled) day 6.00 490.00 2940.00
Mazdoor(semi-skilled) day 6.00 490.00 2940.00
84680.00
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( Hour 36.00 627.60 22593.60
6 mixers) with weight batcher and
suitable capacity calibrated water tank
Needle Vibrator Hour 9.00 251.10 2259.90
Plate vibrator Hour 9.00 54.00 486.00
Water tanker 6 Kl. Capacity Hour 5.00 699.00 3495.00
8000 ltr Rs 898.20.
28834.50
Page 1 of 2
Data Sheet
c) Material
(I) Crushed stone coarse aggregates, grading will be as
per clause 1501.2.4.1 (Table 1500.1) of specifications
@ 0.90 Cum/cum of concrete
5986.99
Rate per cum 5986.99
4 TBS Cutting transverse contraction joints 3 to 4 mm wide and 1/3 rd depth of
C- concrete slab using concrete groove cutting machine with diamond studded saw
Q.VII within 24 - 48 hours of casting of CC Pavement. complete including subsequent
I-01 widening of the groove 8 to 10 mm. wide at top having depth of 15 mm. as
directed by Engineer incharge.
Unit = Rm
RM 1 55.00
55.00
55.00 / RM
5 Collection of gravel and stacking at site to departmental gauge and Spreading
including cost and conveyance of all material and labour charges etc complete
Unit = cum
Taking output = 15 cum
c) Material
Cost of Gravel Cum 1.00 192.88 192.88
192.88
Total cost per cum 192.88 /Cum
// Data approved //
Page 2 of 2