OFFICE OF THE MUNICIPAL CORPORATION BURHANPUR (M.P.

)
Estimate of road and Tensile fabric work near ladli Laxmi Garden Indira Colony
Dismantling of cement concrete pavement i/c breaking to pieces
notexceeding 0.02 cum in volume and stock piling at designated
2.5
1 locations and disposal of dismantled materials up to alead up to 1000
(P-15)
meter, stacking serviceable and unserviceable materials separately and as
per relevant clauses of section-200.
NO. L B D/H QTY. UNIT
1.00 115.00 3.50 0.15 60.38 cum.
60.38 cum. 749.00 45224.62
Excavation for road way in soil by manual means including loading in
3.1
2 tippers and disposal with all lifts and lead up to 1000 meters and as per
(P-21)
relevant clauses of section-300.
NO. L B D/H QTY. UNIT
1.00 31.00 3.50 0.45 48.83 cum.
48.83 cum. 119.00 5810.77
Crusher Run Macadam- Providing & laying crushed stone aggregate,
on a prepared surface,spreading and mixing with a motor grader,
4.2 b) watering and compacting with a vibratory roller as per clause 407 of the
3 i (P- specifications.
29) b) By Mixing Plant :
i)For 53 mm maximum
NO. L B D/H QTY. UNIT
1.00 31.00 3.50 0.10 10.85 cum.
10.85 cum. 1322.00 14343.70
Construction of Dry lean cement concrete Sub-base over aprepared sub-
grade with coarse and fine aggregate conforming to IS:383,the size of
coarse aggregate not exceeding 26.5mm,aggregate cement ration ot to
exceed 15:1,aggregate gradation after blending to be as per MORTH
Specifications Table 600-1,cement content not to be less than 150
kg/cum,optimum moisture content to be determined during trial length
6.1
4 construction , concrete strength not to be less than 10 Mpa at 7 days,
(P-48)
mixed in a batching plant,transported to site,laid with paver with
electronic sensor/mechanical paver,compacting with 8-10 tonnes
vibratory roller,finishing and curing and as per relevant clauses of
section- 601.

NO. L B D/H QTY. UNIT


1.00 31.00 3.50 0.10 10.85 cum.
10.85 cum. 3017.00 32734.45
Providing and laying Cement Concrete grade M 20 (Nominalmix1:1.5:3)
with 20 mm graded crushed stone aggregate,mixing shall be in
mechanical mixer,laying with paver compacting by use of pin,plate/
6.6
screed vibrators including form work by strong steel girders fixed by
5 (P-49)
spikes,separation membrane 125 micron thick,i/ccutting of joints @ 4
Vol III
to 5 m interval & filling it with hot applied bituminous
sealant(withoutdowel bars). (max. thickness 20cm)

6.7Deduct from Item No.6.2 ,6.3 and 6.6 above if paver with
electronic sensor is not used and laying, compaction is done by any
other method (Note: The acceptance criteria regarding
level,thickness,surface regularity,texture finish,strength of concrete
cum.
and all other quality control measures shall be the same as in case of
machine laid work.) This item is to be executed with Prior written
permission of Engineer- in-charge

NO. L B D/H QTY. UNIT 391.00


1.00 31.00 3.50 0.20 21.70 cum.
1.00 115.00 6.00 0.15 103.50 cum.
125.20 cum. 5420.00 678584.00
Brick work will well burnt open bhatta bricks crushing strength not less
6.8 than 25kg/cm² and water absoption not more than 20% in foundation and
6
P-56 plinthIn cm 1:6.

NO. L B D/H QTY. UNIT


6.00 3.00 0.20 0.40 1.44 cum.
1.44 cum. 3868.00 5569.92
Providing and laying below ground unplasticised PVC pipe to with stand
working pressure of 4 kg/cm2 soild waste pipes confirming to IS:13592
and IS:4985 including jointing with seal ring confirming to IS :5282
7 22.10.1 leaving 10mm gap for thermal expansion all necessary fittings etc.
complete. Excavation to be paid seperataly.
110 mm dia
NO. L B D/H QTY. UNIT
6.00 20.00 120.00 m
120.00 m 217.00 26040.00
Providing & fixing of precast reinforced cement concrete manhole
17.24.1 cover without frame including cost of transporting at site and all material
8 etc. complete
4
560 x 900 mm size extra heavy duty

Crossing Drain NO. No. QTY. UNIT


6.00 1.00 6.00 Each
6.00 Each 2053.00 12318.00
Tensile (fabric) structure system
Design built, supply and erection of Tensile (fabric) structure system
including designing and fabrication in M.S. steel tubular structure as per
Indian standard section as per approved design and shape including base
plate, dash fastener, clits etc. Cutting, patterning, plotting and wielding
12.85.2 of fabric with the help of tensile structure software. Fabric should be
P-399 wielded by high frequency PVC wielding in proper line with PVC cader
9 civil to be fixed on end of the fabric and to be stretched & fixed on M.S.
Sor design structure with the help of. M.S. Flat bar with self-taping screw.
2022 M.S. structure to be painted with one coat of epoxy primer with MRF PU
paint of approved colour in desired shape. With 1050 GSM tensile fabric
With precontraint tensile membrane 1050 GSM (15 Years warranty)

NO. L B D/H QTY. UNIT


1.00 31.00 3.20 1.00 99.20 Sqm
99.20 Sqm 8151.00 808579.20
Total 1629205.00
Add 18 % GST 293257.00
Total 1922462.00

Sub Engineer Assistant Engineer Executive Engineer


Municipal Corporation Municipal Corporation Municipal Corporation
Burhanpur Burhanpur Burhanpur