Est - New Pumpests - R5
Est - New Pumpests - R5
Est - New Pumpests - R5
NAME OF THE WORK: Formation of CC road along with CC drains on either side of proposed Bhimavaram
Bypass road (150 mts length) between l4’th and 17’th Wards in Tadepalligudem Municipality.
Page 1 564877597.xls
S.No Description of Item No L B D Qty Rate Per Amount
Construction of un-reinforced, plain cement concrete
pavement, thickness as per design, over a prepared sub base,
with 43 grade cement or any other type as per Clause
1501.2.2 M35 (Grade) Design Mix, coarse and fine aggregates
conforming to IS : 383, maximum in a concrete mixer of not
less than 0.2 cum capacity and appropeiate weigh batcher
using approved mix design, laid in approved fixed side
formwork (steel channel, laying and fixing of 125 mictron
thick polythene film, wedges, steel plates including levelling
the formwork as per drawing), spreading the concrete with
sholvels, rakes, compacted using needle, scareed and plate
vibrators and finished in continuous operation including
provision of ntraction and expansion, construction joints,
5 applying debonding strips, primer, sealant, dowel bars, near
approaches to bridge / culvert and construction joints,
admixtures as approved, curing of concrete slabs for 14- days,
curing compound (where specified) and water finishing to
lines and grade as per drawing and Technical Specification
Clause 1501 MORD. item RBR-CCPV-5 of standard data etc.,
complete as per S.S and as directed by the departmental
officer in charge of the work.
Page 2 564877597.xls
S.No Description of Item No L B D Qty Rate Per Amount
Providing High Yield Strength Deformed (HYSD)/ Thermo
Mechanically Treated (TMT) / Mild steel (MS) steel bars (Fe
415/ Fe 500 grade as per IS 1786-1979) of different diameters
for RCC works , including labour charges for straightening,
cutting, bending to required sizes and shapes, placing in
position with cover blocks of approved materials and size and
tying and lap-splicing with binding wire of 18 SWG, forming
grills for reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
1216.60
6 spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges 1186.19
such as cutting, bending, placing in position, tying including
sales and other taxes on all materials etc., complete for
finished item of work in all floors. ( APSS No.126) for Dewel
Bars) (Mild steel dowel bar 25mm dia of grade S 240. 500 mm
long @ 25 cm c/c for expansion and longitudinal joints and at
construction joint including 5 per cent wastage)
Page 3 564877597.xls
S.No Description of Item No L B D Qty Rate Per Amount
For road= longitudinal direction- 8 mm dia @ 30 cm c/c 20
(585/20=19.50 ) x152x0.395 Kg=1200.80 Kg.
For road =Trans direction - 8 mm dia @ 30 cm c/c 500
(15200/30=506.666)x5.85x0.395 Kg=1170.778 Kg
Total=308.640+140.676+1200.80+1170.778=2820.894 Kg.
2821.00 48.59 1 Kg 137072.00
Say 2821.00 Kg.
Granular sub-base/base/surface course with local materials
(Table 400.13) by mix in place method normal Construction of
granular sub-base by providing local material spreading in
uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at once and
7 compacting with smooth wheel roller to achieve the desired
density complete as per Clause 401.4 as per Technical
Specification Clause 408 MORD. using gravel (Hand Roller)
Superintending Engineer(PH)
Circle-Rajahmundry.
Page 4 564877597.xls
TADEPALLIGUDEM MUNICIPALITY
NAME OF THE WORK: Supply, Delivery and Erection of suitable capacity of Centrifugal Pumpsets to pump clear water from sump at Sitaramapet Reservoir to
proposed 900KL capacity Reservoir at Ramakrishna Rice Mill area in Yagarlapalli including all accessories such as panel board, cable connections and transformer
under 13th FC Grants for the year 2014-15
DETAILED ESTIMATE
S.No Description of Item Nos / % Length in mts Bredth in mts Depth in mts Quantity
1 1.00 Nos
2 2.00 Nos
3 Supply of Cubical main fitted with accessories of Seimens/Schneider makes with the following for incoming -1No.,
[160Amps MCCB], for out going 100Amps - 1No., FASD Starters - 1Nos, 63 Amp capacity Controlling MCB -1No, Vaccum
pump DOL starter - 1no., 32Amps 4 pole MCB for Lightening Controlling Aluminium Busbars chamber, with Aluminium
Flat CT Coils - 3nos., RYB indication Lamps - 3nos., Amps Meters -2nos., voltMeter - 1no., single phase preventer - 1nos,
Hour Meter -1nos, Amps and Volts meter selector switch - 2No, Internal wiring suitable lugs.
1 1.00 Nos
4 Supply Armered copper cable 3.5core, 35sqmm (of PVC Insulated single Leed 16 Sqmm. Sheated flexible) copper cable for
voltage upto 1100v as per IS694/1990 of makers Finolex/Polycab.
2 2.00 Nos
6 Laying the concerte bed block with1:2:4 usin 20mm graded material including cost convency of all materials to site including
of all labour charges centering charges mechain mixing, laying vibrating curing and other incidental charges but excluding
sendrige charges duly grouting the surface to neat finishing as directed by the departmental officers in charge.
2 2.00 Nos
C Plumping / Piping works for Manifolds
1 1.00 job
of 16 guage MS/CRCA sheet dust and vermi proof duly painted with
powder coating over the two layers of anti corosive red oxide paint. The
and suitable busbar of alluminium and internal writing with copper wires.
a) Incoming : 250 Amps MCCB -1no.
b) Outgoing : 100 amops MCCB - 3nos.
c) Capacitors : 10 Kvar bank with required capacity controlling unit -
3nos.
d) 32 MCB 4 pole for Vaccum pump and lighting arrangements - 2nos.
e) Supply,delivery and fixing of FASD starters of 40 HP capacity seimens
nake - 3nos.
f) 0-500 Volts meters of Rishab/Meeko makes with selector switch of
suitable size. - 1nos.
g) 0-200 Ammeter with selector switch and CT coils of 200/5 range
Rishab/Meeko - 4nos.
h) Red and green push bottons for the operation of starters - 4nos.
i) RYB indicating lamps of standard make - 12nos.,
J) APFC panel of suitable capacity for automatic power fadtor contol for
2no's x 43HP mortar
Leed 16 Sqmm. Sheated flexible) copper cable for voltage upto 1100v as
5
Pump set erection charges including cost of MS Foundation bolts and Nuts.
Stripps and 40mm GI pipes in the treated pits duly construting and filled
Resilient seated soft sealing gate valves (Sluice valves) with body bonnet
with EPDM food grade quality and seals of NBR and the valves should be
of vacuum tight and 100% leak proof with face to face dimensions as per
Electrostatic powder coating both inside and outside pocket less body
amendments upto date, if any) having body, cover, Door, Bearing Holder
with DI, Hinge Pin & Door Pin, Door Suspension Pin with stainless steel
(IS: 6603), body seat ring, door face ring, bearing bushes, plugs for hinge
pin with leaded tin bronze (IS 318); bolts, nuts with carbon steel; gaskets
with rubber; hinges with cast steel inclusive of transportation & all taxes
complete
200mm dia 2.00 Nos 33,311.26 1 Nos 66,622.52
11 Labour charges for Lowering and keeping in position of DI / CI Sluice
valves, reflux valves and scour valves
150mm dia 2.00 Nos 239.44 1 Nos 478.88
200mm dia 4.00 Nos 395.03 1 Nos 1,580.12
12 Jointing DI Pipes / CI pipes, fittings and valves with flanged ends
including cost of jointing materials such as bolts, rubber insertion, white
lead including filling with water, with lead up to 500 meters and testing to
required pressure complete. (Reference to specifications. BIS
No.3114/1994.)
150mm dia 12.00 Joints 498.17 1 Joint 5,978.04
200mm dia 21.00 Joints 544.59 1 Joint 11,436.39
250mm dia 18.00 Joints 787.33 1 Joint 14,171.94
(Socket) as per specification in light grey / natural ivory grey / any other
stores anywhere in Andhra Pradesh, including Excise duty and sales tax
14 Laying, jointing and testing for UPVC pressure pipes in ready made
excluding cost & conveyance of pipes from source of supply and jointing
15 VAT @ 5%
61,921.00
16 Seigniorage Charges
5,000.00
TOTAL 1,372,548.00
Total 255,000.00
or Say 255,000.00
2 Supply, Delivery of HSC pump of Kirloskar/Cromption/Mather & Platt
make having a duty capacity of 84liters/sec @ Total Head 31mts
capacity with an efficiency 75% casting, Bronze impellers, SS410/C-40
shaft, shaft Sleeve. The pump should fitted with suitable
Crompton/Kirloskar/equivalent make Horizontal Footmounted Squirrel
cage TEFC induction motor, IS 325 / ISI12615, voltage 415V+/-
10%,frequency 50Hz+/-5% Continous rating (SI Duty) IP-55
enclousre,with class "F" insulation suitable for ambient temperature
500C (Temperature rise limited to class "B") and altitude of upto 1000m
above MSL. the rate is inclusive of MS base plate luv joy type coupling
and other incidentals.
inclusive of all taxes such as VAT, CST,etc..,and including inspection
charges.
Nos 1.00 240,713.00 1Nos 240,713.00
(CST @ 2% included) Total 240,713.00
or Say 240,713.00
3 Supply of Cubical main fitted with accessories of Seimens/Schneider
makes with the following for incoming -1No., [160Amps MCCB], for out
going 100Amps - 1No., FASD Starters - 1Nos, 63 Amp capacity
Controlling MCB -1No, Vaccum pump DOL starter - 1no., 32Amps 4
pole MCB for Lightening Controlling Aluminium Busbars chamber, with
Aluminium Flat CT Coils - 3nos., RYB indication Lamps - 3nos., Amps
Meters -2nos., voltMeter - 1no., single phase preventer - 1nos, Hour
Meter -1nos, Amps and Volts meter selector switch - 2No, Internal
wiring suitable lugs.
564877597.xls / Data 02 13 / 89
S.No Description Unit Quantity Rate Rs Per / Unit Amount Rs.
7 Providing twin earthing to the new erected pumpets and motor control
panel board duly giving continuity connection with required size of GI
Stripps and 40mm GI pipes in the treated pits duly construting and filled
char coal, Salt and earthing powder.
Nos 1.00 7,500.00 1Nos 7,500.00
Total 7,500.00
or Say 7,500.00
8 Manufacture, Supply and delivery of CI specials & fittings, Class A to
suit the pipes as per IS 13382 & IS 1537 (considering latest
ammendments), including cost of materials and conveyance to the
work site including loading, unloading & stacking at site.
150mm dia
a) Labour
Plumber 1st class day 0.18 510.00 1Day 91.80
Plumber 2nd class day 0.42 400.00 1Day 168.00
Man mazdoor day 1.1 350.00 1Day 385.00
Municipal Area Allowance @ 20% 128.96
b) Material
Bolts and nuts 20mm dia 65mm long Kgs 24.00 123.00 1Kg 2,952.00
Rubber insertion 6mm thick Kgs 4.30 103.00 1Kg 442.90
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials
needed for testing (as per Sub Analysis 2 A)
Rmt 27.50 7.50 1Rmt 206.25
d = Total (a + b +c) 4,374.91
e) Add for Water @ 1% on labour & testing charges 9.80
f=d+e 4,384.71
g) Add for Overheads & Contractor's Profit @ 13.615% 596.98
h = Total cost for 10 Joints = f + g 4,981.69
i = Total cost for 1 Joint = h/10 498.17
564877597.xls / Data 02 14 / 89
S.No Description Unit Quantity Rate Rs Per / Unit Amount Rs.
13 Jointing CI pipes, fittings and valves with flanged ends including cost of
jointing materials such as bolts, rubber insertion, white lead including
filling with water, with lead up to 500 meters and testing to required
pressure complete. (Reference to specifications. BIS No.3114/1994.)
200mm dia
a) Labour
Plumber 1st class day 0.18 510.00 1Day 91.80
Plumber 2nd class day 0.42 400.00 1Day 168.00
Man mazdoor day 1.1 350.00 1Day 385.00
Municipal Area Allowance @ 20% 128.96
b) Material
Bolts and nuts 20mm dia 65mm long Kgs 25.20 123.00 1Kg 3,099.60
Rubber insertion 6mm thick Kgs 6.16 103.00 1Kg 634.48
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials
needed for testing (as per Sub Analysis 2 A)
250mm dia
a) Labour
Plumber 1st class day 0.2 510.00 1Day 102.00
Plumber 2nd class day 0.42 400.00 1Day 168.00
Man mazdoor day 1.2 350.00 1Day 420.00
Municipal Area Allowance @ 20% 138.00
b) Material
Bolts and nuts 20mm dia 65mm long Kgs 39.60 123.00 1Kg 4,870.80
Rubber insertion 6mm thick Kgs 8.50 103.00 1Kg 875.50
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials
needed for testing (as per Sub Analysis 2 A)
75mm dia
Basic Rate as per SSR 2016-17 Rmt 1 76.00 1Rmt 76.00
VAT @ 5% 3.80
Excise Duty @ 16.48% -
Sub Total 79.80
Add for Overheads & Contractor's Profit @ 13.615% 10.86
Total Cost 90.66
564877597.xls / Data 02 15 / 89
Lowering & Laying of uPVC pipes
Lowering, laying, jointing and testing to hydraulic test pressure including cost of water with minimum water lead of 500 m for UPVC pressure
pipes in readymade trenches true to alignment and gradient including all sundries but excluding cost and conveyance of pipes from source of
supply and jointing materials as per BIS no 7634 - Part 3 - 1975
Sub analysis for 160mm Dia Length = 500 Joints = 83
(i) For lowering/ sub surface transport Rates Quantity Amount
a) Labour
Mazdoor day 350.00 7.000 2,450.00
(ii)Jointing Fitter day 475.00 2.000 950.00
(iii) Testing (As per Sub- Analysis 2A) Rm 8.00 16.000 128.00
TOTAL
6,756.55
Rate per Rmt
13.51
Rate per 10mm/Rm
0.84
Specials - LS
Labour charges for lowering and keeping in position of C.I./DI Sluice valves(with cap/with hand wheel), reflux valves and scour valves. Unit
each PHE-CISV-15
size in mm 150 200 250 300 350
Labour for laying sluice valves with
cap/with hand wheel weight in kgs
Description of materials
beyond 5 km upto 30
conveyance charges
conveyance charges
conveyance charges
km @ Rs 12.60/km
beyond 30 km @
Rs 10.50/km
Basic Rate
SSR Code
Total cost
upto 5 km
Source
charg
Total
Lead
Unit
SNo
1 2 3 4 5 6 7 8 9 10 11 12
1
Cement (for the month of September, 2016) 1.00 MT Local 0.00 6,400.00 - - - - - 6,400.00
2
Steel (for the moonth of September, 2016) 1 cum Local 0.00 34,500.00 - - - - - 34,500.00
3 Sand for concrete (M006) 1 cum Vadapalli 35.00 95.00 84.00 315.00 52.50 451.50 397.39 492.39
4 Sand for plastering (M005) 1 cum Vadapalli 35.00 165.00 84.00 315.00 52.50 451.50 397.39 562.39
5 Sand for filling
Venkataraman
(M004) 1 cum 7.00 95.00 84.00 25.20 - 109.20 96.11 191.11
nagudem
6 HBG Metal - 6mm SS5 m/c (M050) 1 cum Pangidi 41.00 735.00 84.00 315.00 115.50 514.50 452.85 1,187.85
7 HBG Metal - 10mm SS5 m/c (M051) 1 cum Pangidi 41.00 935.00 84.00 315.00 115.50 514.50 452.85 1,387.85
8 HBG Metal - 12mm SS5 m/c (M052) 1 cum Pangidi 41.00 1,097.00 84.00 315.00 115.50 514.50 452.85 1,549.85
9
HBG Metal-13.20/12.50mm SS5 m/c (M052) M052) 1 cum Pangidi 41.00 1,097.00 84.00 315.00 115.50 514.50 452.85 1,549.85
10 HBG Metal - 20mm SS5 m/c (M053) 1 cum Pangidi 41.00 1,365.00 84.00 315.00 115.50 514.50 452.85 1,817.85
11 HBG Metal - 25mm SS5 m/c ) (M054 1 cum Pangidi 41.00 1,313.00 84.00 315.00 115.50 514.50 452.85 1,765.85
12 HBG Metal - 40mm SS5 (M055) 1 cum Pangidi 41.00 845.00 84.00 315.00 115.50 514.50 452.85 1,297.85
13 Aggregates 13.20 to 0.09mm graded HBG IRC
(M042) 1 cum Pangidi 41.00 798.00 84.00 315.00 115.50 514.50 452.85 1,250.85
m/c metal )
14 Aggregates 11.20 to 0.09mm graded HBG IRC
(M041) 1 cum Pangidi 41.00 704.00 84.00 315.00 115.50 514.50 452.85 1,156.85
m/c metal
15 Aggregates 2.36mm to 5mm graded HBG IRC
m/c metal
Initial Cost=308 (33a) 1 cum Pangidi 41.00 455.00 84.00 315.00 115.50 514.50 452.85 907.85
Basic Rate= 308+308*25% for machine
crusing+70 for blasting Charges
16
Aggregates 5 to 7 mm graded HBG IRC m/c metal
Initial Cost=504
(33b) 1 cum Pangidi 41.00 700.00 84.00 315.00 115.50 514.50 452.85 1,152.85
Basic Rate= 504+504*25% for machine
crusing+70 for blasting Charges
564877597.xls / LEAD 19 / 89
Description of materials
beyond 5 km upto 30
conveyance charges
conveyance charges
conveyance charges
km @ Rs 12.60/km
beyond 30 km @
Rs 10.50/km
Basic Rate
SSR Code
Total cost
upto 5 km
Source
charg
Total
Lead
Unit
SNo
1 2 3 4 5 6 7 8 9 10 11 12
18 Aggregates 12 to 14mm graded HBG IRC m/c
metal
Initial Cost=780 (33d) 1 cum Pangidi 41.00 1,045.00 84.00 315.00 115.50 514.50 452.85 1,497.85
Basic Rate=780+780*25% for machine
crusing+70 for blasting Charges
19 Aggregates 19 to 22mm graded HBG IRC m/c
metal
Initial Cost=984 (33e) 1 cum Pangidi 41.00 1,300.00 84.00 315.00 115.50 514.50 452.85 1,752.85
Basic Rate=984+984*25% for machine
crusing+70 for blasting Charges
20 Aggregates 25 to 27mm graded HBG IRC m/c
metal
Initial Cost=944 (33f) 1 cum Pangidi 41.00 1,250.00 84.00 315.00 115.50 514.50 452.85 1,702.85
Basic Rate=944+944*25% for machine
crusing+70 for blasting Charges
21 Aggregates 22.4 to 2.36 mm graded HBG IRC m/c
(M031) 1 cum Pangidi 41.00 914.00 84.00 315.00 115.50 514.50 452.85 1,366.85
metal
22 Aggregates 2.36 mm and below graded HBG IRC
(M022) 1 cum Pangidi 41.00 438.00 84.00 315.00 115.50 514.50 452.85 890.85
m/c metal
23 Aggregates 80 to 40mm graded HBG IRC m/c
sl No 10 1 cum Pangidi 41.00 650.00 84.00 315.00 115.50 514.50 452.85 1,102.85
metal)
24 Aggregates 63 to 45mm graded HBG IRC m/c
(M038) 1 cum Pangidi 41.00 662.00 84.00 315.00 115.50 514.50 452.85 1,114.85
metal
25 Aggregates 45 to 22.4 mm graded HBG IRC m/c
(M034) 1 cum Pangidi 41.00 1,145.00 84.00 315.00 115.50 514.50 452.85 1,597.85
metal
26
Stone Crusher Dust finer than 3mm with not more
(M021) 1 cum Pangidi 41.00 357.00 84.00 315.00 115.50 514.50 452.85 809.85
than 10% passing 0.075 sieve
564877597.xls / LEAD 20 / 89
Description of materials
beyond 5 km upto 30
conveyance charges
conveyance charges
conveyance charges
km @ Rs 12.60/km
beyond 30 km @
Rs 10.50/km
Basic Rate
SSR Code
Total cost
upto 5 km
Source
charg
Total
Lead
Unit
SNo
1 2 3 4 5 6 7 8 9 10 11 12
28 Aggregates 37.5 to 25 mm graded HBG IRC m/c
(M036) 1 cum Pangidi 41.00 1,145.00 84.00 315.00 115.50 514.50 452.85 1,597.85
metal
29 Close graded granular sub base material 2.36mm
(M020) 1 cum Pangidi 41.00 489.00 84.00 315.00 115.50 514.50 452.85 941.85
& below
30 Aggregate 25mm-10mm (M 046) 1 cum Pangidi 41.00 1,129.00 84.00 315.00 115.50 514.50 452.85 1,581.85
31 Aggregate 10mm - 5mm (M 040) 1 cum Pangidi 41.00 875.00 84.00 315.00 115.50 514.50 452.85 1,327.85
32 Aggregate 5.60mm below (M 030) 1 cum Pangidi 41.00 557.00 84.00 315.00 115.50 514.50 452.85 1,009.85
33 Aggregate 13.2mm-10mm (M 044) 1 cum Pangidi 41.00 1,029.00 84.00 315.00 115.50 514.50 452.85 1,481.85
34 Gravel for sub base (M008) 1 cum kankudu 9.00 103.00 84.00 50.40 - 134.40 118.29 221.29
35 Chatru / Quarry rubbish 35A 1 cum Pangidi 41.00 89.00 84.00 315.00 115.50 514.50 452.85 541.85
36 Pothineedi
Rough stone for revetment 225mm thick pg no.35 1 cum 33.00 145.00 84.00 315.00 31.50 430.50 378.91 523.91
palem
37 Pothineedi
Rough stone R.R stone for masonary pg no.36 1 cum 33.00 180.00 84.00 315.00 31.50 430.50 378.91 558.91
palem
38 Bricks 1000No.s Local 5,200.00 - - - 5,200.00
39 Vishakapatna
Bitumen 80/100 Grade 1 MT 220.00 37,565.45 - - - - 660.00 38,225.45
m
40 Vishakapatna
Bitumen 60/70 Grade 1 MT 220.00 38,523.05 - - - - 660.00 39,183.05
m
41 Vishakapatna
BT Emultion 1 MT 220.00 34,782.00 - - - - 660.00 35,442.00
m
42 Aggregates 20mm graded HBG SS5 m/c metal including seignoiorage, blasting charges, machine crushing charges Unit 1.00
cum
Cost 20mm metal 0.70 Cum 1,817.85 1.00 cum 1,272.49
Cost 13.20 / 12.50mm metal 0.10 Cum 1,549.85 1.00 cum 154.98
Cost 10mm metal 0.10 Cum 1,387.85 1.00 cum 138.78
Cost 6mm metal 0.10 Cum 1,187.85 1.00 cum 118.78
1,685.03
43 Aggregates 25 to 10mm graded HBG SS5 m/c metal including seignoiorage, blasting charges, machine crushing charges Unit
1.00 cum
Cost 25mm metal 0.70 Cum 1,765.85 1.00 cum 1,236.09
Cost 20mm metal 0.10 Cum 1,817.85 1.00 cum 181.78
Cost 13.20 to 12mm metal 0.10 Cum 1,549.85 1.00 cum 154.98
Cost 10mm metal 0.10 Cum 1,387.85 1.00 cum 138.78
1,711.63
564877597.xls / LEAD 21 / 89
1
SNo
564877597.xls / LEAD
2
Description of materials
Tadepalligudem Municipality
SSR Code
3
Unit
4
Source
5
Lead
Tadepalligudem Municipality
6
Basic Rate
conveyance charges
7
upto 5 km
conveyance charges
8
beyond 5 km upto 30
km @ Rs 12.60/km
conveyance charges
9
beyond 30 km @
Rs 10.50/km
Total
10
conveyance charges
Tadepalligudem Municipality
Deduct 13.615% on
11
Total cost
22 / 89
TADEPALLIGUDEM MUNICIPALITY
DATA 2016 - 17
S.No Description Unit Quantity Rate Rs Amount Rs.
564877597.xls / Data 01 23 / 89
S.No Description Unit Quantity Rate Rs Amount Rs.
or Say 1,189,975.00
564877597.xls / Data 01 24 / 89
S.No Description Unit Quantity Rate Rs Amount Rs.
Material:
185sqmm, 3.5Core XLPE insulated, 1100V grade armored alluminum
cable as per specifications confirming to IS : 7098 (part - 1)
Makes: torenet / Universal / CCI / Unicab
(SSR 2015-16, Page No: 142, Item Code: Elec-4.1.40, Sl. No:901)
1 Rmt 934.00 934.00
Labour:
Observed Data as 30% of the Material Cost 1 Rmt 280.20 280.20
Sub Total 1,214.20
Adding Contractor's Overhead & Profit @ 13.615% 165.31
Total 1,379.51
or Say 1,379.60
3 Supply & Installation of 25sqmm 3.5 core XLPE insulated, 1100V grade
armored alluminum cable as per specifications confirming to IS : 7098
(part - 1)
Makes: torenet / universal/ CCI / Unicab - Output 1Rmt
Material:
25sqmm, 3.5Core XLPE insulated, 1100V grade armored alluminum
cable as per specifications confirming to IS : 7098 (part - 1)
Makes: torenet / Universal / CCI / Unicab
(SSR 2015-16, Page No: 141, Item Code: Elec-4.1.19, Sl. No:880)
1 Rmt 207.00 207.00
Labour:
Observed Data as 30% of the Material Cost 1 Rmt 62.10 62.10
Sub Total 269.10
Adding Contractor's Overhead & Profit @ 13.615% 36.64
Total 305.74
or Say 305.80
4 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other deleterious aterial and disposal upto a lead of 50 m,
dressing of sides and ottom and backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH for foundations etc., complete as per S.S and as directed by the departmental officer in charge of the
work.
Labour
Mazdoor un skiled day 3.64 350.00 1,274.00
20% labour 254.80
1,528.80
Add 13.615% C.P 208.15
1,736.95
Rate per cum 173.69
564877597.xls / Data 01 25 / 89
S.No Description Unit Quantity Rate Rs Amount Rs.
5
Plain cement concrete (1:4:8) {Cement: fine aggreate: coarse aggregate} for foundation and under flooring bed using coarse
aggregate 40mm size hard machine crushed granite from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site including seigniorage charges, sales and other taxes on all materials and
including all charges for machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cmlayers
finishing top surface to the required level curing etc.complete for finished item of work{APSE No.402}- for buildings, Drains &
Culverts . RBR-FNDN-4A(I-i)
a Labour
Mason 1st class Day 0.1 445.00 44.50
Mazdoor un skilled Day 1.39 350.00 486.50
531.00
20% labour 106.20
b Machinery
Concrete mixer 10/7 cft, Pg No.42 (irrigation) Hour 0.4 471.10 188.44
8 Disposal of surplus earth with a lead of 1km over initial lead including ,transport, unloading etc complete unit 1.00
cum
6 Reinforced Cement Concrete M20 mix using 20mm graded hard machine crushed granite from approved quarry including
cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges,
sales and other taxes on all materials and including all charges for machine mixing, laying concrete in foundations and under
flooring bed, ramming in 15cm layers finishing top surface to the required level curing etc. complete for finished item of work
(APSS No. 402) .RBR-FNDN-4C(i) with 10% form work for culvert slabs
a Labour
Mason 1st class Day 0.1 445.00 44.50
Mazdoor un skilled Day 1.39 320.00 444.80
489.30
20% labour 97.86
b Machinery
Concrete mixer 10/7 cft Hour 0.4 620.00 248.00
c Material
cement kg 330 6.40 2.11
Coarse aggregate, 20mm graded cum 0.9 1,685.03 1,516.53
Fine aggregate cum 0.45 492.39 221.58
2,575.38
Form work@10% 257.54
2,832.91
Add 13.615% C.P 385.70
Taking out put 1 cum per cum 3,218.62
564877597.xls / Data 01 26 / 89
S.No Description Unit Quantity Rate Rs Amount Rs.
a Labour
Bar benders Day 10 555.00 5,550.00
Mazdoor unskiled Day 10 320.00 3,200.00
8,750.00
20% labour 1,750.00
b Material
HYSD /TMT/MS BARS INCLUDING 5% OF OVERLAPS AND t 1.05 34,500.00 36,225.00
WASTAGE
Binding wires kg 6 60.00 360.00
47,085.00
Add 13.615% C.P 6,410.62
Taking out put 1 MT per 1 MT 53,495.62
Rate per 1 kg 53.50
564877597.xls / Data 01 27 / 89
TADEPALLIGUDEM MUNICIPALITY
DATA 2016 - 17
S.No Description Unit Quantity Rate Rs Amount Rs.
1
Earthwork in excavation for structures as per drawing and technical specifications Clause
305.1 including setting out, construction of shoring and bracing, removal of stumps and other
deleterious aterial and disposal upto a lead of 50 m, dressing of sides and ottom and
backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH for foundations etc., complete as per S.S and as directed by the
departmental officer in charge of the work.
Labour
Mazdoor un skiled day 3.64 350.00 1,274.00
20% labour 254.80
1,528.80
Add 13.615% C.P 208.15
1,736.95
Rate per cum 173.69
2
Carting away of excavated earth / debris to a lead of 2KM (the rate including conveyance
charges, labour charges for loading, unloading charges) including ideal hire charges of truck
etc. complete as directed by the Departmental Authorities of the work.
a Labour
Mason 1st class Day 0.1 445.00 44.50
Mazdoor un skilled Day 1.39 350.00 486.50
531.00
20% labour 106.20
b Machinery
Concrete mixer 10/7 cft, Pg No.42 (irrigation) Hour 0.4 471.10 188.44
564877597.xls / Data 28 / 89
4
Granular sub-base/base/surface course with LOCAL MATERIALS(Table 400.13) by mix in
place method normal Construction of granular sub-base spreading in uniform layers and
compacting with smooth wheel roller to achieve the desired density etc., complete as
directed by the departmental in-charge. STONE DUST FOR ROAD WORK RBR-SBBS-12(ii)
5
Granular sub-base/base/surface course with Locally available materials (Table 400.13) by mix
in place method normal Construction of granular sub-base spreading in uniform layers and
compacting with smooth wheel roller to achieve the desired density etc., complete as
directed by the departmental in-charge.
RBR-SBBS-12(ii) 100% Gravel
564877597.xls / Data 29 / 89
87,381.15
Rate per cum= (A+B+C+D+E)/300 291.27
6 Disposal of surplus earth with a lead of 1km over initial lead including ,transport, unloading
etc complete unit 1.00 cum
Conveyance for 1km vide pg no 39(2015-2016)of
SSR cum 1 31.50 31.50
7
Sand filling,taking out put 1 cum, Ref-Part-1,pg No-8, RBR -FNDN-2(1)
a Labour
Mazdoor un skilled Day 0.31 350.00 108.50
20% labour 21.70
b Materials
Sand cum 1 191.11 191.11
water charges KL 0.1 103.00 10.30
331.61
Add 13.615% C.P 45.15
376.76
8 Cement Concrete Pavement-RBR-CCPV-5, pg No: 414, out put 75cum, with M35 grade
a Labour
Mason 1st class Day 5.00 445.00 2,225.00
Mason 2nd class Day 5.00 400.00 2,000.00
Mazdoor unskilled Day 150.00 350.00 52,500.00
Mazdoor skilled Day 6.00 320.00 1,920.00
Surveyor Day 2.00 - -
Mazdoor(Semi-skilled) Day 6.00 - -
Black smith for cutting dowel bars Day 1.00 - -
58,645.00
20% Labour 11,729.00
b Machinery
Concrete mixer 0.28/0.4cum capacity hour 36.00 471.10 16,959.60
Needle Vibrator, Pg No. 43, Sl. No: 40 (irg) hour 9.00 184.60 1,661.40
Screed Vibrator hour 9.00 - -
Plate Vibrator hour 9.00 - -
Concrete joint cutting machine hour 4.00 - -
Water tanker 6KL capacity hour 5.00 630.00 3,150.00
Air Compressor hour 2.00 - -
c Material
Crushed stone aggregate(25mm & 12.5mm
67.50
lending)
25mm HBG metal 2/3% on 67.5 cum 45.00 1,765.85 79,463.03
12.5mm HBG metal 1/3% on 67.5 cum 22.50 1,549.85 34,871.52
Sand cum 33.75 492.39 16,618.32
Cement MT 31.50 6,400.00 201,600.00
Polythene sheet 125micron sqm 412.50 18.00 7,425.00
Bitumen primer, BMT H-94 kg 5.00 45.00 225.00
Bitumenous sealent,BMT H-93 l 19.00 96.00 1,824.00
Jute Rope mts 90.00 - -
Debonding strips mts 90.00 - -
Plothyene Sheating No 483.00 - -
Plasticizer 0.5% ltr 122.00 - -
Curing Compound ltr 131.25 - -
Water for curing KL 18.00 103.00 1,854.00
564877597.xls / Data 30 / 89
Joint filler board 20mm BMT-U.02, Pg No.58(R&B) sqm 3.00 902.00 2,706.00
438,731.87
564877597.xls / Data 31 / 89
d form work @3% 13,161.96
451,893.82
Add 13.615% C.P 61,525.34
513,419.17
Rate per cum=75 6,845.59
11
Reinforced Cement Concrete M20 mix using 20mm graded hard machine crushed granite
from approved quarry including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, including seigniorage charges, sales and other taxes on
all materials and including all charges for machine mixing, laying concrete in foundations and
under flooring bed, ramming in 15cm layers finishing top surface to the required level curing
etc. complete for finished item of work (APSS No. 402) .RBR-FNDN-4C(i) with 10% form work
for culvert slabs
a Labour
Mason 1st class Day 0.1 445.00 44.50
Mazdoor un skilled Day 1.39 320.00 444.80
489.30
20% labour 97.86
b Machinery
Concrete mixer 10/7 cft Hour 0.4 620.00 248.00
c Material
cement kg 330 6.40 2.11
Coarse aggregate, 20mm graded cum 0.9 1,685.03 1,516.53
Fine aggregate cum 0.45 492.39 221.58
2,575.38
Form work@10% 257.54
2,832.91
Add 13.615% C.P 385.70
564877597.xls / Data 32 / 89
Taking out put 1 cum per cum 3,218.62
a Labour
Bar benders Day 10 555.00 5,550.00
Mazdoor unskiled Day 10 320.00 3,200.00
8,750.00
20% labour 1,750.00
b Material
HYSD /TMT/MS BARS INCLUDING 5% OF t 1.05 34,500.00 36,225.00
OVERLAPS AND WASTAGE
Binding wires kg 6 60.00 360.00
47,085.00
Add 13.615% C.P 6,410.62
Taking out put 1 MT per 1 MT 53,495.62
Rate per 1 kg 53.50
12 Plain Cement concrete (1:3:6) Nominal Mix with 20mm graded HBG SS5 m/c metal including
seignoiorage, blasting charges, machine crushing charges and including cost & conveyance
of all materials and labour chages for laying, concreting, watering and curing etc complete.Pg
No.489 (WITH OUT FORM WORK) RBR-FNDN-4A(I-i) for bed drain culvertFor Side Wall of
Drain (kerb Wall) (Lean cement Concrete)
a Labour
Mason 1st class Day 0.1 445.00 44.50
Mazdoor Day 1.39 320.00 444.80
489.30
20% labour 97.86
b Machinery
Concrete mixer 300/200 ltr Hour 0.4 352.50 141.00
Water tanker 6KL capacity Hour 0.13 630.00 81.90
c Material
cement kg 220 6.40 1,408.00
Coarse aggregate,20mm graded cum 0.9 1,817.85 1,636.06
Fine aggregate cum 0.45 492.39 221.58
Water KL 1.2 103.00 123.60
4,199.30
Add centering charges 4% 167.97
4,367.27
Add 13.615% C.P 594.60
Taking out put 1 cum per cum 4,961.87
Plain cement concrete(1:3:6) with 40mm (2/3rd) & 20mm (1/3rd) for drain & culvert walls .
13
RBR-FNDN-4A(I-i)-PG No.489 with form work 10%
a Labour
Mason 1st class Day 0.1 445.00 44.50
Mazdoor Day 1.39 320.00 444.80
489.30
20% labour 97.86
b Machinery
Concrete mixer 300/200 cft Hour 0.4 352.50 141.00
Water tanker KL 0.13 630.00 81.90
c Material
cement kg 220 6.40 1,408.00
Coarse aggregate, 40mm(2/3rd) cum 0.6 1,297.85 778.71
coarse aggregate, 20mm(1/3rd) cum 0.3 1,817.85 545.35
564877597.xls / Data 33 / 89
c
14
Bailing out water from the pipe line trenches with oil engine driven pump sets, including hire
charges, fuel charges and wages for Driver and Helper unit HP hour
Basic Rate (P.No. 7, Item No. 26.a) 1.00 HP Hour 53.00 53.00
Overheads & Contractors Profit @ 13.615% 7.22
Rate per 1.00 HP Hour 60.22
15 Fixing of channels, levelling the concrete with beam vibrator, vacuum dewatering power
trowelling to finish as per the directions of Engineer-in -Charge, rate inclusive of labour
charges all complete for finished item of work
Unit = Sqm
Taking output = 100 Sqm
a) Machinery
Vaccum dewatering mat hire charges Sqm 100.00 2.00 200.00
Vaccum dewatering machine hire charges Sqm 100.00 4.00 400.00
Generator 30 KVA (3 Phase) Hrs 4.00 832.30 3,329.20
rough finishing power trowerller skilled Sqm 100.00 4.00 400.00
Smooth finishing power trowerller unskilled Sqm 100.00 3.00 300.00
b) Labour
General operator skilled Nos 0.50 420.00 210.00
Vacuum dewatering skilled Nos 0.50 420.00 210.00
Vacuum dewatering un-skilled Nos 1.00 320.00 320.00
rough finishing power trowerller skilled Nos 0.50 420.00 210.00
rough finishing power trowerller un-skilled Nos 1.00 320.00 320.00
Smooth finishing power trowerller skilled Nos 0.50 420.00 210.00
Smooth finishing power trowerller unskilled Nos 1.00 320.00 320.00
Mason 1st Class Nos 0.50 420.00 210.00
Add MA @ 20% 402.00
Rate per 100 Sqm 7,041.20
Rate per 1 Sqm 70.41
Over heads and Contractors profit @ 13.615% 9.59
Rate per 1 Sqm 80.00
16 Carrying cut groove cutting 75mm deep with petrol driven saw as per the directions of
Engineer-in-Charge, rate including of labour charges, machinery charges all complete for
finished item of work
Unit = Sqm
Taking output = 100 RM
a) Machinery
Generator 30 KVA (3 Phase) Hrs 4.00 832.30 3,329.20
Floor saw cutting hire charges RM 100.00 15.00 1,500.00
Water tanker-8000 ltr Hrs 4.00 865.50 3,462.00
Bitumen 60/70 Gr Kgs 43.35 33.71 1,461.33
b) Labour
General operator skilled Nos 0.50 420.00 210.00
Floor power saw cutter skilled Nos 0.50 420.00 210.00
Floor power saw cutter unskilled Nos 1.00 320.00 320.00
Water tanker driver Nos 0.50 480.00 240.00
564877597.xls / Data 34 / 89
Man Mazdoor Nos 1.00 320.00 320.00
Rate per 100 RM 11,052.53
Rate per 1 RM 110.53
Over heads and Contractors profit @ 13.615% 15.05
Rate per 1 RM 125.58
17 Laying Sand Bags in the stipulated places including cost of empty cement bag, sand, thread,
stiching charges and labour charges with 13.615 % overhead charges and contractors profits
(Page No: 32, Sl. No: 2)
units=Nos
Nos 1 8.50 8.50
564877597.xls / Data 35 / 89
Tadepalligudem Municipality
Lowering D.I. Pipes (all classes) and specials (fittings) with s/s ends carefully into trenches and laying them tr
excluding cost and conveyance of pipes from source of supply
Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with s/s
ends carefully into trenches and laying them true to alignment and
250mm dia - DI K9
Observed Data for Testing of 450mm dia PSC Main: Pumping main to Hydralic field test pressure inc
Water with minimum lead of 500 M (PHE-LCIF-2A)
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
(a) Labour
Sl. No Description Mandays Rate per day
Fitters (2 x 3days)
Fitters 1st Class 3 475.00
Fitters 2nd Class 3 400.00
Sub Total
Municipal Area Allowance @ 20%
Total (a)
(b) Machinery
A
Sl. No Description Mandays Rate per day
Hire chargers for Hydralic field test
pressure testing including
Sub Analysis - 2A
Specials - LS
Material
250mm dia
(BLD-CSTN 2-11) - Cement concrete M- 20 mix using 20mm size graded machine crushed hard granite metal f
all materials like cement, fine aggregate, coarse aggregate, water etc., to site and including Seigniorage cha
operational, incidental and labour charges including centering, shuttering, machine mixing, laying concrete,
excluding VAT and labour cess.For Columns
Sl. No Description of Work Quantity
Material
a) Cement for Mix 330kgs
b) Coarse aggregate 20 mm graded metal 0.90Cum
c) Fine aggregate 0.45Cum
d) Water (including curing) 1.20KL
Labour
c) Mason - 1st Class 0.13Days
Mason - 2nd Class 0.27Days
d) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
Centering Charges = Labour charges @ Rs.1700.00 + Material
(D) Charges @ Rs. 341.00 + Municipal Area Allowance @ 20% over
Rs.1700.00 i.e., 340.00 = Rs. 2381.00
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges, laying , levelling , mach
etc complete as per SS for lintel beams / roof beams excluding VAT and labour cess.- unit 1Cum
Labour
c) Mason - 1st Class 0.13Days
d) Mason - 2nd Class 0.27Days
d) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges = Labour charges @ Rs.1426.00 + Material
Charges @ Rs.2002.00 + Municipal Area Allowance @ 20% over
Rs.1426.00 i.e., 285.20 = Rs. 2381.00
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges, laying , levelling , mach
etc complete as per SS up to 150mm thick Slab - excluding VAT and labour cess. - Unit 1Cum
Labour
c) Mason - 1st Class 0.133Days
d) Mason - 2nd Class 0.27Days
e) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges (1/0.115
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges, laying , levelling , mach
etc complete as per SS for sunshade - excluding VAT and labour cess. - Unit 1Cum
Sl. No Description of Work Quantity
Material
a) Cement for Mix 330kgs
b) Coarse aggregate 20 mm graded metal 0.90Cum
c) Fine aggregate 0.45Cum
d) Water (including curing) 1.20KL
Labour
c) Mason - 1st Class 0.133Days
d) Mason - 2nd Class 0.27Days
e) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges (1/0.115
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges, laying , levelling , mach
etc complete as per SS for Ramp outside of the pumping house - excluding VAT and labour cess. - Unit 1Cum
Sl. No Description of Work Quantity
Material
a) Cement for Mix 330kgs
b) Coarse aggregate 20 mm graded metal 0.90Cum
c) Fine aggregate 0.45Cum
d) Water (including curing) 1.20KL
Labour
c) Mason - 1st Class 0.133Days
d) Mason - 2nd Class 0.27Days
e) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges for Bed Blocks
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials a
and cost of centering etc, complete
Sl. No Description of Work Quantity
Material
a) Cement for Mix 330kgs
b) Coarse aggregate 20 mm graded metal 0.90Cum
c) Fine aggregate 0.45Cum
d) Water (including curing) 1.20KL
Labour
c) Mason - 1st Class 0.133Days
d) Mason - 2nd Class 0.27Days
e) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges for Bed Blocks
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
Brick Masonry in C.M (1:3) prop. with OPC Cement Using 2nd class bricks including cost and conveyance of a
cement mortar, watering, curing etc., complete complete for finished item of work.
BLD-CSTN-3-1
a) Material
OPC Cement
2nd Class Bricks
Fine Aggregate
b) Labour
Mason 1st Class
Mason 2nd Class
Mazdoor
Area allowance on labour
c) Machinery
NIL
(d) Sub Total (a) + (b) + (c)
towards Overheads & Contractors Profit
Supply & fixing of Rolling Shutter made of 80 x 1.25mm machine rolled CRCA laths, interlocked together through
end lockes, mounted on specially designed pipe shaft of 50mm dia nominal bore MS B class pipe with Plates,
and arrangements for inside & outside locking with push - pull operations including cost of hood cover and spr
primer, locks, ball bearings, all accessories etc., complete for finished item of work as per special spn: 1108 - BM
Sl. No Description of Work Quantity
a) Material
Cement Mortar (1:3)
b) Labour
Masons 1st Class
Mazdoor Unskilled
Labour component
Material
Bolts and nuts 20mm dia 65mm long 24.00Kgs
Rubber Insertion 6mm thick 4.30Kgs
150mm dia
Testing
150mm dia
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500
M, including hire charges of testing equipment, labour and Materials
needed for testing (as per Sub Analysis 2 A)
27.50Rmt
Total = Labour + Material + Testing
Add for water charges @ 1% on Labour & Testing Charges
Total
Add for Contractor's Overhead & Profilts @ 13.615%
Total per 10Joints
Total per 1Joint
Labour
Plumber 1st Class 0.180Days
Plumber 2nd Class 0.420Days
Man Mazdoor 1.100Days
Municipal Area Allowance @ 20%
Material
Bolts and nuts 20mm dia 65mm long 25.20Kgs
6.16Kgs
200mm dia
Material
Bolts and nuts 20mm dia 65mm long 39.60Kgs
8.50Kgs
250mm dia
Flooring with 25mm thick polished shabad stones set over base coat of CM (1:8) over already laid CC bed / RCC
including neat cement slurry of honey like consistency spread @ 3.3 kgs per sqm. & Jointed with neat cement to
including cost of all materials like cement, sand, and water and flooring stones etc., complete, including seigniora
charges, labour charges for dressing of flooring stones etc., complete for finished item of work, but excluding the
conveyance of all materials.
A. MATERIALS :
Polished Shabad Stone - Building SSR Page
No: 2 (BMT-B.17) 10.00 Sqm 1,654.00
Cement for CM (1:8) proportion for base coat 21.60 kgs 6.40
Cement for slurry 33.00 kgs 6.40
Cement for Jointing 20.00 kgs 6.40
Sand for CM (1:8) proportion for base coat 0.12 cums 492.39
B. LABOUR
Mason 1st class 3.10 day 445.00
Mason 2nd class 1.10 day 400.00
Mazdoor (unskilled) 0.32 day 350.00
Area allowance at @ 20% 1,931.50
YEAR 2015-16
and laying them true to alignment and gradient including all sundries but excluding
ations. BIS No.3114/94) - Assumption 10mts - 200mm dia CI Pipe - 5mts length -
Amount in Rs.
1,425.00
1,200.00
2,625.00
525.00
3,150.00
Amount in Rs.
3,600.00
3,600.00
Amount in Rs.
60.00
633.00
320.00
3,462.00
4,475.00
4475+3600+3150
11,225.00 Rs.
11,225.00 Rs.
22.45 Rs.
22.45 Rs.
0.50 Rs.
t of the gasket but including all sundries filling with water, with a water lead up to
3114/1994/12888/1987
Rate in Rs. Unit Amount in Rs.
- 1 Nos -
12.50 1 Rmt 625.00
1,482.40
14.82
1,497.22
203.85
1,701.07
170.11
352.50 1 HR 468.83
Total cost of machinery 468.83
2,381.00
8,954.77
1,154.74
10,109.51
10,109.51
10,109.51
ges, laying , levelling , machine mixing but exculding cost of steel in reinforcement,
- unit 1Cum
352.50 1 HR 468.83
Total cost of machinery 468.83
3,973.75
468.83
2,131.19
3,713.20
10,286.97
1,344.28
11,631.25
11,631.25
11,631.25
ges, laying , levelling , machine mixing but exculding cost of steel in reinforcement,
nit 1Cum
352.50 1 HR 468.83
Total cost of machinery 468.83
3,973.75
468.83
2,131.19
(1/0.115) x Rs. 389/- 3,382.61
9,956.38
1,307.21
11,263.59
11,263.59
11,263.59
ges, laying , levelling , machine mixing but exculding cost of steel in reinforcement,
3,973.75
468.83
2,131.19
(1/0.115) x Rs. 410/- 3,565.22
10,138.99
1,332.07
11,471.06
11,471.06
11,471.06
ges, laying , levelling , machine mixing but exculding cost of steel in reinforcement,
labour cess. - Unit 1Cum
Rate in Rs. Unit Amount in Rs.
352.50 1 HR 468.83
Total cost of machinery 468.83
3,973.75
468.83
2,131.19
305.00
6,878.77
888.19
7,766.96
7,766.96
7,766.96
onveyance of all materials and labor charges for mixing, laying, vibrating watering
352.50 1 HR 468.83
Total cost of machinery 468.83
3,973.75
468.83
2,131.19
305.00
6,878.77
888.19
7,766.96
7,766.96
7,766.96
g cost and conveyance of all materials and labour, seignorage charges, mixing of
Unit 1 Cum
4,580.04
Add 13.615% 4580.04 623.57
Total per 1Cum 5,203.61
per 1Cum 5,203.61
nterlocked together through their entire length and jointed together at the ends by
S B class pipe with Plates, plates, guide channels, stoppers, bottom locking plates
cost of hood cover and springs complete, painted with one coat of approved steel
s per special spn: 1108 - BMT-F-29
Rate in Rs. Unit Amount in Rs.
Units 10 Sqm.
123.00 1 kg 2,952.00
103.00 1 kg 442.90
7.50 1 Rmt 206.25
4,412.71
44.13
4,456.84
606.80
5,063.64
506.37
123.00 1 kg 3,099.60
103.00 1 kg 634.48
123.00 1 kg 4,870.80
103.00 1 kg 875.50
1,654.00
10sqmts
138.24
1kg
1kg 211.20
1kg 128.00
1Cum 59.09
day 1,379.50
day 440.00
day 112.00
386.30
4,508.33
45.08
4,553.41
619.95
5,173.36
Tadepalligudem Municipality
Observed Data for Testing of 450mm dia PSC Main: Pumping main to Hydralic field test pressure includi
Water with minimum lead of 500 M (PHE-LCIF-2A)
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
(a) Labour
Sl. No Description Mandays Rate per day
Fitters (2 x 3days)
Fitters 1st Class 3 475.00
Fitters 2nd Class 3 400.00
Sub Total
Municipal Area Allowance @ 20%
Total (a)
(b) Machinery
Sl. No Description Mandays Rate per day
Hire chargers for Hydralic field test
pressure testing including
transportation of water @ Rs.
1200/- (1000+200) / day 3 1,200.00
Sub Analysis - 2A
Total (b)
(c) Material
Sl. No Description Quantity Rate per unit
Specials - LS
Material
250mm dia
Material
Labour
Abstract
Centering Charges @ Rs. 61.00 for material, Rs. 244.00 for Labour &
(D)
MAA on labour @ 48.80 (Sl. No: B, Page no: 66, Building SoR)
Total
Total
(BLD-CSTN 2-11) - Cement concrete M- 20 mix using 20mm size graded machine crushed hard granite metal fr
of all materials like cement, fine aggregate, coarse aggregate, water etc., to site and including Seigniorage cha
all operational, incidental and labour charges including centering, shuttering, machine mixing, laying concrete
work, excluding VAT and labour cess.For raft/footing.
Sl. No Description of Work Quantity
Material
a) Cement for Mix 330kgs
b) Coarse aggregate 20 mm graded metal 0.90Cum
c) Fine aggregate 0.45Cum
d) Water (including curing) 1.20KL
Labour
c) Mason - 1st Class 0.13Days
Mason - 2nd Class 0.27Days
d) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
Centering Charges = Labour charges @ Rs. 473.00 + Material
(D) Charges @ Rs. 277.00 + Municipal Area Allowance @ 20% over
Rs.473.00 i.e., 94.60 = Rs. 844.60
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges, laying , levelling
reinforcement, etc complete as per SS for Side walls of valve chamber excluding VAT and labour cess.- unit 1Cum
Labour
c) Mason - 1st Class 0.13Days
d) Mason - 2nd Class 0.27Days
d) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges (1/0.30) x
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges, laying , levelling
reinforcement, etc complete as per SS up to 150mm thick Slab - For Cover Slabs of Valve Chamber excluding VA
Labour
c) Mason - 1st Class 0.133Days
d) Mason - 2nd Class 0.27Days
e) Mazdoor (Unskilled) 4.60Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
(D) Centering Charges (1/0.30) x
Total
(E) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
supply and fixing of SFRC man- hole frame with covers with ISI marking any where in AP, F.O.R. destination in
tax, but excluding CED, Vat and labour cess etc complete - 560mm dia HD20. (SOR Item No: 29 (d), Page No: 3
Sl. No Description of Work Quantity
Material
a) SFRC Manhole frame with Cover - HD 20 - 560mm clear opening 1Nos
b) Contractor's Overhead & Profit 13.615%
Municipality
EAR 2016-17
ause 305.1 including setting out, construction of shoring and bracing, removal
of sides and bottom and backfilling in trenches with excavated suitable material
Cum RBR-FNDN-1 I-A
- 1 Cum -
480.00 1 day -
350.00 1 day 1,274.00
254.80
1,528.80
-
-
1,528.80
1,528.80
208.15
1,736.95
1,736.95
173.70
173.70
h and laying them true to alignment and gradient including all sundries but
o specifications. BIS No.3114/94) - Assumption 10mts - 200mm dia CI Pipe -
Amount in Rs.
1,425.00
1,200.00
2,625.00
525.00
3,150.00
Amount in Rs.
3,600.00
3,600.00
Amount in Rs.
60.00
633.00
320.00
3,462.00
4,475.00
4475+3600+3150
11,225.00 Rs.
11,225.00 Rs.
22.45 Rs.
22.45 Rs.
0.50 Rs.
cost of the gasket but including all sundries filling with water, with a water lead
ns IS 3114/1994/12888/1987
Rate in Rs. Unit Amount in Rs.
- 1 Nos -
352.50 1 HR 352.50
Total cost of machinery 352.50
357.22
Total cost of Labour 2,143.34
4,093.25
352.50
2,143.34
353.80
6,942.89
936.97
7,879.86
7,879.86
7,879.87
352.50 1 HR 468.83
Total cost of machinery 468.83
3,973.75
468.83
2,131.19
844.60
7,418.37
945.56
8,363.93
8,363.93
8,363.93
charges, laying , levelling , machine mixing but exculding cost of steel in
and labour cess.- unit 1Cum
352.50 1 HR 468.83
Total cost of machinery 468.83
3,973.75
468.83
2,131.19
(1/0.30) x Rs.457.25/- 1,524.17
8,097.93
1,046.25
9,144.18
9,144.18
9,144.19
charges, laying , levelling , machine mixing but exculding cost of steel in
alve Chamber excluding VAT and labour cess. - Unit 1Cum
352.50 1 HR 468.83
Total cost of machinery 468.83
445.00 1 day 59.19
400.00 1 day 106.80
350.00 1 day 1,610.00
355.20
Total cost of Labour 2,131.19
3,973.75
468.83
2,131.19
(1/0.30) x Rs. 339/- 1,130.00
7,703.77
1,000.51
8,704.28
8,704.28
8,704.28
in AP, F.O.R. destination including loading, unloading & stacking at site , sales
Item No: 29 (d), Page No: 368)
Rate in Rs. Unit Amount in Rs.
Note: Classifications of Earthwork specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H unit - 1Cum
Ordinery soils - Mechanical means upto 3m depth, taking output 240Cum, Unit = 1Cum
Sl. No Description of Work Quantity
Material
a) N I L 240.00Cum
Machinery
b) Hydraulic Excavator 1Cum bucket capacity (Shovel 0.85Cum Capacity)
6.00Hr
Labour
c) Male 0.00Days
d) Mazdoor (Unskilled) 8.32Days
Municipal Area Allowance @ 20%
Sub Total
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
Total
(D) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 240Cum
Cost per 1Cum
Cost per 1Cum
Earth work in excavation for structures as per drawing and technical specifications clause 305.1 including setting
stumps and other deterious material and disposal upto a lead of 50mts, dressing of sides and bottom and backfilli
Technical specification 305 MORD / 304 MORTH for foundations of CC Drains and Culverts, pipe line trenches - RBR
Note: Classifications of Earthwork specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H unit - 1Cum
in Ordinery soils - Mechanical means from 3mts to 6mts depth, taking output 210Cum, Unit = 1Cum
Sl. No Description of Work Quantity
Material
a) N I L 210.00Cum
Machinery
Labour
c) Mason - 1st Class 0.10Days
d) Mazdoor (Unskilled) 1.39Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
Total
(D) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1Cum
Cost per 1Cum
Cement Mortar (1:3) prop., with O.P.C.
BLD-CSTN-1-4
Labour
Man Mazdoor for Mixing Mortar
20% labour
Material
Cement
Sand including 5% wastage
Seinorage charges for sand
Add C.P
Taking out put 1Cum
Plastering with CM (1:3) prop., 12 mm thick, with sponge finishing including cost and conveyance of all mater
lifts, curing, scaffolding and all other incidental and operational charges etc., complete for finished item of work
(BLD-CSTN 6-1)
Labour
Mason 1st class
Mazdoor
20% labour
Material
cement mortar (1:3)
Seigniorage charges for F.A
Add OH & CP
Taking out put 10sqm
Taking out put 1sqm
Plastering with CM (1:3) prop., 12 mm thick, with sponge finishing including cost and conveyance of all mater
lifts, curing, scaffolding and all other incidental and operational charges etc., complete for finished item of work - u
Sl. No Description of Work Quantity
1 Plastering CM 1:3, 12mm thick basic price 1.00Sqmts
2 Centering & Scaffolding charges - 1st floor
1.00Sqmts
Plastering with CM (1:3) prop., 12 mm thick, with sponge finishing including cost and conveyance of all mater
lifts, curing, scaffolding and all other incidental and operational charges etc., complete for finished item of work - f
Sl. No Description of Work Quantity
1 Plastering CM 1:3, 12mm thick basic price 1.00Sqmts
2 Centering & Scaffolding charges - 1st floor 1.00Sqmts
Painting with snow-cem or other equal and approved Water Proof Cement paoni over priming coat, 2
all materials and labour charges for painting, curing etc complete as per the directions of the departmental authoriti
(BLD-CSTN 10-4)
Labour
Painter
Mazdoor - Unskilled
Sundries including brushes, etc., @ 1%
20% labour
Material
Cement Paint at 3 sqm., per kg
Painting, priming coat by using water based cement primer of exterior grade - 2 on newly plastered surfaces includi
charges as per the directions of the departmental authorities..
(BLD-CSTN 10-2)
Labour
Painter
Sundries including brushes, etc., @ 0.50%
20% labour
Material
Cement Primer
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete
Sl. No Description of Work Quantity
Material
a) Cement for Mix 441kgs
b) Coarse aggregate 20 mm 0.90Cum
c) Fine aggregate 0.45Cum
d) Water (including curing) 1.20KL
Labour
a) Mason - 1st Class 0.067Days
b) Mason - 2nd Class 0.133Days
c) Mazdoor (Unskilled) 2.50Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
Total
(D) Add for contractor's profit and overheads on (A+B+C) @ 0.000%
Total
Cost per 1Cum
Cost per 1Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for base slab
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for slabs above 0.30mts thickness
1.54Sqmts
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for cylinderical wall from 3.66mts height to 7.32mts height
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for slabs upto 0.30mts thickness 3.33Sqmts
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for columns upto 3.66mts height
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for columns upto 3.66mts height 1.00Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for columns from 3.66mts height to 7.32mts height
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for columns from 3.66mts to 7.32mts
height 1.00Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for beams
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for beams 1.00Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for top slab
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for slab upto 150mm thickness 6.67Sqmts
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for top dome
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for dome slabs 1.00Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - for Haunches
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for bed blocks 1.00Cum
Providing VRCC with M30 Design Mix using 20mm HBG metal including cost and conveyance of all materials and lab
cost of centering etc, complete - sidewalls
Sl. No Description of Work Quantity
1 VRCC M30 basic rate 1.00Cum
2 Centering & Scaffolding charges - for slabs upto 0.30mts thickness
Rs.399/- per sqmt 1.00Cum
Machinery
a) N I L 0.00HR
Labour
a) Black Smith or Bar Bender 10.00Days
b) Mazdoor (Unskilled) 10.00Days
Municipal Area Allowance @ 20%
Abstract
(A) Cost of Material
(B) Cost of Machinery
(C) Cost of Labour
Total
(D) Add for contractor's profit and overheads on (A+B+C) @ 13.615%
Total
Cost per 1MT
Cost per 1MT
Cost per 1kg
480.00 1 day -
350.00 1 day 108.50
21.70
130.20
201.42
-
130.20
331.62
42.20
373.82
373.82
373.82
373.82
ause 305.1 including setting out, construction of shoring and bracing, removal of
des and bottom and backfilling in trenches with excavated suitable material as per
erts, pipe line trenches upto 3.00mts depth - RBR - FNDN-1, I-B
- 1 Cum -
2,815.90 1 Hr 16,895.40
480.00 1 day -
350.00 1 day 2,912.00
582.40
3,494.40
-
16,895.40
3,494.40
20,389.80
2,776.08
23,165.88
23,165.88
96.53
96.53
ause 305.1 including setting out, construction of shoring and bracing, removal of
des and bottom and backfilling in trenches with excavated suitable material as per
erts, pipe line trenches - RBR - FNDN-1, II-B
- 1 Cum -
2,815.90 1 Hr 16,895.40
480.00 1 day -
350.00 1 day 2,912.00
582.40
3,494.40
-
16,895.40
3,494.40
20,389.80
2,776.08
23,165.88
23,165.88
110.32
110.32
cluding cost of all materials and labour charges etc. complete- In foundation and
471.10 1 HR 471.10
Total cost of machinery 471.10
2,550.05
471.10
637.20
3,658.35
483.63
4,141.98
4,141.98
4,141.98
Day 0.2 350.00 70.00
70.00
14.00
471.10 1 HR 125.79
194.60 1 HR 51.96
Total cost of machinery 177.75
4,803.65
177.75
1,149.62
6,131.02
-
6,131.02
6,131.02
6,131.02
yance of all materials and labor charges for mixing, laying, vibrating watering and
34,500.00 1 MT 36,225.00
60.00 1 kgs 360.00
Total cost of materials 36,585.00
- 1 HR -
Total cost of machinery -
36,585.00
-
10,500.00
47,085.00
6,410.63
53,495.63
53,495.63
53,495.63
53.50
r Executive Engineer
pality Tadepalligudem Municipality