ESTIMATION
ESTIMATION
ESTIMATION
E CIVIL
10 Sqm
G.F 1 1.82 1.2 2.20
3 1.21 1.2 4.39
4 0.91 1.2 4.40
11.00 8600.00 94590.54
KSRB 4-6.7:Providing and removing centering
LINTEL shuttering,strutting,propping etc.and
removal of from work for sidesand soffits of
beams,beam haunching,Lintels cantilever griders
bressumers and lintels not exceeding 1m in depth
including cost of all materials,labours completeas per
11 specification Sp no KBS 4.6.2(SI no 4.34/17) Sqm
G.F 3 8.57 0.4 9.77
2 7.33 0.4 5.57
3 2.67 0.38 3.04
18.38 292 5368.24
KSRB 4.2.3:Providing and laying in position
reinforced cement concrete of mix 1:2:4 with 2mm
and dow size grade granite/Trap/Basalt
metal,machine mixed, concrete laid in layers not
exceeding 15cms thick,vibrated for R.C.C.Lintels,
columns of all sizes in foundation plinth and
superstrcture ground floor level for columns,
including cost of all materials,labour,HOM of
machinery,curing,complete asper specifications.Sp
12 No KBS 4.1,4.6 (si no.4.18/16) Cum
G.F 3 8.57 0.4 9.77
2 7.33 0.4 5.57
3 2.67 0.4 3.0438
21.98 5800.00 127457.32
KSRB 4-6.7:Providing and removing centering BEAM
shuttering,strutting,propping etc.and removal of
from work for sidesand soffits of beams,beam
haunching, cantilever griders bressumers and lintels
not exceeding 1m in depth including cost of all
materials,labours completeas per specification Sp no
13 KBS 4.6.2(SI no 4.34/17) Cum
G.F 3 8.57 0.23 0.6 3.548
3 7.33 0.23 0.6 3.0346
1 2.67 0.23 0.6 0.3685
6.95 350 2432.87
KSRB 4.2.9:Providing and laying in position
reinforced cement concrete of mix 1:2:4 with 2mm
and dow size grade granite/Trap/Basalt
metal,machine mixed, concrete laid in layers not
exceeding 15cms thick,vibrated for R.C.C.beams,
columns lintels,of all sizes in foundation plinth and
superstrcture ground floor level for columns,
including cost of all materials,labour,HOM of
machinery,curing,complete asper specifications.Sp
14 No KBS 4.1,4.6 (si no.4.18/16)
G.F 3 8.57 0.23 0.5 2.661
3 7.33 0.23 0.5 2.276
1 2.67 0.23 0.5 0.2763
5.21 5800.00 30237.11
KSRB 4-6.2:Providing and removing SLAB
centering, shuttering,strutting,propping etc.&
removal of from work for flat surface such as
suspended floors,roofs,landings,balconies and
likes,thickness upto 200mm including cost of all
materials,labor complete as per specification Sp no
15 KBS 4.6.2(SI no 4.29/17) Sqm
GF 1 7.33 8.57 62.82
62.82 3360.00 211068.82
KSRB 4.2.3:Providing and laying in position
reinforced cement concrete of mix 1:2:4 with 2mm
and dow size grade granite/Trap/Basalt
metal,machine mixed, concrete laid in layers not
exceeding 15cms thick,vibrated for R.C.C staire,slab
columns lintels,of all sizes in foundation plinth and
superstrcture ground floor level for columns, including
cost of all materials,labour,HOM of
machinery,curing,complete asper specifications.Sp
No KBS 4.1,4.6 (si no.4.12/15) SLAB
16 Cum
GF 1 7.33 8.57 0.1 8.17
8.17 9050.00 73905.49
KSRB 4.9.2:Providing and fabricating mild
steel/HYSD steel reinforcement including
straightening,cutting,bending,hooking,lapping &
welding wherever required,placing in position,tieing
with binding wire & anchoring to the adjoining
members wherever nessecary including all laps &
wastages etc,complete as per design & specification
& direcation (laps & wastages not to be measured &
paid).Sp.no KBS 4.6.3 (SI No 4.46/19)
17
Footing 280
Column 425
lintel 336.00
beam 455.00
slab 1350.00
23 Doors Sqm
G.F 1 1.21 2.1 2.54
5 0.91 2.1 9.56
12.10 3390 41005.44
KSRB 15-17.6:Providing and applying paintng two
coats (excluding priming coat) on new wood surface
and/or wood based surface with enamel paint to give
an even,cleaing the surface f all dirt,dust and foreign
matter,sand papering including cost of
materials,laour,complate as per specification.(SI no
24 15.60/113) Sqm
G.F 54
54.00 2280.00 123120.00
Total 3780424.85
7.5% Electrification charges 283531.86
7.5% Plumbing charges 283531.86
Supervision 4% 151216.99
GRAND TOTAL Rs--------- 4498706