ESTIMATION
ESTIMATION
ESTIMATION
24 Doors Sqm
G.F 1 1.3 1.3 1.69
3 0.9 2.7 7.29
2 0.76 1.52 2.31
F.F 2 0.9 1.8 3.24
2 0.76 1.52 2.31
Total 2265547.55
5% Electrification charges 113277.38
5% Plumbing 113277.38
Supervision 3% 67966.43
GRAND TOTAL Rs--------- 2560069
TWENTY FIVE LAKHS SIXTY THOUSAND RUPEES ONLY. SAY 2560000/-