Module 2, Part A
Module 2, Part A
MODULE 2
Part A
DESIGN OF DIVERSION WEIR AND MAIN CANAL
August, 2013
Bahir Dar
Contributors Alphabetically:
Abdo Kedir
Endager Getinet
Design of diversion weir and canal
TABLE OF CONTENTS
September 2012 ii
Design of diversion weir and canal
List of Figure
List of Tables
Table 1-1 Recommended runoff coefficient c for pervious surfaces by selected hydrologic soil
groupings and slope ranges ..................................................................................................... 4
Table 1-2 Frequency Factors for Rational Formula ........................................................................ 5
Table 1-3 Area to point rainfall ration .......................................................................................... 18
Table 1-4 Runoff curve number for the hydrological soil cover complex for condition II ......... 19
Table 1-5 Runoff curve number (CN) conversion and constants ................................................. 21
Table 2-1Recommended type of weir ........................................................................................... 26
Table 2-2 Tabular value of stage and discharge at the weir site for x-river ................................. 34
Table 2-3 Value of f for different soil ........................................................................................... 37
Table 2-4 Recommended value of Bligh coefficient and safe hydraulic gradient ........................ 38
Table 2-5 Coefficient of friction between concrete and cohesive and non cohesive soil ............. 44
Table 2-6 Internal angle of friction for different type of soil ....................................................... 45
Table 2-7 Allowable bearing pressure of different material ......................................................... 45
Table 3-1Recommended tertiary unit sizes................................................................................... 54
Table 3-2Hydraulic design formulae for unlined and lined canal ................................................ 58
Table 3-3 Recommended value of manning‘s ―n‖ ........................................................................ 60
Table 3-4 Permissible velocities for various soil textures ............................................................ 61
Table 3-5 Recommended canal side slope .................................................................................... 62
Table 3-6 Recommended B/D ratio for unlined channels ............................................................ 63
Table 3-7 Recommended canal freeboard .................................................................................... 66
Table 3-8 Seepage canal losses values for different soil canal routes .......................................... 67
Table 3-9 Recommended radius of bends ..................................................................................... 68
Table 3-10 Recommended seepage gradients for different soil types .......................................... 69
Table 3-11 Recommended Minimum Embankment Widths ........................................................ 70
3-12 Recommended Linings ......................................................................................................... 71
Table 3-13 Recommended values of maximum velocity & roughness coefficient ...................... 75
Table 3-14 Side slopes for lined canals ........................................................................................ 77
Table 3-15 Recommended B/d Ratio for Hard Surface ................................................................ 77
Table 3-16 Recommended freeboard values for hard surface lined canals .................................. 78
Table 3-17 Canal Lining Thickness .............................................................................................. 79
September 2012 iv
Design of diversion weir, canal and small dams
1 HYDROLOGY
1.1 Introduction
Hydrology is generally defined as a science dealing with the interrelationship between water on
and under the earth and in the atmosphere. For the purpose of this manual, hydrology will deal
with estimating flood magnitudes as the result of precipitation. In the design of hydraulic
structure like weir, floods are usually considered in terms of peak runoff or discharge in cubic
meters per second (m3/s) and hydrographs as discharge per time.
The collection of relevant data, test of the appropriateness of data‘s and analysis of data by
applying the principles of applied hydrology to obtain the required values are the first and most
important task to be conducted before the design of any hydraulic and irrigation structure
commences. For all hydrologic analyses, the following factors shall be evaluated and included
when they will have a significant effect on the final results:
Drainage basin characteristics including: size, shape, slope, land use, geology, soil type,
surface infiltration, and storage;
Stream channel characteristics including geometry and configuration, natural and
artificial controls, channel modification, aggradation - degradation, and debris;
Flood plain characteristics; and
Meteorological characteristics such as precipitation amounts and type, time rate of
precipitation (hyetograph)
The maximum design discharge (peak flood) is the peak river discharge that corresponds to a
certain return period which is usually decided by the designer on economic and engineering
ground. The maximum design discharge will be used to determine the weir crest length and the
back water curve & afflux.
Many hydrologic methods are available. The methods to be used and the circumstances for their
use are depends on the available data, size of the catchment and importance of the project. If
July 2013 1
Design of diversion weir, canal and small dams
possible the method shall be calibrated to local conditions and tested for accuracy and reliability.
The following hydrologic methods can be used for the peak flood estimation:
Rational method
SCS method (NCRS curve number method)
Catchment area regression equations
Flood frequency analysis like Gumbel or Log Pearson III analyses
Empirical formula
The flood frequency analysis method is particularly useful where long records of stream gauge
data are available at or near to and on the same stream as the structure site. Regional regression
equations provide estimates of peak discharge for watersheds in specific geographic regions.
Hence in this manual the Rational and SCS method will be described since these method can be
used in the area where streamflow data is not availiable which is quite often the case in the
design of weir for small scale irrigation scheme.
1.2.1 Return period
Flood discharges are often referred to as peak discharges as they occur at the peak of the
stream‘s flood hydrograph (discharge over time). Peak discharge magnitudes are a function of
their expected frequency of occurrence, which in turn relates to the magnitude of the potential
damage and hazard
While designing a weir, provision must be made for the flood that is likely to occur during the
lifetime of the structure. However, one can neither choose a very high nor a very low flood
magnitude for the design. A very high flood never occurs during the lifetime of the structure. If
such magnitude it will result in a costly structure. On the other hand, if a very low flood
magnitude is chosen for the design and exceeded, it will result in the failure of the structure,
causing much more damage than would have been caused in the absence of the structure. The
hydrological study guideline of the ministry of water resource of Ethiopia recommend a peak
river discharge that corresponds to 25 to 50 & 50 to 100 years return period for small & medium
scale diversion structures.
1.2.2 Rational Formula
The Rational Method was first introduced in 1889. Although it is often considered simplistic, it
still is appropriate for estimating peak discharges for small urban and rural watershed in which
July 2013 2
Design of diversion weir, canal and small dams
no significant flood storage appears. It is found to be suitable for peak flow prediction in small
catchments in area where the time of concentration is small.
The rational formula estimates the peak rate of runoff at any location in a catchment area as a
function of the catchment area, runoff coefficient, and means rainfall intensity for duration equal
to the time of concentration.
The rational formula is expressed as:
Where,
Q = design peak discharge (m3/sec).
C = runoff coefficient repressenting a ration of runoff to rainfall
I = average rainfall intensity for aduration equat to the time of concentratio, for a selected return
period, mm/hr
A = the watershed area (km2)
Assumption in rational formula
The rate of runoff resulting from any constant rainfall intensity is maximum when the duration of
rainfall equals the time of concentration. That is, if the rainfall intensity is constant, the entire
drainage area contributes to the peak discharge when the time of concentration has elapsed. This
assumption becomes less valid as the drainage area increases. For large drainage areas, the time
of concentration can be so large that the assumption of constant rainfall intensities for such long
periods is not valid, and shorter more intense rainfalls can produce larger peak flows.
Additionally, rainfall intensities usually vary during a storm.
Procedure for estimating peak discharge by Rational method:
1. Watershed area
The first step in applying the Rational Method is to obtain a good topographic map and define
the boundaries of the catchment area in question. A field inspection of the area should also be
made to determine if the natural drainage divides have been altered.
2. Time of concentration
Determine the time of concentration, with consideration for future characteristics of the
watershed. The time of concentration is the time required for water to flow from the
hydraulically most remote point of the catchment area to the point under investigation. Use of the
July 2013 3
Design of diversion weir, canal and small dams
Rational Method requires the time of concentration for each design point within the catchment
area. The duration of rainfall is then set equal to the time of concentration and is used to estimate
the design average rainfall intensity (I) in rational formula.
The time of concentration can be computed by method:
( )
√
Where‘
Tc = Time of concentration (hr)
L = Length of the main water course (mm)
S = slope of the main water course (m/m)
3. Runoff coefficient
Select or develop appropriate runoff coefficients for the watershed.
The runoff coefficient (C) is the variable of the Rational Method least susceptible to precise
determination and requires judgment and understanding on the part of the designer. A typical
coefficient represents the integrated effects of many drainage basin parameters. Table 1-1 gives
the recommended runoff coefficient (C) for pervious surfaces by selected hydrologic soil
groupings and slope ranges. From this table the C values for non-urban areas such as forest land,
agricultural land, and open space can be determined.
Table 1-1 Recommended runoff coefficient c for pervious surfaces by selected hydrologic
soil groupings and slope ranges
Soil Type
A B C D
Terrain Type
Flat, <2% 0.04-0.09 0.07-0.12 0.11-0.16 0.15-0.20
Rolling, 2-6% 0.09-0.14 0.12-0.17 0.16-0.21 0.20-0.25
Mountain, 6-15% 0.13-0.18 0.18-0.24 0.23-0.31 0.28-0.38
Escarpment, >15% 0.18-0.22 0.24-0.30 0.30-0.40 0.38-0.48
Where the watershed comprises more than one characteristic, you must estimate C values for
each area segment individually. You may then estimate a weighted C value using Equation:
July 2013 4
Design of diversion weir, canal and small dams
Where:
C = weighted (composite) runoff coefficient
C1, C2, C3,… Cn = runoff coefficients applicable to areas A1, A2, A3 … An
n = number of different type of area within watershed
At = total area = A1+A2+A3+…An
The coefficients given in Tables 1-1 are applicable for storms of 5-yr to 10-yr frequencies. Less
frequent, higher intensity storms will require modification of the coefficient because infiltration
and other losses have a proportionally smaller effect on runoff. The adjustment of the Rational
method for use with major storms can be made by multiplying the right side of the rational
formula by a frequency factor Cf. The rational formula now becomes:
5 1.0
10 1.0
25 1.1
50 1.2
100 1.25
Group C: Sandy clay loam. Soils having a moderately high runoff potential due to slow
infiltration rates. These soils primarily consist of soils in which a layer exists near the surface
that impedes the downward movement of water or soils with moderately fine to fine texture.
Group D: Clay loam, silty clay loam, sandy clay, silty clay or clay. Soils having a high runoff
potential due to very slow infiltration rates. These soils primarily consist of clays with high
swelling potential, soils with permanently-high water tables, soils with a clay pan or clay layer at
or near the surface, and shallow soils over nearly impervious parent material.
4. Rainfall intensity
The rainfall intensity (I) is the average rainfall rate in mm/hr for duration equal to the time of
concentration for a selected return period. Once a particular return period has been selected for
design and a time of concentration calculated for the catchment area, the rainfall intensity can be
determined from Rainfall-Intensity-Duration curves. Rainfall-Intensity-Duration curves for use
in Ethiopia are given in Annex-1-Hydrology part.
This method was developed by the U.S. Department of Agriculture and Natural Resources
Conservation Service (NRCS), formerly known as the Soil Conservation Service (SCS). The
SCS (now known as NRCS) peak flow method calculates peak flow as a function of drainage
basin area, potential watershed storage, and the time of concentration
The primary input variables for the NRCS methods are as follows:
drainage area size (A) in square kilometers
time of concentration (Tc) in hours
weighted runoff curve number (RCN)
rainfall distribution (NRCS Type II)
total design rainfall (P) in millimeters.
Catchment Area: A catchment area is determined from topographic maps and field surveys. For
large catchment areas it might be necessary to divide the area into sub-catchment areas to
account for major land use changes, obtain analysis results at different points within the
catchment area.
July 2013 6
Design of diversion weir, canal and small dams
Rainfall: The SCS method is based on a 24-hour storm event which has a Type II time
distribution. The Type II storm distribution is a 'typical" time distribution which the SCS has
prepared from rainfall records. It is applicable for interior rather than the coastal regions and
should be appropriate for Ethiopia. To use this distribution it is necessary for the user to obtain
the 24-hour rainfall value.
Rainfall-Runoff Equation: A relationship between accumulated rainfall and accumulated
runoff was derived by SCS from experimental plots for numerous hydrologic and vegetative
cover conditions. Data for land-treatment measures, such as contouring and terracing, from
experimental catchment areas were included.
The SCS runoff equation is therefore a method of estimating direct runoff from 24-hour or 1-day
storm rainfall. The equation is:
( )
( )
Where:
Q = accumulated direct runoff, mm
P = accumulated rainfall (potential maximum runoff), mm
Ia = initial abstraction including surface storage, interception, and infiltration prior to runoff, mm
S = potential maximum retention, mm
The relationship between Ia and S was developed from experimental catchment area data. It
removes the necessity for estimating Ia for common usage. The empirical relationship used in the
SCS runoff equation is:
Substituting 0.2S for Ia in foregoing equations, the SCS rainfall-runoff equation becomes:
( )
( )
S is related to the soil and cover conditions of the catchment area through the CN. CN has a
range of 0 to 100, and S is related to CN by:
( )
July 2013 7
Design of diversion weir, canal and small dams
The design storm rainfall is estimated by using frequency analysis. Extreme value type I
distribution (EVI) is applied for estimation of design storm rainfall. Storm rainfalls are
commonly modeled by EVI as it applicable to the extreme hydrological events.
EVI is expressed using the equation:
̅
Where = the design storm for a certain return period (mm)
̅ = the mean of the observed daily highest rainfall (mm)
s = the standard deviation of observed daily highest rainfall (mm)
= the frequency factor for a return period, T
For EVI, (Chow, 1964) derives the following expression for a frequency factor:
√
{ [ ( )]}
̅ ∑
√ ( ̅)
Example
The maximum daily rain fall of X-meteorological station for 19 years of record is shown in the
following table. Calculate the design storm that can be used for the determination of design
discharge for the design of diversion weir for 50 years return period
Maximum daily highest rainfall for 19 year period of x- meteorological station
Year 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981
RF
(mm) 43.1 44.3 44.7 47 49.2 50 50.8 51 58 58.3
Year 1982 1983 1984 1985 1986 1987 1988 1989 1990
RF
(mm) 58.5 60 6.4 66.2 67 82 85.5 95.2 99.8
Solution
From the descriptive statistics‘
July 2013 8
Design of diversion weir, canal and small dams
̅
s = 21.365
√
{ [ ( )]}
( )
√
Where‘
Tc = Time of concentration (hr)
L = Length of the main water course (mm)
S = slope of the main water course (m/m)
If the slope of the river course is not uniform in all reach of the river, the time of concentration is
computed by dividing the longest water course into different segment so that the time of
concentration would be found by summing the individual time of concentration.
Where
July 2013 9
Design of diversion weir, canal and small dams
( )
√
7 Rainfall Excess duration D hr 0.30
( )
July 2013 10
Design of diversion weir, canal and small dams
12 13 14 15 16 17 18 19
Duration Daily point Rainfall Rain Areal Areal Incremental Descending
rain fall of profile fall to point rainfall rainfall order
return profile rainfall
period 50 ratio
years
hr mm % mm % mm mm No
0-0.30 25 27.5 57 15.7 15.7 1. 15.7
0.30-0.60 34 37.4 59 22.1 6.4 2. 9.4
0.60-0.90 44 48.4 65 31.5 9.4 3. 6.4
110
0.90-1.20 48 52.8 69 36.4 4.9 4. 5.0
1.20-1.50 53 58.3 71 41.4 5.0 5. 4.9
1.50-1.80 57 62.7 73 45.8 4.4 6. 4.4
12 Fill in 0-D hr, D-2D hr, … 5D-6Dhr.
13 Determine the magnitude of the daily rainfall with the given recurrent interval by
applying statistical method.
14 Read from figure. 1-2 the rainfall profile (%) occurring in D, 2D, 3D … 6D
hours, and enter in 14.
15 Multiply 13 and 14 to find the rainfall profile (mm) and enter in 15
16 From Table 1-1, read areal to point rainfall ratio for different duration and
particular catchment area. The method is based on research conducted in India
and influenced by return period, magnitude of storm shape and orientation of area
etc. Alternatively for small catchment, you can use area reduction factor, ARF so
that column17 can be obtained by multiplying ARF with column 16
July 2013 11
Design of diversion weir, canal and small dams
20 21 22 23 24 25
Rearranged Rearranged Cumulative Times of incremental hydrograph
order incremental rainfall Time of Time of Peak Time to end
rainfall beginning
No. mm mm hr hr hr
6 4.4 4.4 0 1.23 3.3
4 5.0 9.4 0.30 1.53 3.6
3 6.4 15.8 0.60 1.83 3.9
1 15.7 31.5 0.90 2.13 4.2
2 9.4 40.9 1.20 2.43 4.5
5 4.9 45.8 1.50 2.73 4.8
20 From 19, mention the rearranged order as 6, 4, 3, 1, 2, 5 (arbitrarily) but
considering ascending and descending feature of the hydrograph ordinates, where
peak value is around the middle of the hydrograph.
21 Fill in the corresponding incremental rainfall value to the rearranged order of 20
from 18.
22 Fill in the cumulative rainfall values of 21 by adding with the rainfall values in the
preceding duration
23 Fill in the time of beginning of hydrograph as 0, D, 2D … 5D hr.
24 Fill in the time to peak as Tp, D+ Tp, 2D+Tp … 5D + Tp or add Tp in every value of
23 and mention in 24.
25 Add Tb in every value of 23 and fill in 25
July 2013 12
Design of diversion weir, canal and small dams
26 27 28 29 30 31
Land use Area Ratio Hydrologic Curve No. Weighted Sum Weighted ―CN‖
cover Condition ―CN‖ ―CN‖
Wood land 0.20 Poor 83 17 AMC CN
Meadows 0.30 Good 48 23 II 86
Cropland 0.50 Poor 91 46
III 94
26 Identify all types of land use cover such as cropped area, fallow land, pastures,
meadow, forest etc. from the catchment map.
27 Find ratio of each type of land use cover to the total catchment area and enter in
27.
28 Ascertain treatment practice of each type of land use cover, hydrologic condition
corresponding to it from the catchment map and enter in 28.
29 Ascertain hydrologic soil groups for each type of land use cover as below:
Group A: Low runoff potential
Group B: Moderate runoff potential
Group C: Soil having high runoff potential
Group D: Soil having very high runoff potential
Find the corresponding curve number ―CN‖ from Table 1-4.
30 Multiply 27 and 29 and enter in 30.
31 Add 30. This curve number is corresponding to antecedent moisture condition II
(AMC-II). Find ―CN‖ for AMC III from Table 1-5.
July 2013 13
Design of diversion weir, canal and small dams
( )
July 2013 14
Design of diversion weir, canal and small dams
35 36 37 38 39 40
23 24 25
Duration Cumulative Incremental Peak Time of Time Time Composite
Runoff Runoff Runoff for Beginning to to Hydrograph
Increment Peak End
Hr. mm Mm m3/S hr. hr. hr. t-Q
0-0.30 0 0 0 0 1.23 3.3 Triangular
0.30-0.60 1.7 1.7 20.4 0.30 1.53 3.6 Hydrograph
0.60-0.90 5.5 3.8 45.6 0.60 1.83 3.9 Synthesis
0.90-1.20 18.0 12.5 150.0 0.90 2.13 4.2
1.20-1.50 26.4 8.4 100.8 1.20 2.43 4.5
1.50-1.80 31.0 4.6 55.2 1.50 2.73 4.8
35 Enter the same time as in 12 i.e. 0 – D, D – 20, 2D – 3D, … 5D – 6D
36 There are the values of Q as found out in 34 corresponding to the value of P.
37 Find incremental runoff by reducing the values of 36 by preceding values.
38 Multiply 37 with peak rate of runoff corresponding to mm runoff excess as found at
11.
39 Plot triangular hydrograph, Figure1-1, with time of beginning, peak time and, time to
end as mentioned in 23, 24, 25 and peak runoff as mentioned in 38.
40 Plot a composite hydrograph, Figure1-1, by adding all the triangular hydrographs.
The resultant hydrograph will be composite hydrograph of desired return period. The
coordinate of the peak of this hydrograph will give the peak runoff with desired
return period.
July 2013 15
Design of diversion weir, canal and small dams
July 2013 16
Design of diversion weir, canal and small dams
July 2013 17
Design of diversion weir, canal and small dams
July 2013 18
Design of diversion weir, canal and small dams
July 2013 19
Design of diversion weir, canal and small dams
of grass or closed-seeded legumes in rotations, (d) percent of residue cover on the land surface
(good > 20%), and (e) degree of roughness.
Poor : Factors impair infiltration and tend to increase runoff.
Good : Factors encourage average and better than average infiltration and tend to
decrease runoff.
Meadow-continuous grass,
-- 35 59 72 79
protected from grazing
Poor 48 67 77 83
Brush-weed-grass mixture Fair 35 56 70 77
with brush the major element3 Good 304 48 65 73
Poor 57 73 82 86
Woods-grass combination 5 Fair 43 65 76 82
Good 32 58 72 79
Poor 45 66 77 83
Fair 36 60 73 79
Woods6 Good 304 55 70 77
Farms—buildings,lanes, -- 59 74 82 86
driveways, and surrounding
lots
1
Average runoff condition, and Ia = 0.2S
2
Poor: < 50% ground cover or heavily grazed with no mulch
Fair: 50 to 75% ground cover and not heavily grazed
Good: > 75% ground cover and lightly or only occasionally grazed
3
Poor: < 50% ground cover
July 2013 20
Design of diversion weir, canal and small dams
July 2013 21
Design of diversion weir, canal and small dams
2 DIVERSION WEIR
A diversion weir is a structure built across a river to raise water elevation up to a specified level
and to divert the water in a specified orientation for different purposes, such as irrigation,
hydropower generation, flood control, etc.
The diversion weir will be designed and constructed to serve the following functions:
Raise the water level on its upstream side;
Regulate the supply of water into the canal;
Control the entry of silt into the canal; and
Help in controlling changes in river behavior.
There are some important criteria that should always be satisfied in the design of diversion weirs
irrespective of type. These criteria are listed below:
1. The desired amount of water should be diverted for most of the time.
2. The sediment grains in water should not be allowed to enter the water intake. However, no
matter how perfect the design is, some sediment will always exist in the diverted water.
Therefore, an ideal design should aim at limiting the amount of entrainment of especially
coarse sediment into the intake.
3. Head losses in the intake should be minimized in order to have a low spillway.
4. Accumulated objects in front of the intake should be easily flushed downstream.
5. The flow velocity should be controlled in order to protect the river bed from the erosion and
to protect the related structures from scouring.
6. Water level fluctuations in front of the intake should be decreased.
In addition to the above criteria, the following condition should be assessed while selecting the
weir site for irrigation:
a) Proximity of the irrigable area
July 2013 22
Design of diversion weir, canal and small dams
The associated canal alignment should enable adequate command without excessive excavation
or embankment. Under optimum conditions the diversion site should be located neither very
close to the irrigable area so as not to miss gravity command area nor very far so as to avoid very
long idle reach of main canal that would inflate project cost.
With respect to the adjoining land surface, the elevation of water surface upstream of the weir
should not be so low as to require an excessively high weir to divert the water at the intake;
b) River bank (abutment) & river bed stability and water tightness
Assuring the water tightness & stability of the abutment & river bed is quite important once the
diversion site is selected. The weir should be located with firm, well defined banks so that the
river couldn‘t overtops its embankment and change its course. From the hydraulic point of view
the most suitable location for diversion structures is where the river is straight, has stable banks
& no deposit islands are formed. When a straight reach cannot be found, the weir should be built
on the outside bank of a bend where the river even at its minimum discharge can supply the main
canal with adequate water and sedimentation is less.
In contrast to the use of standard abstraction or a barrier across a river (which is a weir structure)
river bank diversion is also possible very rarely as it demands unerrodible riverbed &
undepositing river section. In addition the abstraction of flow in the irrigation season should be
very small percent of the river discharge and the minimum water level at the site should be
sufficient to provide command of the area so as to facilitate river bank diversion.
c) Availability of construction material at nearest place
d) Easy arrangement of flow diversion during construction
Diversion weirs can be classified according to various criteria. The following broad classification
could be employed:
a) According to function:
Storage weirs: used to divert & at the same time store water hence some time called low dams.
Pickup weirs: used to divert released water from an upstream located storage facility
Diversion /intake weirs: used to raise the level of water upto a required level & divert into a
canal.
Discharge weirs: generally used as spillways to carry over floods.
July 2013 23
Design of diversion weir, canal and small dams
July 2013 24
Design of diversion weir, canal and small dams
The most common components of the weirs & barrages are basically the following:
Weir /spilling section
Under-sluice /scouring sluice
Intake structure/head regulator for canal
Apron
Cutoff
Divide wall
Retaining and river protection works
1. Weir spilling section
Weir spilling section/overflow section of the weir is part of a weir placed across the river
obstructing the flow to attain certain head for commanding the field.
In selecting the type of spillway section to be used in the design of diversion structure (weir) for
a particular site, the following factors are to be considered particularly under the Ethiopian
Context. These are; character & strength of foundation, availability of construction material,
necessity for a controlled crest, cost & last but not least river morphology as related to sediment
transport based on the nature of the river (perennial or intermittent).
As it can be easily noticed most perennial & intermittently flowing rivers particularly in the
northern portion of the country, are characterized by river morphology which carries quite
significant volume of bed & suspended sediment load, where the bed load has sizes of boulders
ranging from few centimeters up to 75 cm. Thus this calls for a special consideration that will
allow the passage of this bed load right after the first occurrences of the flood flow season.
Therefore weirs with opening slots or barrages could be recommended for this purpose.
However, for ordinary purposes the following table suggests the recommended type of weirs
considering both safety & cost.
July 2013 25
Design of diversion weir, canal and small dams
2. Under-sluice
Under-sluice/scouring sluice are opening provided in the body of the weir. The function of the
under sluice is to intercept the bed loads as it approaches the canal intake and discharge it, with
its bed load, downstream of the weir. This allows drawing comparatively silt free water to the off
taking canal. Sluice also used be used to decrease the flow over the crest during the peak flow
period. The under-sluices may be on one or both sides of the headworks, depending on whether it
is a single canal or double canal system.
3. Intake structure
July 2013 26
Design of diversion weir, canal and small dams
Intake structure is provided to regulate the supply of water into the off taking canal; to control
entry of silt and other material to the off taking canal as well as to exclude high flood entering
into the off taking canal.
4. Divide Wall
It is a long solid wall constructed at right angle to the weir axis & divides the river channel into
two compartments, small and bigger. The smaller compartment which is nearer to the head
regulator will be used to create a stilling pond to be used by the head regulator.
It usually extends upstream beyond the beginning of the regulator and downstream to the
launching apron (talus). The sluice bay floor level is generally kept as low as possible to create
pool conditions (for silt settlement and its exclusion) and the dividing wall separates the two
floor levels of the weir. The downstream extension of the dividing wall provides a barrier
between the stilling basin and scouring bay, in order to avoid cross-currents. A properly designed
dividing wall can also induce desirable curvature to the flow for sediment exclusion from the
canal-head regulator.
5. Apron
The main purpose of u/s apron is to protect the channel bed from the impact of the flow against
the weir, and to protect the upstream bed against cross currents flow along the face of the weir,
particularly when the scouring sluices are in operation. The upstream apron also provides extra
length to the structure and hence reduces the under-floor pressure and exit gradient of seepage
flow. The upstream apron generally is generally set at the minimum bed level of the channel at
the site. The purpose of downstream apron is to resist uplift pressure, reduce the exit gradient of
seepage and to dissipate the energy over the weir
6. Cutoff
The primary purpose of cutoff is to increase the percolation path to prevent piping of the
foundation material and reduce percolation. Cutoffs also protect a structure from undermining if
excessive erosion should occur at the end of the structure.
7. Retaining wall and Wing wall
These walls are provided to anchor the structure into the abutment; to guide and confine the river
into a restricted channel for smooth entry of flow into the intake as well as to protect the area
from river overflow and submergence.
July 2013 27
Design of diversion weir, canal and small dams
July 2013 28
Design of diversion weir, canal and small dams
Where
Qo = Design discharge of the weir
C = Coefficient of discharge (1.705 for broad crested type of weir)
Lo = Length of the overflow section of the weir
He = Specific energy over the crest of the weir
The approach velocity head, Ha has been computed using the following formula:
Where, Hd = design head (excluding the velocity head) over the weir crest
The approach velocity head can also be expressed in terms of approach velocity:
( )
( )
Where, h = height of the weir
The value of Hd and Ha can be computed by trial and error from the foregoing two equation of Ha
The upstream and downstream water and energy level become:
U/S HFL = Zo + h + Hd
U/S TEL = U/S HFL + Ha
D/S HFL = Zo + D3
D/S TEL = D/S HFL+ hd
July 2013 29
Design of diversion weir, canal and small dams
Where
Zo = Elevation of river bed at the weir axis
D3 = tail water depth corresponding to the design discharge
hd = velocity head in d/s side
2.5.3 Section of the weir body
Design of vertical drop weir (Bligh theory)
Section of the weir body
Horizontal broad crested weir with vertical drop has been designed on Bligh‘s theory. Bligh‘s
has given the following expression for the design of the weir wall (Garg, 2007).
The top width of weir:
√
Where,
G = specific gravity of floor material
The bottom width of the weir (B) should not be less than:
√
2.5.4 Water profile at the weir site
The water surface profile downstream of the weir is required to carry out stability analysis of the
weir; structural design of the weir; design of downstream retaining wall, and d/s protection
works. The water profile upstream of the weir is required to determine the height of the river
banks upstream of the weir and to find out whether the water surface profile is high enough to
deliver the required discharge into the off-taking canal.
control location of the jump, the apron and stilling basin are designed to suit arrange of river
discharge.
Hydraulic jump on horizontal surface
On the horizontal apron downstream of a weir the following equation are valid.
√
( )
√
Where
F1 = the incoming Froude no
V1 = velocity at the weir toe = q/D1
q = discharge per metre width of the channel
HL = head loss (dissipated energy as a result of the jump)
dc = critical depth
D1 = pre-jump depth
D2 = sequent depth (conjugate depth)
D3 = Tail water depth
It should be noted that the friction loss on the weir is ignored, since the distance is short and
friction loss compared to the jump loss is very small. It also assumed that the jump loss occur
suddenly at the location of the jump.
The water depth at the weir toe can be determined by applying well-known Bernoulli‘s equation
between the weir crest and weir toe assuming that the jump forms on a horizontal surface and
friction loss is negligible.
The length of the jump can be estimated in terms of sequent depth for a given Froude number as
presented in Figure 2-2 (Chow, 1959)
Figure 2-2 Length of the jump in terms of sequent depth of jump in horizontal channel
July 2013 32
Design of diversion weir, canal and small dams
Approximate method
The approximate method is applicable method of determining the upstream water profile for
preliminary design purpose in a channel with uniform cross section and constant hydraulic
properties.
The water profile u/s of the weir can be computed by approximate method (Baban, 1995):
( )
July 2013 33
Design of diversion weir, canal and small dams
1. Surveys should be carried out at the location of the weir to draw the cross-section of the river
2. The cross-section needs to be drawn to a suitable scale. Assume different water depths in the
river, and determine the water area and wetted perimeter corresponding to each depth.
2471
2470
Elevation (masl)
2469
2468
2467
2466
2465
0 5 10 15 20 25 30 35 40
Distance (m)
3. For each depth, determine the flow velocity and discharges by using manning equation.
Table 2-2 Tabular value of stage and discharge at the weir site for x-river
Stage Elevation A P R DHYD S n vavg Q
m masl sqm m m m m/m m/s m3/s
0 2465.852 0 0 0 0 0 0 0 0
0.4 2466.252 1.42 4.73 0.3 0.32 0.0104 0.05 0.92 1.3
0.8 2466.652 3.31 5.74 0.58 0.68 0.0104 0.05 1.42 4.7
1.2 2467.052 5.27 6.55 0.8 1.06 0.0104 0.05 1.77 9.33
1.6 2467.452 7.37 8.11 0.91 1.24 0.0104 0.05 1.92 14.16
2 2467.852 10.09 10.28 0.98 1.32 0.0104 0.05 2.02 20.41
2.4 2468.252 14.25 17.62 0.81 0.96 0.0104 0.05 1.78 25.31
July 2013 34
Design of diversion weir, canal and small dams
4. Plot the assumed depths and their corresponding discharge to present the rating curve
July 2013 35
Design of diversion weir, canal and small dams
The piping phenomenon can be minimized by reducing the exit gradient, i.e. by increasing the
creep length. The creep length can be increased by increasing the impervious floor length and by
providing upstream and downstream cut-off piles.
2.5.6.2 Uplift pressures
The base of the impervious floor is subjected to uplift pressures as the water seeps through below
it. The uplift upstream of the weir is balanced by the weight of water standing above the floor in
the pond, whereas on the downstream side there may not be any such balancing water weight.
The impervious base floor may crack or rupture if its weight is not sufficient to resist the uplift
pressure. Any rupture thus developed in turn reduces the effective length of the impervious floor
(i.e. reduction in creep length), which increases the exit gradient.
The provision of increased creep lengths and sufficient floor thickness prevents this kind of
failure.
( )
If the actual water waterway provided is greater than or equal to the regime width,
( )
Where
Rs = Regime scour depth measured from the high flood level (HFL)
q = the discharge per unit width of the channel
f = Lacey‘s silt factor corresponding to the bed material
√
Where d is the mean depth of the particle up to the scour depth
July 2013 36
Design of diversion weir, canal and small dams
The value of Lacey‘s silt factor of bed material are shown in Table 2-3, where the bed materials
are built up with the alluvial deposits up to 2 mm size as there is a limitation for adopting
Lacey‘s silt values.
The scour depth may be multiplied by a factor of safety of 1.25 and 1.5 for upstream and
downstream cut-off depth determination respectively.
Upstream scour depth = 1.25Rs and Upstream cut-off level = U/S HFL- 1.25 R
Downstream scour depth = 1.5Rs and Downstream cut-off level = D/S HFL -1.5 R
Weir failure due to scour can be prevented by extending the sheet pile cut-offs to a level
sufficiently below the régime scour depth across the full width of the river.
2.5.6.4 Length and thickness of apron by Bligh’s theory
The Bligh‘s theory assumes that the water upstream of the weir creeps to its downstream, along
the contact base of the structure with the soil. On other words, water creeps along the bottom of
the contour of the structure. The length of path thus traversed by water is called the length of the
creep. Further, it is assumed that in this theory, that loss of the head is proportional to the length
of the creep. The short coming of this method is that it does not discriminate between the
horizontal & vertical creep.
The exit gradient according to the creep flow theory proposed by Bligh is
Where;
July 2013 37
Design of diversion weir, canal and small dams
Safety against piping or undermining: According to Bligh, safety against piping can be
ensured by providing sufficient creep length, given by L = CH L, where C is Bligh‘s coefficient
for the soil. The hydraulic gradient, i.e. HL/L is equal to 1/C. Hence it may be stated that the
hydraulic gradient must be kept under a safe limit in order to ensure safety against piping.
Table 2-4 Recommended value of Bligh coefficient and safe hydraulic gradient
Type of soil Creep coefficient Safe hydraulic gradient
(C) (1/C)
Light sand and mud 18 1/18
Fine sand 15 1/15
Coarse grained sand 12 1/12
Boulder or shingles and gravel mix 5 to 9 1/5 to 1/9
sand
Safety again uplift: If h‘ is the uplift pressure head at a point under the floor, the pressure
intensity is
July 2013 38
Design of diversion weir, canal and small dams
Giving,
Where G is the relative density of the floor material (ρm/ρ)
Thus we can write
( )
Where h is the pressure head (ordinate of hydraulic gradient) measured above the top of the
floor. A safety factor of around 33% is usually adopted, thus giving the design thickness of the
floor as
The floor thickness has to be designed according to the above equation only for the downstream
floor. The water standing on the upstream floor more than counter balance the uplift caused by
the same water and hence, only a nominal floor thickness is required on the upstream side, so as
to resist wear, impact of flowing water, etc.
From pressure diagram the uplift pressure at point x will be
July 2013 39
Design of diversion weir, canal and small dams
( )
L= 2d1+b+2d2
July 2013 40
Design of diversion weir, canal and small dams
Alternatively the length of protection work can be worked out from Varsheny recommendation
Where
Dd = water depth corresponding to the design discharge just of the solid apron at downstream of
the weir
Du = water depth corresponding to the design discharge just of solid apron at the upstream side
of the weir
NB: Refer Lanes and Khosla‘s theory for seepage and uplift calculation from any standard
hydraulic/irrigation book.
The stability design provides adequate structure dimensions so that for the foundation materials,
the structure will resist sliding, overturning, tension and limit foundation pressure below the
maximum allowable bearing pressure.
The major forces acting on the weir are:
1. Static water pressure
2. Uplift water pressure
3. Soil reaction at the weir base
4. Friction forces at the base which develop to balance the horizontal forces
July 2013 41
Design of diversion weir, canal and small dams
( )
Self weight load
Structure self-weight is accounted for in terms of its resultant, Pm, which is considered to act
through the centroid of the cross-sectional area Ap of the weir profile:
γc is unit weight of material used for the construction of the weir (KN/m3)
Uplift load
July 2013 42
Design of diversion weir, canal and small dams
Where z1 the water head upstream side of the weir and z2 is the tail water depth
Referring to the two-dimensional profile, the nominal plan area is defined by section thickness,
i.e. Ah = T then the foregoing equation becomes
With pu acting through the centroid of the pressure diagram at a distance of y1 (m) from the heel
and
Alternatively the uplift area can be split into rectangular and triangular area and the uplift load
and centroid for each section can be determined separately.
Sediment load
The gradual accumulation of significant deposits of fine sediment, notably silts, against the face
of the weir generates a resultant horizontal force, Ps. The magnitude of Ps, which is additional to
water load, Pwh is a function of the sediment depth,z3, the submerged unit weight, γ‘s and the
active lateral pressure coefficient, Ka i.e.
Where Øs is the angle of shearing resistance of the sediment (see Table 2-6)
The submerged unit weight,
Stability criteria
For the structure to remain stable the following criteria must be fulfilled:
1. The sum of stabilizing moment must exceed the sum of overturning moment of the structure
for safety against overturning.
∑
∑
2. The structure subject to differential lateral pressure must capably resist the tendency to slide
for safety against sliding.
∑
∑
3. The resultant of all forces acting on the structure should fall within the middle third of the
structure base so that tension will not develop at the base.
∑
| |
∑
4. The contact pressure (stress) at the toe or heel of the weir body should be less than the
allowable bearing pressure of the foundation material.
∑
( )
Where
μ = coefficient of friction
ex = the eccentricity
Pall = allowable pressure of the foundation material (see Table 2-7)
B = width of the weir base
The coefficient of friction, between concrete and cohesive and non cohesive soils is given below
Table 2-5 Coefficient of friction between concrete and cohesive and non cohesive soil
Type of material μ
Non cohesive soils
Sand 0.56
Non cohesive soils
Gravel 0.60
Rubble/stone 0.70
Clay 0.2
Cohesive soils
Sandy clay 0.3
July 2013 44
Design of diversion weir, canal and small dams
2.7 Under-sluice
The hydraulic design of under-sluice/scouring sluice will consider that the discharge over the
under sluice portion be capable of passing the highest of the following:
Two times the canal discharge to ensure good scouring capacity; and
10-20% of the maximum flood discharge at high flood
The under sluice portion should not be too wide to keep the approach velocities sufficiently
lower than the critical velocities to cause maximum settling of suspended silt load within the
pond. It needs to be checked that the gate opening is never less than two times the maximum size
of sediment the river is capable of moving.
July 2013 45
Design of diversion weir, canal and small dams
The floor level of the under sluice is kept as low as possible to create pool condition for silt
settlement and exclusion.
The hydraulic design is largely related to considerations of the range of upstream and
downstream water levels as the river flow varies and the type of control used for regulation.
The sluice gate is underflow gates if the water passes underneath the structure. Hydraulically the
underflow gates function as orifice and thus the flow through them is computed using orifice
flow equation:
√
Where,
Cd = Coefficient of discharge ≈ 0.61
A = Area of the gate opening (m2)
h = head available at the gate and equal to the measure of difference in water surface elevation,
upstream and downstream from the gate if the bottom of the gate is submerged on the
downstream side whereas for free flow it is a measure of water surface elevation to the center of
gate opening.
When stop-log is used for regulation, hydraulically the flow over the under-sluice act as a weir
and the flow through the structure are determined from the formula for flow over rectangular
weir:
Where
Qu = Discharge of the under-sluice portion (m3/s)
C = Coefficient of discharge = 1.705
Lu = Width of the under-sluice portion (m)
H = Total head over the crest (m)
Canal head regulator regulates the supply of water into the off-taking canal and control the entry
of silt and other material to the off-taking canal. Head regulator also exclude high flood entering
into the off-taking canal.
July 2013 46
Design of diversion weir, canal and small dams
The weir creates sufficient head to supply the main irrigation canal with the design discharge.
The canal head regulator is usually gated to control the amount of flow into the canal. Most
common types of head regulators are
a) Open intake (submerged not submerged): This consist of intake mouth, which acts an orifice
or weir, a transition and main canal. The intake is usually designed as an orifice.
b) Closed or culvert intake: The characteristics of the flow in culverts are very complicated since
the flow is controlled by many factors. In designing a culver for the intake, it is convenient to
assume that the pipe is fully flowing with both end submerged and to include all the head losses
in the orifice coefficient. To obtain the full flow condition, the pipe inlet must be submerged to a
depth not less the sum of the velocity head and head loss in the pipe.
The discharge through the regulator is computed by the orifice formula:
√
C = discharge coefficient
A = Area of the gate opening
H = head over the opening
Retaining walls are provided to anchor the structure into the abutment; to guide and confine the
river into a restricted channel for smooth entry of flow into the intake as well as to protect the
area from river overflow and submergence and to provide stability of earth and any other
material.
2.9.1 Type of retaining wall
Based on the method of achieving stability, retaining walls may be categorized into the
following:
Gravity wall
The stability of the wall depends on their weight
Made of plain concrete or stone masonry
Trapezoidal in section with the base projecting beyond the face and back of wall
No tensile stress in any portion of wall.
Economically used for walls less than 6 m high
Cantilever walls
July 2013 47
Design of diversion weir, canal and small dams
July 2013 48
Design of diversion weir, canal and small dams
The usual practice in the design of the retaining wall is to assign tentative dimensions and check
for the overall stability of the structure. Accordingly the dimensions of retaining wall are
determined as per the recommendation given below for gravity retaining wall and thereafter the
stability analysis will be carried to check whether the dimension is sufficient from stability
consideration.
July 2013 49
Design of diversion weir, canal and small dams
A system of irrigation canals, also known as a ‗canal network‘, transports water from its source
to the fields, and is made up of many canals.
Irrigation canal can be classified in a number ways;
1. Classification based on alignment:
(i.) Contour canal: Contour canal follows a contour, except for giving the required longitudinal
slope to the canal. A contour canal irrigates only on one side because the area on the other
side is higher. As a drainage flow is always at right angle to the contour, such a canal would
definitely have to cross a natural drain and stream, necessitating the construction of cross-
drainage structure.
(ii.) Watershed (ridge) canal: The canal which is aligned along any natural watershed (ridge line)
is called watershed canal or ridge canal. Along a canal on the ridge, ensures gravity
irrigation on both sides of the canal. Moreover, since the drainage flow away from the ridge,
no drainage can cross a canal aligned on the ridge. Thus, a canal aligned on a watershed
saves the cost of construction of cross-drainage works.
(iii.) Side slope canal: Canal aligned at right angles to the contours but not on a watershed or
valley. Since such a canal runs parallel to the natural drainage flow, it usually doesn‘t
intercept the drainage channels, thus, avoiding the cross-drainage structures.
2. Classification based on size:
(i.) Primary canal (main canal) is a canal which conveys water from the source to the command
area. This canal usually terminates at the end of the command area or may split into several
secondary canals somewhere in the command. In some instances, the flow in a primary
canal may be supplemented from another source. The canal delivering this supplemental
flow is known as a feeder canal.
(ii.) Secondary canal is the canal which conveys water from the primary canal (main canal) to
the tertiary units or, in small schemes, directly to the farmers' fields through an outlet
structure.
July 2013 50
Design of diversion weir, canal and small dams
(iii.) Tertiary canal is a canal which feeds a tertiary unit and conveys water from the secondary
canal to the quaternaries. Tertiaries may also convey water directly to the fields in a small
system.
(iv.) Quaternary canal is channels which conveys water to field channel or directly to the farmers.
(v.) Field channels are channels which convey water to farmers' fields from the quaternary canal.
In the case of hill irrigation project, they may be filled directly from the secondary or tertiary
canal.
Figure 3-1 Layout of irrigation system with five level hierarchy of canal
The purpose of canal system design is to provide water, adequate in quantity and command to all
farms within the area serviced. The system should be convenient to operate & should blend with
the pattern of farming.
The distribution system of an irrigation scheme is defined as the network of canals (or pipes) and
associated structures which convey water from the source works to the cropped areas in a
controlled way. Many schemes have a drainage system, complementary to the distribution
system, for removal of surplus water, particularly excess rainfall and canal escape flows. The
objectives of the distribution system operation are to deliver the right amount of water to the
July 2013 51
Design of diversion weir, canal and small dams
right place, at the right time to meet crop needs. Ideally, water should be distributed equitably
among farmers according to their needs.
Layout is defined as the arrangement of canals, drains and structures required to achieve the
water distribution objectives and to remove surplus water. The objective of layout planning is to
establish the optimum arrangements, positions and levels of channels and structures to ensure
satisfactory distribution and drainage at an acceptable cost, while taking account of the physical,
technical and social constraints.
The planning and layout of an irrigation system/canal design is dictated by the area to be
irrigated and the source of supply. It is influenced also particularly by agricultural, engineering
and economic characteristics of the area. In addition, existing land use practices and the socio-
economic conditions of the area need to be considered.
It is also true that for efficient water management practice and economical implementation of
any irrigation scheme, the judicious design of the layout system is an imperative. A modern
irrigation scheme will have a network of irrigation canals, drainage channels, access roads, flood
protection & in certain circumstances, cattle corridors.
General Alignment and layout procedure/principle
The following are the general alignment and layout procedures to be followed
Survey maps shall be prepared to different scales according to the size of the project:-produced
preferably to a scale of 1:1000 or 1:2000 - 1:2500 for small scale projects and 1:2000 or
1:5000 - 1:10,000 for medium scales showing the contours, spot levels & important land
features for the whole project area.
Alignments of all canal grades (main, secondary, tertiaries etc) shall be marked on the map.
Align main canal as a contour canal wherever possible and secondary and tertiary are to be
aligned as watershed or side slope canals.
The main canal should be generally carried on a contour alignment, until either it commands
the full area to be irrigated or it attains the top of a watershed. From such a point, it should be
aligned down to the watershed ceasing to be a contour canal.
Secondary canals and tertiaries should take-off from a canal or near the points where the canal
crosses watershed.
Taking in mind of the economic considerations, deep cuttings or high embankments should be
generally avoided by suitable detouring, after comparing the overall costs of the alternative
July 2013 52
Design of diversion weir, canal and small dams
July 2013 53
Design of diversion weir, canal and small dams
A canal should divert from a supply source at a position of sufficient elevation to reach the
land to be under irrigation by providing proper gradients & using most economic route. At
turnouts, the canal water surface must be high enough to permit irrigation of the land located at
far end and the higher patch of the lower area.
Find out those reaches which require lining (if any), and choose practical & economical ones.
Maintain as far as possible, the full supply water level in the lined and unlined lengths within
the same reach.
July 2013 54
Design of diversion weir, canal and small dams
July 2013 55
Design of diversion weir, canal and small dams
July 2013 56
Design of diversion weir, canal and small dams
Ideally, unlined canals are designed to be non-silting (when conveying sediment laden water),
and to be non-scouring when carrying silt free water. These requirements impose limitations on
the choice of water surface slopes, and also affect the shape of the cross section.
Unlined trapezoidal shaped canals are the most common and economic solution in most
irrigation schemes in whatever terrain situation. Ideally, canal sections should be chosen so that
July 2013 57
Design of diversion weir, canal and small dams
the construction and maintenance costs are minimized, while erosion and sedimentation
problems are contained.
July 2013 58
Design of diversion weir, canal and small dams
4. Water carrying sediment in lined canals. The design For sizing: Manning equation
is governed by the need to ensure the sediment load For sediment transport: Engelund and
that can be transported. Hansen equations.
Manning’s equation
The manning equation is recommended for the design of unlined canals (flat terrain) up to 5
m3/s; for steep canals of non-erodible type and channels conveying clear water and also for lined
canals.
The equation is:
√
Where
V = velocity (m/s)
Q = discharge (m3/s)
A = area of the flow (m2)
R = hydraulic radius (m)
= A/P
P = the wetted perimeter (m)
S = water surface slope
n = roughness coefficient
( )
( ) ( ) ( )
√( ) √
( )
√
b = bed width of the canal
d = water depth of the canal
Side slope = 1: Z (V: H)
July 2013 59
Design of diversion weir, canal and small dams
T = top width
The principle decisions to be made are:
The choice of roughness coefficient,
The choice of slope
The section shape
(I.) Roughness
The choice of roughness coefficient is best made from measurements of existing, similar
channel. However such data are rarely available. The best way in choosing roughness coefficient
is to measure existing similar channels. However, such data is hardly attainable, and in practice a
choice has to be made based on experience. In theory the coefficient will depend on:
The shape & size of canal surface particles;
The canal surface irregularities (e.g. due to poor canal construction resulting in changes
in wetted perimeter and cross section);
Vegetation on canal bed and side slopes;
Variations in channel cross-sections, i.e. whether gradual, varying frequently or
occasionally,
Relative effect of obstructions in the canal, whether negligible, minor or severe,
Degree of meandering, whether, minor, appreciable or strongly developed.
July 2013 60
Design of diversion weir, canal and small dams
(II.) Slope
The choice of slope in a channel designed using manning's equation will depends on the non-
scouring and non-silting limitations. The minimum slope shall be set to provide reasonable
minimum velocity to prevent weed growth and to transport the anticipated sediment load. To
provide a degree of flexibility, the usual practice is to allow a choice in the range set by the
above limiting conditions. Therefore, for determining channel bed slopes, the velocities should
be checked and the maximum grade designed velocity shall not exceed the limits given in Table
3-4.
July 2013 61
Design of diversion weir, canal and small dams
In hilly areas, wide sections are not usually feasible particularly for primary canals, and a narrow
section has to be used. However, this is not usually so critical since canal capacities are generally
small.
The shape of the trapezoid is determined by:
bed width;
depth of flow;
the side slopes;
The side slope of the canal depends mainly on the material in which it is cut and of which its
banks are made. To limit excavation & expropriation (land acquisition) costs, side slope are
usually designed to be as steep as possible according to the soils, and whether the canal is in cut
or in fill. For erodible soils, the slopes should be checked against criterion of the maximum
allowable velocity or by the principle of tractive force. Other factors including the method of
construction, depth of canal & the level of ground water table are among others to be considered
in canal slope selection.
Based on similar countries experience referred in the literatures of similar conditions of terrain
conditions (Nepal & India) to Ethiopia, recommended side slopes are presented in Table 3-5.
Recommendation on bed width to depth ratios for canals design using Manning's equation are
given in Table 3-6.
July 2013 62
Design of diversion weir, canal and small dams
Note: These values may be affected by the water table condition and moisture condition. Values
in the table above are given assuming low moisture content & water-table below canal bed. The
slopes need to be flattened if these conditions are unachievable.
When a bed width to depth ratio (K) is used, the Manning formula can be simplified as:
( )
* √ +
Where K = b/d
Z = side slope
For given K & Z, these equations become:
( )
[ √ ]
( ⁄ )
√ ⁄
Once K4 has fixed, it is relatively easy to solve the equation for varying values of S & D.
July 2013 63
Design of diversion weir, canal and small dams
Example
Determine the section of an earthen canal (width and depth) in a hilly terrain conveying a
discharge of 100 l/s. The soil along the alignment of the canal is loam soil. The longitudinal
slope of the canal is 0.001.
Solution
The value of n for a canal in a hilly terrain, n= 0.025 (From Table 3-3)
The maximum allowable velocity of water for Loam soil is 0.63m/s. (from table 3-4).
Free board = 0.3 m (from table3-7)
The recommended b/d ration for discharge of 0.1 m3/s in a hilly terrain is 1.0 from Table 3-6.
Hence b/d = 1 and therefore K=1
The suggested side slope for loam type of soil is 1:1 to 1:5 from Table 3-5. Let us take a side
slope of 1:1.
Z=1
From the foregoing equations;
( )
* √ + * √ + [ √ ]
( ⁄ ) ( ⁄ )
⁄ ⁄
√
The formula for the depth from this equation becomes;
July 2013 64
Design of diversion weir, canal and small dams
In designing canal cross-sections in hill areas the following points should be borne in mind:
Canal should be in cut wherever possible, or at least with design water level below
ground level. Fill section should be where absolutely necessary. If the excess material is
used for banks, these should be adequately compacted. Surplus material should not be
dumped, but placed in a site carefully chosen to avoid any likehood of instability
For deep cuts, berms should be provided at a minimum of every 2 m depth & 5 m depth
for small and medium scale projects respectively.
Canal banks should be designed with a suitable seepage gradient, if the canal is not lined
or in rock.
For main canals, an access track way should be provided along the whole length,
typically 2-3 m wide. A path way of 1 m width is commonly provided along distribution
canals.
July 2013 65
Design of diversion weir, canal and small dams
Canal Losses
In principle, irrigation canals are to be partly excavated in natural ground and partly constructed
above the natural ground to hold the required quantity of irrigation water.
The canal section is never made 100% water tight. Thus, the water seeps into the ground and also
evaporates from the canal surface to the atmosphere. In general terms, irrigation water, when
taken in the canal system for conveying it to the fields, is liable to be lost in various ways. The
two major water loss ways are through evaporation, and seepage.
Losses Due to Evaporation
July 2013 66
Design of diversion weir, canal and small dams
In most of the cases (except very hot ones) evaporation loss is insignificant. The range of canal
water loss through evaporation is estimated to be from 0.25% to 1% of the total canal water. The
factors that determine the rate of loss of water in the process of evaporation include:
Temperature of the region,
Prevailing wind velocity of the area,
Humidity, and
Area of water surface exposed to the atmosphere.
Generally it could be inferred that the loss due to evaporation is directly dependent on the
climatic conditions of a region. It is also directly dependent on the exposed water surface area &
inversely dependent on the depth of water in the canal.
Due to Seepage
Seepage losses are primarily dependent on the type of soil from which the canal is constructed.
These losses are expressed in m3/s per million square meters of wetted perimeter. In our
country's case, the following guidelines may be adopted.
Table 3-8 Seepage canal losses values for different soil canal routes
Soil type Seepage losses m3/s per
km2 of canal surface
Impervious clay loam 0.8 - 1.20
Medium clay loam 1.20 - 1.70
Clay loam or silty soil 1.70 - 2.70
Gravelly clay loam or sandy clay or gravely cemented with clay 2.70 - 3.50
Sandy loam 3.50 - 5.20
Sandy soil 5.20 - 6.40
Sandy soil with gravel 6.40 - 8.60
Previous gravelly soil 8.60 - 10.40
Gravel with some earth 10.40 - 20.80
Generally used formula to compute losses through seepage is total losses through seepage in
reach (m3/s) = S x P x L/106
July 2013 67
Design of diversion weir, canal and small dams
Curves radii are required to be determined for roads and canals equally. Service roads are
provided on the banks of primary & secondary canals and may determine canal radii. The radius
of service roads depends upon the type of vehicles or equipment to be used on the roads. It is
recommended to adopt 15 m curve radius & 20 m curve radius for 4 & 5 m wide service roads
respectively.
July 2013 68
Design of diversion weir, canal and small dams
Embankments
If a canal is in cut the size of the embankment is often determined by the amount of spoil to be
disposed of. The width of top of the bank depends on the type of soil from which the canal is to
be constructed, flow capacity, canal type (earth, lined/or both), the seepage gradient & the width
of service road to be provided.
It is usual to specify minimum heights and widths for the embankments so that a reasonable road
is formed. Where the spoil is in excess of this minimum amount of material required, and cannot
be used elsewhere, the embankment may be either raised or widened. The disadvantage of
widening the embankment is that a greater reservation is required and where space is restricted
this may be important.
Bank widths of 3 to 6 m are required where service roads are provided for small & medium
canals with surface roads. It is better to provide, the bank widths of 2 to 3 m along the main canal
& 1 m within the distribution canals of steep area canals.
Where embankments are in fill with canal water level above natural ground level, the seepage
gradient needs to be considered for the stability of the embankment. In such cases the bank width
should be sufficiently wide to retain the seepage gradient below the toe of the outer face of the
bank.
Seepage gradients vary from 1:3 for clay soils to about 1:7 for alluvial soils. Table 3-10 shows
the recommended values of seepage gradients to different soil types. Similarly Table 3-11 shows
the recommended minimum embankment widths for canals of different capacities.
July 2013 69
Design of diversion weir, canal and small dams
Canal embankment may be damaged by rainfall due to direct impact on bare-slopes or by surface
runoff. Gullies or other forms of erosion will occur if the slopes are not grassed. Newly
excavated canals in hilly are easily eroded due to steep slopes, and gullies are formed rapidly
when rainfall is severe. The banks on the downhill sides are also subject to sever erosion if the
surface is not covered by turfs, or other covering materials. Similar problems occur in a canal in
plain terrain although the magnitude is less.
July 2013 70
Design of diversion weir, canal and small dams
Different conditions require different type of lining. The availability of materials also dictates the
choices. There are four broad classification of lining:
Hard surface lining, such as concrete, (in-situ or precast), brick, burnt clay tile, shortcrete,
asphalt and masonry.
Buried & protected membrane linings, such as sprayed in place asphalt, synthetic rubber
and plastic film.
Earth linings, such as thick or thin compacted earth or soil cement.
Dry linings, of limited use in preventing seepage losses, but used where surcharge
pressures create unstable soil conditions. Dry stone and brick pitching (with appropriate
filter bedding) is often used.
Recommended linings that could be used in Ethiopian condition are given in Table 3-12. The use
of these linings will depend very much on the availability of local material in the vicinity of the
anticipated project.
July 2013 71
Design of diversion weir, canal and small dams
I. Stone/Brick Masonry
Stone masonry has better wearing qualities than brick masonry and is preferred where local stone
is available. With carefully pointed joints, good water tightness can be achieved.
Typical thickness of stone/brick masonry is 0.2 to 0.4 m. 1:4 cement mortar is commonly used.
II. Concrete
Concrete linings can be laid in situ or be precast. Concrete lining provides effective hydraulic
sections, but are generally an expensive to construct.
The success of in-situ concrete depends largely on the sub-grade materials and the need to
provide a stable foundation. Sub-grades should therefore be compacted, and if there is any
danger that the sub-grade will swell or shrink under changing moisture conditions, alternative
linings should be used. Problems are especially likely where canals are constructed in fill. In-situ
linings may be laid by hand or by paver. Compaction of the concrete on the sides of the canal can
be difficult.
Joints for concrete shrinkage and sub-grade movement need to be provided to counteract
cracking. Cracking may be avoided by providing reinforcement, but this tends to make the lining
uneconomical.
Typical thickness of in situ concrete lining ranges from 75 mm to 150 mm.
Precast concrete are usually laid as rectangular slabs with rebated edges. The joints are filled
with mortar or bituminous mastic. They provide greater flexibility than in-situ concrete and can
withstand more movement, although the joints will crack. They generally require more labour to
cast and lay them, but the thickness can be reduced usually to 50 mm to 100 mm. The sub-grade
on which the slabs are to be laid requires careful preparation. They are often used in conjunction
with a buried membrane to ensure water tightness.
Normal steel reinforcement has these days been widely accepted and 0.25 to 0.3% of concrete
adds practically nothing to the structural strength of uncracked lining. But it has been found that
reinforcement reduces the width of shrinkage cracks, thereby reducing seepage and prevents
July 2013 72
Design of diversion weir, canal and small dams
possible faulting of the cracked slabs where unstable sub grades are encountered. Transverse
expansion and contraction joints can be avoided by providing longitudinal steel with
reinforcement of about of 0.5% and transverse steel reinforcement of about 0.25% of the cross-
sectional area of concrete.
III. Dry Stone/Brick Lining (Pitching)
This is used not to prevent seepage, rather to protect erosion and bank stability. It requires to be
placed on gravel/sand filter backing, to prevent fine materials being washed out from the
underlying sub grade. The typical thickness is 0.2 to 0.3 m.
IV. Shotcrete
Shotcrete is a specially proportioned concrete mixture, which is applied using pneumatic
equipment to force the mix on to and into the surface being lined. They are used for bank
stability and seepage prevention in fractured rock zones of steep terrains canals. The plant used
for the application of shortcrete is reasonably small and portable.
Thickness to be used is 25 to 50 mm. For steep side slopes (steeper than 1:1.5), it may be
required to provide a wire mesh reinforcement to prevent the fresh concrete from slumping.
V. Earth Lining
Earth lining are principally used to prevent seepage, since they offer no savings in canal section,
nor does it provide stability.
Suitable material for earth linings are inorganic clays of low to medium plasticity, sandy clays,
silty clays and lean clays.
Where suitable materials are locally available, earth lining is the cheapest form of lining for
seepage limitation. Earth linings are usually compacted and are classified thick linings (0.3-1.0
m) or thin linings (0.15 to 0.3 m). Thick compacted earth linings are preferred for several
reasons, including easier construction, better erosion resistance and better to damage during
maintenance. In practice, thick linings have been shown to be more economical than thin linings
in the long term, due to difference in the cost of maintenance. Thin lining are also susceptible to
damage caused by wetting and drying (e.g. in canals operating on rotation). For these reasons
thin earth linings are not recommended.
VI. Buried Membrane Linings
They are used only to reduce seepage, since as with earth linings, they offer no other advantages.
There are a number of membranes which are commonly used for lining canals. These include:
July 2013 73
Design of diversion weir, canal and small dams
July 2013 74
Design of diversion weir, canal and small dams
The maximum average velocity which linings of particular types can withstand are given in
Table 3-13 alongside recommended values of roughness coefficient ―n‖ for use in Manning‘s
equation.
July 2013 75
Design of diversion weir, canal and small dams
√
( ⁄ )
July 2013 76
Design of diversion weir, canal and small dams
Canals using earth or buried membrane linings will be designed as unlined canals.
For hard surface linings, the objective is to minimize the lining perimeter, since lining is the
greatest proportion of the canal cost. In practice, however, higher ratios are adopted for
convenience of construction and maintenance.
Some of the values recommended are presented in Table 3-15.
July 2013 77
Design of diversion weir, canal and small dams
Table 3-16 Recommended freeboard values for hard surface lined canals
Status Discharge m3/s Total Freeboard (m) Lining Freeboard
(m)
Small scale projects < 0.1 0.2 0.1
0.1 - 0.5 0.3 0.15
0.5 - 1.0 0.4 0.2
Medium scale 1.0 - 2.0 0.5 0.2
projects 2.0 - 3.0 0.55 0.25
3.0 - 5.0 0.60 0.3
Medium to large scale 5.0 - 10.0 0.70 0.35
projects 10 - 30 0.8 0.4
> 30 1.0 0.5
(d) Embankments
In principle, bank top widths for lined canals are not different from those for unlined canals.
Clearly, there is no need to design canals with impermeable linings against a seepage gradient,
and this may allow narrow banks. However, in some cases the construction techniques may
depend on width. For example; if a concrete paving machine is to be used, a minimum bank top
width (road) will be required for the paver to run on and to be serviced with concrete. This width
could be 3 to 4 m for small scale (canals) projects, up to 5 or 6 m for medium scale (larger
canals) projects.
With this expectation noted, the bank top widths should follow recommendations for unlined
canals. A berm of 0.2 to 0.5 m is sometimes provided at lining top level for conveniences of
construction. However, it is not always essential..
At the connection between the lining and earth embankment, the joint should be strengthened by
embedding the edge of lining inside the bank to a reasonable length (0.15 m to 0.3 m depending
on canal size).
For canals in fill, the material placed in the embankments need to be specially compacted to
support concrete linings
July 2013 78
Design of diversion weir, canal and small dams
Canals of steep slopes, masonry lining is usual, and the masonry edge should be embedded into
the hill slope from a depth of 0.5 m to 1.0 m depending on the canal size. On the downhill the
lined section is embedded in the earthen bank by 0.3 to 0.5 m.
Grassing or turfing is provided just above the lining to protect against soil erosion & gully
formation. Catch drains to divert rain water are provided on the uphill side of the hill canal.
These catch drains are connected to the nearest natural drains.
Similarly, recommendation on service roads and side drains for unlined canals also apply to lined
canals.
(e) Lining Thickness
The lining thickness depends on the type of lining and size of the canal. Table 3-17 summarizes
lining thickness for different materials and applications.
July 2013 79
Design of diversion weir, canal and small dams
Earth lined canals and buried membrane lined canals should follow the guidelines set out for
unlined channels.
Lined canals can a much tighter radius of curvature since they are protected against bank erosion.
As with unlined canals, radii may be determined by the radii of the associated service roads.
Where there are no constraints, a radius of 3 x surface width is recommended. If it is necessary to
use a tighter bend, special measures should be considered, particularly for fast flowing canals.
(g) Back Pressures on Lining
The stability of hard surface lining needs to be carefully checked if there is a danger of
groundwater pressure behind the lining. If the canal is drowned in such cases, the lining will fail.
Groundwater tables rise during the wet season and account should be taken of this when carrying
out investigations of the water table in the dry season.
If there is a danger of water pressure occurring behind the lining, under drainage needs to be
provided.
The key factors in assessing the possibility of the failure are:
the position of the water table, and its seasonal variation
the permeability of the sub-grade,
the likelihood of drawdown in the canal
The permeability of the soil is important, since if the canal construction material is poorly
drained, a temporary water pressure may exist, even if the water table is low, when the canal is
suddenly emptied. For permabilities greater than 10-6 m/s (clean sands/gravel) there should be no
problem, since the soils are relatively quick to drain. For permeabilities less than this (clayey
sands, silty/sandy/clayey mixture, clays) the provision of under-drainage needs to be considered.
(Although it is noted that if the soils are clayey there should be no need of lining for seepage
control).
Drainage can be provided in several ways:
by providing longitudinal drains under the lining discharging to natural drainage channels
or at suitable points into the canal via valves
by providing pressure relief valves in the bottom and/or sides of the canals at frequent
intervals, typically 5m spacing
by providing weepholes at frequent intervals in the bed side of the canal
Typical Cross Sections
July 2013 80
Design of diversion weir, canal and small dams
Typical cross-section for a variety of canals and different linings are presented in Figures 3-3to
3-7.
Figure 3-3 Masonry canal lining (in area with back water pressure problem)
July 2013 81
Design of diversion weir, canal and small dams
July 2013 82
Design of diversion weir, canal and small dams
REFERENCE
July 2013 83
Design of diversion weir, canal and small dams
ANNEXES
Annex-1 Hydrology
Rainfall
July 2013 84
Design of diversion weir, canal and small dams
Intensity-Duration-Frequency
Regions A1 & A4
Figure 5-9
400,0
350,0
300,0
250,0 2 Year
Intensity, mm/hr
5 Year
10 Year
200,0 25 year
50 Year
100 Year
150,0
100,0
50,0
0,0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Duration, min.
July 2013 85
Design of diversion weir, canal and small dams
Intensity-Duration-Frequency
Regions A2 & A3
Figure 5-10
400
350
300
250 2 Year
Intensity, mm/hr
5 Year
10 Year
200 25 year
50 Year
100 Year
150
100
50
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Duration, min.
July 2013 86
Design of diversion weir, canal and small dams
Intensity-Duration-Frequency
Regions B, C & D
Figure 5-11
400.0
350.0
300.0
250.0
2 Year
Intensity, mm/hr
5 Year
200.0
10 Year
25 year
150.0 50 Year
100 Year
100.0
50.0
0.0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
July 2013 87
Duration, min.
Design of diversion weir, canal and small dams
Intensity-Duration-Frequency
Bahir Dar & Lake Tana
Figure 5-12
400,0
350,0
300,0
250,0 2 Year
Intensity, mm/hr
5 Year
10 Year
200,0 25 year
50 Year
100 Year
150,0
100,0
50,0
0,0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Duration, min.
July 2013 88
Design of diversion weir, canal and small dams
July 2013 90
Design of diversion weir, canal and small dams
July 2013 91