Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Method Statement

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 93

Provision for Engineering Design,

Construction and Installation of


Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

SECTION 3 – PROJECT EXECUTION PLAN


_______________________

17th November 2023

PROJECT EXECUTION PLAN 1


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Appendix A1 – PROJECT EXECUTION PLAN


Project Management
1. Tenderer shall identify the critical success factors that, in its opinion, will be crucial to the
successful implementation of this project. Tenderer shall explain how its overall organisation, and the
organisations of other parties i.e. NewcrossEP, design contractor, sub-contractor etc shall function in
order to achieve these critical success factors. (Ans: Sections 2.1, 2.3 .3--9.)

2. Tenderer shall identify specific project challenges in addition to those already identified by
NewcrossEP and recommend how it will pro-actively manage these challenges. (Ans : Section 2.2)

3. Tenderer shall provide evidence of the successful completion of similar projects in terms of
complexity and location, stating project value and provide evidence of completion within the
contractual schedule, budget and HSE targets. Tenderer shall describe how any project learnings will
be incorporated within this project. (Ans : Section 2.4.1)

4. Tenderer shall provide an outline of its proposed execution strategy for this project. This strategy
shall address multiple work locations. (Ans : Section 2.6)

5. Tenderer shall identify how it would execute site work, including interface management with
engineering, vendor activity, and fabrication yards and construction sites, considering social,
geographical and meteorological conditions. (Where this information has been submitted as a part of
Appendix A13 – Interface Management Plan, please ensure that your submission fully covers this
requirement and cross references Appendix A1). . (Ans: Sections 1-9)

6. Tenderer shall describe the planning, progress monitoring, cost review and reporting methods that
would be used to control the work within the agreed project schedule and contract value. (Where this
information has been submitted as a part of Appendix A3 – Detailed Programme, please ensure that
your submission fully covers this requirement and cross references Appendix A1). (Ans : Section 4.8)

7. Tenderer shall provide its plans and procedures to be adopted for technical/integrity reviews and
audits. Ans : Section 2.6)

8. Tenderer shall describe its systems for tracking recommendations from audits and reviews and
provide evidence of the systems effectiveness. (Ans : Sections 4.9.8., 4.10)

9. Tenderer shall demonstrate that its quality management system requires preparation of a project
closeout report as part of the “plan-execute-analyse-improve” loop. Tenderer shall provide a copy of a
project closeout report from between 2018-2021 for a similar oil and gas facilities project. This shall
include client references and endorsements. (Where this information has been submitted as a part of
Appendix A18 – Quality Management Plan, please ensure that your submission fully covers this
requirement and cross references Appendix A1). (Ans Section 4.10)

10. Tenderer to provide its contract mobilisation plan, this shall be linked to the overall project
schedule (Ans sections 4.3, 4.3.1- 4.3.3)

PROJECT EXECUTION PLAN 2


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Engineering
1. Where Tenderer proposes to use an engineering sub-contractor, Tenderers shall provide
evidence of agreements such as a memorandum of understanding. Tenderer shall provide
adequate supporting information to allow NewcrossEP to assess suitability of the proposed
engineering sub-contractor (Not applicable).

2. Tenderer shall propose a method statement for execution of engineering activities,


identifying any special studies to be conducted and how it intends to outsource and manage
them. Ans: sections 5.0(5.1,5.11, 5.1.1.1-5.1.1.5)

3. Tenderer shall describe the engineering software it proposes to use for the execution of
the project, as a minimum, the following shall be addressed: - Ans (section 5.1.1.3)

• 3D Models
• Drawings drafting;
• Architectural design and drawings from FEED drawings
• Civil / Structural Design, Structural Design Analysis Full Package from the
foundations
• (piling) to superstructures
• Geotechnical Investigation to obtain engineering properties of sub-soil
• • Process Engineering and Design Basis for water treatment facilities•
• Process Engineering and Design Basis for sewage treatment facilities
• Hydraulic (Pressure Profile) Studies, Steady State Process Simulations
• Corrosion Studies: Materials / Corrosion Engineering activities and deliverables
• Complete Mechanical Design
• Instrumentation and Control System Design
• Electrical Engineering Design
• Telecommunication
• Quality control systems;
• Information and data management system;

4. Tenderer shall confirm ownership of valid licences for the nominated software.
Additionally, Tenderer shall provide a list of its registered users, together with a statement of
the registered users experience and expertise. Ans:Refer to attachment 2.4.3

5. Tenderer shall detail the number, nature and phasing of design reviews that will be
conducted during the execution of the work, including the mandatory design reviews
Tenderer shall provide a copy of its quality procedure governing the review process.
Ans(items 8,12,15 16) of section 2.5

6. Tenderer to describe its systems for review and tracking of Engineering and construction
Changes during design both architectural and engineering design; and
construction/installation phases of the project..

PROJECT EXECUTION PLAN 3


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

7. Tenderer to provide listing of Projects COMPLETED in the past five years,


including for each project: • Name of the client, contact person and contact details. Ans
(Refer to sections 2.4.1 and 2.4.2)

Contract title.
• A brief description of the scope. (with specific mention of any Hot Tap works carried out
and the processes employed)
• Terrain description and state locations where each phase of the project was executed.
• Challenges encountered (Technical, Commercial, and Installation).
• Date of award (mm/yyyy).
• Total Contract value (FUS$ million).
• Project duration (months).
• Copies of Completion Certificates.
• Description of the staff levels for the various project phases:
▪ Engineering
▪ Procurement and Logistics.
▪ Construction.

PROJECT EXECUTION PLAN 4


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Contents
1.0 INTRODUCTION.....................................................................................................................................8
1.1 PROJECT BACKGROUND..................................................................................................................8
1.2 PROJECT OBJECTIVES.......................................................................................................................8
1.3 DEFINITIONS AND ABBREVIATIONS............................................................................................9
2.0 TASKS OF PROJECT EXECUTION PLAN......................................................................................10
2.1 Critical Success Factors (1)..................................................................................................................11
2.2 Potential risks/Disablers/Specific Project challenges ( 2)....................................................................11
2.3 Critical Schedule Activities ( 2)...........................................................................................................12
2.4 Evidence of Successful Completion of Similar Projects ( 3)...............................................................12
2.5 Outline of proposed execution strategy for this project (4)..................................................................13
2.6 Project Reference Documents (Plans and Procedures) (7).................................................................13
During execution of the project, contractor shall use all but not limited to the following referenced project
specific procedures and plans listed below:...........................................................................................................13
2.7 Applicable Codes, Standards and Regulations.....................................................................................14
2.8 New Cross Exploration and Production Limited Standard Specifications & Philosophies.................14
3.0 PROJECT MANAGEMENT SYSTEM(6)...........................................................................................15
3.1 OVERVIEW OF PROJECT MANAGEMENT SYSTEM..................................................................15
4.0 PROJECT EXECUTION STRATEGY (METHODOLOGY)...........................................................18
4.1 AWARD OF THE CONTRACT.......................................................................................................19
4.2 KICK OFF MEETING.......................................................................................................................19
4.3 MOBILIZATION(10).........................................................................................................................20
4.3.1 Mobilization of Manpower – Phase – I.........................................................................................20
4.3.2 Mobilization of Manpower – Phase – II.......................................................................................21
4.3.3 Mobilization of Manpower – Phase – III.........................................................................................21
4.4 GENERAL ACTIVITIES WORK APPROACH.................................................................................23
4.4.1 Engineering......................................................................................................................................23
4.4.2 Construction.....................................................................................................................................24
4.4.3 Procurement....................................................................................................................................27
4.4.4 Fabrication........................................................................................................................................28
4.5 PROJECT MANAGEMENT ORGANIZATION................................................................................31
4.5.1 Organisation/Roles and Responsibility/Communication.................................................................32
4.6 SUBCONTRACT PLAN.....................................................................................................................36
4.7 TRANSPORTATION PLAN...............................................................................................................36
4.8 PROJECT CONTROL(6).....................................................................................................................37

PROJECT EXECUTION PLAN 5


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.8.1 Schedule...........................................................................................................................................37
4.8.2 Progress Measurement.....................................................................................................................38
4.8.3 Productivity Analysis.......................................................................................................................39
4.8.4 Progress Reporting...........................................................................................................................39
4.9 OCCUPATIONAL HEALTH & SAFETY..........................................................................................41
4.9.1 Contractor Health, Safety and Environment (HSE) Program..........................................................43
4.9.2 Personnel Protective Clothing and Safety Accessories....................................................................43
4.9.3 Dedicated Safety Officer..................................................................................................................44
4.9.4 Admission to the Jobsite, Safety Induction Course..........................................................................44
4.9.5 Reporting of Unsafe Situations, Incident/Accident..........................................................................44
4.9.6 Safety Walks....................................................................................................................................44
4.9.7 Joint CONTRACTOR / COMPANY Audits...................................................................................44
4.9.8 CONTRACTOR Internal / Line Supervisors Audit.........................................................................44
4.9.9 Toolbox Meetings............................................................................................................................45
4.9.10 Incentive Scheme.........................................................................................................................45
4.10 QUALITY MANAGEMENT PROGRAM (9)....................................................................................46
4.10.1 CONTRACTORs Quality Assurance and Quality Control (QA/QC) Program..........................46
4.11 DOCUMENT CONTROL MANAGEMENT......................................................................................48
4.11.1 Document Deliverables/Activities...............................................................................................49
4.11.2 DCC Software Requirement:.......................................................................................................49
4.11.3 DCC Electronic File Transfer:.....................................................................................................49
4.11.4 DCC Quality System...................................................................................................................49
4.12 INFORMATION TECHNOLOGY MANAGEMENT........................................................................50
4.13 COMMUNICATIONS.........................................................................................................................50
4.14 INTERFACE MANAGEMENT..........................................................................................................50
4.15 RISK MITIGATION............................................................................................................................51
4.16 SECURITY...........................................................................................................................................51
4.17 SUSTAINABLE COMMUNITY DEVELOPMENT..........................................................................52
4.18 NIGERIAN CONTENT PLAN............................................................................................................52
4.19 TRAINING AND TECHNOLOGICAL TRANSFER.........................................................................53
5.0 ENGINEERING(Method statement for execution of engineering activities)(1).............................54
5.1 Approach to Work................................................................................................................................54
The execution of detail engineering design shall be executed by Makais Synergy Limited. Makais synergy is
an Indigenous ISO 90001 company. Makais has executed several Engineering Procurement and Construction
(EPC) projects for several companies as follows:..............................................................................................54
5.1.1 Development of Detail Engineering Design....................................................................................54

PROJECT EXECUTION PLAN 6


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Deliverables.......................................................................................................................................................68
For Architectural..............................................................................................................................................68
Architectural Design Drawings for all the proposed buildings..........................................................................68
For Civil/Strutural...........................................................................................................................................68
Software Requirements...................................................................................................................................69
IT Requirements...............................................................................................................................................70
IT Requirements...............................................................................................................................................71
Execution Methodology...................................................................................................................................72
Deliverables.......................................................................................................................................................72
Software............................................................................................................................................................72
Deliverables:.....................................................................................................................................................73
For instruments:...............................................................................................................................................73
For Telecommunication...................................................................................................................................73
Software Requirement.....................................................................................................................................73
Software Requirements...................................................................................................................................74
6.0 PROCUREMENT MANAGEMENT....................................................................................................75
6.1 Material Expediting..............................................................................................................................75
6.2 Delivery, Packing and Shipment..........................................................................................................76
7.0 CONSTRUCTION..................................................................................................................................76
7.1 Construction Mobilisation....................................................................................................................76
7.1.1 Civil Facilities..................................................................................................................................77
7.1.2 Mechanical Facilities........................................................................................................................77
7.2 Construction Management....................................................................................................................79
7.3 Construction Resources & Subcontracts..............................................................................................79
7.3 Construction Procedures.......................................................................................................................79
7.4 Construction Camp & Site Facilities....................................................................................................79
7.4.1 Pre-Inspection & Calibration................................................................................................................79
7.5 Subcontract Strategy.............................................................................................................................81
7.6 Structural Works...................................................................................................................................81

PROJECT EXECUTION PLAN 7


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

1.0 INTRODUCTION

1.1 PROJECT BACKGROUND

NewCross Exploration and Production Limited and NNPC Upstream and Investment
Management Services (NUIMS) plan to carry out the Engineering, Construction, Installation
and Rehabilitation of the civil Infrastructures at Ekulama 1&2, and Awoba Flowstations in
OML 24.
The proposed staff accommodation would cater for a staff capacity of about 100 personnel
comprising:
a) Three (3) sets of accommodation building with 20 bedrooms and a reception/common
room attached to each building.
b) One (1) Restaurant building.
c) One (1) Technical building.
d) One (1) Recreation building.
e) One (1) staff complex gate house
f) Fencing of the staff complex
g) One (1) Warehouse-workshop building.
h) Staff complex portable water installations.
i) Sewage treatment plant and overhead tank/facilities at the staff complex/accommodation
j) Jetty and Access Roads to and within the accommodation quarter
k) Drainage and culvert for the residential access road etc
l) Sand filling and piling works for the staff complex structures.
m) Outdoor games center.
Rehabilitation work is also proposed for the attendance accommodation (building) and shore
protection structures at Ekulama 1, Blocks of accommodation building/office/restaurant etc
and the Hilton accommodation respectively at the Ekulama 2 (FLB) Flow station.

1.2 PROJECT OBJECTIVES

The objective of this Project Execution Plan (PEP) is to illustrate the approach Makais
Synergy Limited, and its technical partners (Prowess Engineering and WAV) referred, as
CONTRACTOR will adopt in
the realization of the Contract of Engineering, Construction, Installation and Rehabilitation of
the Civil Infrastructures at Ekulama 1&2, and Awoba Flowstations in OML 24.
This document provides COMPANY with a general view of the work scope and how
MAKAIS/BERG INDUSTRY LIMITED/WAV Consortiums intend to manage execution
challenges as peculiar to the required Engineering, Construction, Installation and
Rehabilitation activity at site.

PROJECT EXECUTION PLAN 8


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Some details represented in this document may be revised during the final execution to meet
changes that may occur for various reasons. However, it is MAKAIS/BERG/WAV
consortiums intention to adhere to this plan whenever practical.
The consortiums working concurrently will ensure that the project is delivered within budget
and a schedule of about 9 months. Please refer to attachment 1.2.1 for proposed project
schedule.
The Consortiums as required shall continually update the Execution Plan to meet project
requirements. Changes will be reviewed and agreed with COMPANY. As changes arise, the
consortiums shall identify and document critical issues and/or potential constraints that could
adversely affect the accomplishment of Company's objectives for the WORK and shall submit
to COMPANY for approval.
The proposed organization will provide one only interface with the CLIENT (COMPANY) in
order to smoothen all coordination activities between the different disciplines and location.
The entire project (activities) will be managed by a Project Coordination Team led by the
project manager that will take care of all but not limited to the following:

 Interface with the Client


 Site Project Management
 Quality coordination
 Engineering coordination
 Material management and prefabrication
 Safety and HSE coordination
 Administration.
Please refer to appendix 1(A-C) for proposed CONTRACTOR organization charts.

Apart from liaising with Makais Synergy office at Plot 4C, louis Solomon Close off Ahmadu
Bello Way, Victoria Island, the activities above will also be carried out in temporary facilities
installed as closest to site (Ekulama 1&2, and Awoba Flowstations in OML 24).
The following main activities will also be carried out at the temporary site:

 Prefabrication
 Material storing and inspection.
 Construction equipment and logistic, maintenance and management.
The administrative office located on site and in tandem with Makais Office will support all
the aspect related to the:

 Bank relationship
 Customs and importation
 Personnel visa

PROJECT EXECUTION PLAN 9


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Police formalities
The Project Manager (PM) will have the final authority to perform the work in the safest
possible manner and can therefore modify the plan with due consultation with COMPANY
Representative for schedule optimization or to suit the site conditions.

1.3 DEFINITIONS AND ABBREVIATIONS

Definitions:

Project:/Proposal THE ENGINEERING, CONSTRUCTION,


INSTALLATION AND REHABILITATION OF THE
CIVIL INFRASTRUCTURES AT EKULAMA 1&2, AND
AWOBA FLOWSTATIONS IN OML 24 OML FOR
NEWCROSS EXPLORATION AND PRODUCTION
LIMITED/NNPC UPSTREAM AND INVESTMENT
MANAGEMENT SERVICES

CONTRACTOR MAKAIS//BERG/WAV Consortium

COMPANY: NEW CROSS EXPLORATION AND PRODUCTION


COMPANY / NNPC UPSTREAM AND INVESTMENT
MANAGEMENT SERVICES

Abbreviations:

AFC Approved For Construction


Bbls Barrels
BPD Barrel Per Day
DCC Document Control Centre
DED Detailed Engineering Design
DPR Directorate of Petroleum Resources
EPCIC Engineering, Procurement, Construction, Installation and
Commissioning
HSE Health Safety and Environment
PEP Project Execution Plan
PMT Project Management Team
WBS Work Breakdown Structure

2.0 TASKS OF PROJECT EXECUTION PLAN

This project execution plan will fulfill all but not limited to the following purpose listed
below:

PROJECT EXECUTION PLAN 10


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

• Documenting a plan for the execution of the project from Detailed Engineering,
Fabrication, Installation, Construction, Rehabilitation through to Commissioning and
project close out.
• Establishing clear targets.
• Provide the mechanism for gaining CONTRACTOR and COMPANY alignment of
the project scope, execution methodology, schedule and budget prior to work
commencing.
• Identifying critical execution issues and potential constraints.
• Defining a plan for the Project Team activities, including responsibilities of the Team
involved in the Project.
• Facilitate the briefing of project personnel and provide them with a guideline for their
role in the execution of the project.
• Informing involved groups to enable harmonization of their respective contributions
to the overall planning and success of the project.
• Providing a basis against which project execution changes can be identified and
evaluated.

2.1 Critical Success Factors (1)


The Critical Success Factors (CSF’s) are the things that must be done to achieve the project
objectives listed in Section 1.2 above. The Critical Success factors shall include but not
limited to the following:

 Clear definition of the Scope of Work.


 Clearly defined roles, responsibilities.
 Clearly defined deliverables.
 Clear and concise Documentation of stakeholder requirements.
 Clear definition of work processes and procedures to be applied at the project initiation
(Engineering) phase.
 Definition and implementation of HSE plan and project specific initiatives by a set date.
 The quality of the project team throughout the project.
 Completion of all engineering deliverables as set out in the Schedule.
 A successful Interface Management plan to handle all project interfaces.

PROJECT EXECUTION PLAN 11


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 A well thought out Transition Plan from one stage (DED) of engineering to construction,
installation and commissioning stages.
 Key technical peer reviews at critical stages of the project.
 Develop a team culture where changes are minimized, managed and rigorously applied.
 Implement the Management of Change (MoC) process.
 Clearly documented communication and approval processes internally and with New
Cross Exploration and Production Limited.

2.2 Potential risks/Disablers/Specific Project challenges ( 2)

CONTRACTOR has identified the under listed as POTENTIAL DISABLERS for the
successful and timely execution of the projects, viz:
• Community unrests
• Labour unrests
• Work stoppages
• Equipment Failure/Unavailability
• Un-scheduled / Un-planned Delays
• Interface schedules
• Un favorable weather
• Force majeure

A risk assessment workshop involving all stakeholders shall be carried out at the
beginning of the project to determine the aspect and impact of these risks and determine
ways to mitigating them.

2.3 Critical Schedule Activities ( 2)


In order to ensure the implementation of the factors articulated in section 2.1 and 2.2 above.
All but not limited to the following activities are deemed critical to achieving them:

 All stakeholders should be involved and aligned early (i.e integrated team approach).
This requires Alignment Sessions, Client Kick off Meeting and Stakeholder Alignment
Workshop.
 The scope and base documents must be signed off and frozen as indicated in the
Schedule.
 Maintain tight control of change during project execution with a robust management of
change (MoC) process.
 Encourage COMPANY to pursue statutory approvals early to avoid unnecessary delays
if this applies.

PROJECT EXECUTION PLAN 12


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Long lead items should be ordered early by COMPANY to ensure timely provision of
Certified Vendor Data if required.
 Driving design by constructability and operability requirements to avoid delays and
modifications.
 Issuance of deliverables to facilitate modularization and optimize the schedule of site
works as detailed in the Contract.
 Eliminate any resource constraints by flexing team size.
 Recognizing early requirements for the execution phase for document delivery and
ensuring resources are allocated.
 Early detailed planning. Progress the project against all early start activities.
 Continually challenge the critical path to drive for continual improvement to Schedule.
 Delivery of documentation must be in accordance with the agreed Schedule.

2.4 Evidence of Successful Completion of Similar Projects ( 3)

Please Refer to attachments 2.4.1 and 2.4.2 for list of Makais and Partner’s experience

On award of the project, all applicable lesson learnt sessions of relevant previous projects of
Contractors and those provided by COMPANY shall be reviewed and action points collated
and sent to COMPANY and all STAKEHOLDERS for approval.
The approved lessons from previous projects drawn from several functions such as all but not
limited to the following:
 Proposal/ Contracting / Commercial Issues
 Project kickoff
 Interfacing issues
 Team alignments
 Engineering design phase
 Procurement phase
 Construction phase
 Installation phase
Shall be implemented to avoid high impact on schedule, cost, safety and quality during the
execution of the project.

2.5 Outline of proposed execution strategy for this project (4)

The expected generic proposed outlines or key milestones which are predicated on the
specific work pack and phrases of the scope of work within the umbrella contract of the
provision of engineering design, construction and Installation of building/civil Infrastructure
in Ekulama 1, Ekulama 2 and Awoba Flowstations Respectively in OML 24 for New Cross
Exploration and Production Limited and NNPC Upstream Investment Management Services
may include all but not limited to the following:

1. MOBILIZATION
2. KICK OFF MEETING
3. PROJECT MANAGEMENT

PROJECT EXECUTION PLAN 13


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4. DETAIL ENGINEERING (process, instrumentation, architecture,


civil/structural, electrical, mechanical)
5. DEMOBILIZATION OF CERTAIN % ENGINEERING TEAM
7 CASHES.
8 FOLLOW-ON ENGINEERING
9 CONSTRUCTIONS
9.1 SITE PREPARATIONS
9.2 PILING, FOUNDATION AND SANDFILLING
9.3 CIVIL/STRUCTURAL WORKS
9.4 MECHANICAL/HVAC WORKS
9.5 PLUMBERING
9.6 ELECTRICAL WORKS
9.7 PAINTING /CORROSION CONTROL WORKS
9.8 FINISHING/INSTALLATION
10 DEMOBILIZATION

2.6 Project Reference Documents (Plans and Procedures) (7)

During execution of the project, contractor shall use all but not limited to the following
referenced project specific procedures and plans listed below:
: S/N Document Number Title
1 PMT-CME--MAK-0001 Contractor’s Mobilisation & Early Activities Plan
(8weeks)

3 PMT-CC---MAK-0003 Correspondence and Communications Plan


4 PMT-IMP-MAK-0004 Interface Management Plan
5 HSE-PLN-MAK-0001 HSE Plan
6 HSE-ERP-MAK-0006 Emergency Response Plan

7 HSE-RMP-MAK-0005 Risk Management Plan


8 QAC-PQP-MAK-0006 Project Quality Plan
9 PMT-PCP-MAK-0007 Project Controls Plan
10 PMT-PRP-MAK-0008 Peer Review Plan
11 PMT-MCP-MAK-0009 Management of Change Order Procedure
12 PMT-PRP-MAK-0010 Project Reporting Plan
13 PMT-DCD-MAK-0011 Document Control & Data Management Plan.
14 PMT-SDM-MAK-0012 Supplier Data Management Plan Internal Doc
15

PROJECT EXECUTION PLAN 14


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

2.7 Applicable Codes, Standards and Regulations


The design of specific scope of work under the Engineering Procurement and Construction
Services for the project shall be performed in compliance with the latest edition of all but not
limited to the following under listed codes and standards:
.
 Eurocode 0-Basis of Structural Design
 Eurocode 1: Actions on structures –Part 1-4:General actions –wind action
 Eurocode 2: Design of Concrete structures part 1-1 General rules and rules for
building
 American Petroleum Institute (API)
 American Society of Mechanical Engineers (ASME)
 American National Standards Institute (ANSI)
 International Electro Technical commission (IEC)
 American Welding Society (AWS)
 Institute of Electrical and Electronic Engineers (IEEE)
 Industrial cable Engineers Association (ICEA)
 American Society of Testing and Materials (ASTM)
 National Fire Protection Association (NFPA)
 National association of Corrosion Engineers(NACE)
 Det Norske Veritas(DNV)

2.8 New Cross Exploration and Production Limited Standard Specifications & Philosophies

2.9 Interface Management with Engineering, Vendor Activity, and Fabrication and
Construction sites.
The detail engineering design and preliminary vendor activities shall take place at Makais
head office at 4c Louis Solomon close off Ahmadu Bello Way Victoria Island.

Core vendor activity during execution of detail engineering design shall also be domiciled at
makais synergy head office. While fabrication and construction activities shall take place at
makais fabrication yard at Portharcourt (address)and projects sites at Ekulama 1.& 2 and
Awoba flow stations respectively.

The proposed organization will provide one only interface with the CLIENT (COMPANY) in
order to smoothen all coordination activities between the different disciplines and location.
The entire project (activities) will be managed by a Project Coordination Team led by the
project manager that will take care of all but not limited to the following:

PROJECT EXECUTION PLAN 15


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Interface with the Client


 Site Project Management
 Quality coordination
 Engineering coordination
 Material management and prefabrication
 Safety and HSE coordination
 Administration.
Please refer to appendix 1(A-C) for proposed CONTRACTOR organization charts.

Apart from liaising with Makais Synergy office at Plot 4C, louis Solomon Close off Ahmadu
Bello Way, Victoria Island, Victoria Island, the activities above will also be carried out in
temporary facilities installed as closest to site (Ekulama 1&2, and Awoba Flowstations in
OML 24).
The following main activities will also be carried out at the temporary site:

 Prefabrication
 Material storing and inspection
 Construction equipment and logistic, maintenance and management.
The administrative office located on site and in tandem with Makais Office will support all
the aspect related to the:

 Bank relationship
 Customs and importation
 Personnel visa
 Police formalities

The Project Manager (PM) will have the final authority to perform the work in the safest
possible manner and can therefore modify the plan with due consultation with COMPANY
Representative for schedule optimization or to suit the site conditions.

3.0 PROJECT MANAGEMENT SYSTEM(6)

This section describes the project management system proposed for planning, scheduling,
analyzing, forecasting and control of the project.

3.1 OVERVIEW OF PROJECT MANAGEMENT SYSTEM

An efficient and dynamic project management system is of critical importance in ensuring


the success of the project. Based on a system of analysis and decision-making, the
purpose of this system will be to:

PROJECT EXECUTION PLAN 16


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Direct and actualize the intent of the project.

 Identify actions, risks and responsibilities within the project.

 Prepare schedule modifications.

 Develop and maintain schedules, which contain the resources, required to bring about
the successful completion of the project.

The key project team members headed and directed by the project manager shall be
responsible for providing and developing a feasible plan of operation in terms of time,
cost and to update and reschedule each phase during the construction period by
studying project status and evaluation data and information received.

The project manager shall also be responsible for coordination, through discussion
with COMPANY and the project management team of all planning activities for
mobilization and demobilization, procurement, fabrication, construction, and
commissioning as required to meet the dictates of the project.

 Planning

Planning in this project shall be concerned with the determination of quantity and
timing for all activities to be executed under the duration of the contract. Specifically,
it shall involve decision making on the following:

1) Tasks - activities to be carried out

2) Strategies - means for achieving the objectives

3) Budgeting - actions necessary to achieve the goals

Project planning suitable tools and techniques shall be employed to facilitate planning
process. These tools include but not limited to the following:

 Time and cost estimates


 Budget

 Cash flow charts

 Personnel data charts

 Material availability details

PROJECT EXECUTION PLAN 17


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Gap analysis – This shall be used in determining the performance gap between the
current activities and operations and possible future target – once this is
ascertained, it becomes easier to determine future plans and strategies for filling
that gap.

 Scheduling

Project scheduling shall involve the determination of project activities in the sequence
in which they have to be performed. Materials and personnel needed at each stage of
the contract shall be computed and the time each activity will take place also set.

Scheduling in this project shall indicate the following:

a) Relationship of each activity to others and to the whole project

b) Identify precedence relationships among activities

c) Facilitate the setting of realistic time and cost estimates for each activity.

 Construction Scheduling

CONTRACTOR construction scheduling system shall utilize a number of specialized


schedules used for the control of progress, manpower, construction equipment,
materials (both imported and locally purchased) and field supervision requirements.

The construction progress plan shall consists of a summary sheet on which the total
construction status is summarized in a histogram and an S-curve and detailed
supporting sheets in which the work is divided into areas and activities.

Target field dates shall be developed for such activities. Thereafter the sequence and
duration of the works shall be developed for the entire project after discussion with the
COMPANY. This then becomes the basis for the planning of manpower, equipment
and field supervision and influences priorities on purchasing efforts and construction
mobilization.

 Scheduling Tools

CONTRACTOR shall utilize the scheduling tools listed below: They shall be
presented in tables and bar charts:

 Manpower loading plan:


This will indicate monthly craft requirement.

 Construction equipment plan:

PROJECT EXECUTION PLAN 18


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

This will indicate monthly equipment requirements for each phase of the work,
including arrival dates for each item of work.

 Field Supervision plan:


This shows monthly supervision requirements from the mobilization period
throughout construction and the final demobilization phase of the project.

 Monthly/weekly work plan:


This shall list the project manager’s commitment of work to be accomplished
during the period.

 Project Review and evaluation Techniques (PERT):


This technique shall be utilized to:

 Create and fine-tune project schedule

 Link tasks to specify the task sequence and determine start and finish dates

 Graphically show completed, in-progress and not yet-started tasks

 Assign personnel and other resources, such as equipment to specific tasks.

CONTRACTOR project scheduling software shall be microsoft project and


primavera.

 Project Control

Project control shall involve the monitoring of resources, costs, quality and budgets.
It shall also involve using a feedback loop to revise and update the project plan and
schedule and having the ability to shift resources to where they are needed most.

Work shall be controlled by measuring work, adjusting the start and finish dates;
reallocating resources so that the schedule is maintained. Cost shall be controlled by
monitoring of productivity and costs to maximize the earlier and minimize the latter.

Project control shall be at the level – 3 details and shall utilize tracking facilities
available in Microsoft Project for Window planning tool. The aim will be to
proactively predict contracts and delays, and put in place measure agreeable with
COMPANY to control or at worst recover the schedule.

 Project Control Meeting

The project manager will schedule periodic meetings at least once weekly with his key
staff to review the progress of the work and to discuss the need for corrective actions.

PROJECT EXECUTION PLAN 19


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The project manager will also schedule project review meetings as stated in tender
documents or at least once monthly between COMPANY and CONTRACTOR
Services to ascertain whether the project is on schedule and to determine the project
status with regard to utilization of resources.

Major suppliers shall also hold periodic meetings with COMPANY Project key staff
and all CONTRACTOR supervisors. The periodicity of these meetings shall be at the
instance of the Project Manager.

4.0 PROJECT EXECUTION STRATEGY (METHODOLOGY)

The CONTRACTOR acknowledges that the project duration of 9 months is an


important element in the successful implementation of this project and therefore, has
developed an execution strategy keeping in mind the following important aspects of
the project:

 Establishment of an efficient and workable organization for the project.


 Access to site for the PLANT & EQUIPMENT and the heavy construction
machinery
 Timely Mobilization to work site
 Providing floats in project planning and scheduling in order to minimize the
negative effects of climatic conditions, holidays, production downtime, community
restiveness, etc, which may affect work performance.
 Eliminating inland / sea logistic problems for project materials.
 Identification of areas of risk and their contingency plan.
 Automation of the work process.
 Provision of subcontracting for areas of work where the required skill sets are not
entirely available in-house and specialist agencies are available

4.1 AWARD OF THE CONTRACT

Immediately after award of the Contract, the key personnel identified for this project
shall identify their respective teams, their staffing plan based on the task, and the
positions identified in the organization chart. These teams shall begin review of the bid
documents and CONTRACTOR’S proposals.

A detailed project execution plan shall be developed there-after. The Detailed project
execution plan shall also incorporate the method of co-ordination, monitoring &
reporting procedure and list of periodic submissions to the COMPANY. This plan
shall be discussed in detail with the COMPANY project team and once approved, shall
be followed for the entire duration of project.

This shall be followed by a preparatory plan for the Project Kick off meeting.

PROJECT EXECUTION PLAN 20


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

CONTRACTOR will also provide and equip TEMPORARY OFFICES for the
COMPANY at CONTRACTOR’S own office premises.

4.2 KICK OFF MEETING

For the preparation of the kick off meeting, the CONTRACTOR shall prepare and
send to the COMPANY an agenda of the meeting with the key aspects proposed to be
discussed. Inputs shall also be taken from the COMPANY while preparing the agenda
of the meeting.

During the Kick off Meeting, action and discussions on the following shall be planned;
 Mobilization Plan
 COMPANY Priorities
 Preliminary discussions on Schedule with emphasis on activities to be performed in
the first three months.
 Exchange of Data
 Discussions on Plans & Procedures to be submitted and list of deliverables.
 Discussion on overall execution plan with emphasis on requirements for obtaining
statutory compliance, permits and permissions.
 Areas of Contractor concerns and assistance required from the COMPANY.
 Communication procedure between COMPANY and CONTRACTOR

This shall be followed by an internal meeting at the CONTRACTORs office in Lagos


and Portharcourt chaired by the Project Manager. In this meeting facilitation
requirements from Corporate Office related to staffing, equipment and financial needs,
review of proposal and requirements for project, risk mitigation etc. shall be discussed
and concluded.

Broad action plans shall be formulated for each functional group.

4.3 MOBILIZATION(10)
CONTRACTOR considers the mobilization of Manpower, Machinery & equipment,
and finances on time as one of the most important elements affecting the success of a
project. Therefore, a mobilization plan has been formulated in accordance with the
overall project schedule.

4.3.1 Mobilization of Manpower – Phase – I


The very first phase of Mobilization will be done within the first 14 days after the
Effective Date(ED), i.e. Contract Award and will comprise of Mobilization of Key
Personnel. The first team to be mobilized will consist of all but not limited to the

PROJECT EXECUTION PLAN 21


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

following:

• Project Manager
• Project Control & Planning Manager
• Engineering Manager
• Contracts Manager
• Construction Manager
• Procurement and Subcontracts Manager
• QA/QC Manager
• Community Interface Manager
• Health & safety manager
• Lead Engineers
• Skeletal Staff to support above

The intention of this mobilization is to firm up the initial core team to arrange the
preparation and issuance of the Project Documents for Company review and approval
and commencement of Detail Engineering Design, within 30 days after ED. The
documents are as follows:
• Initial Master Document Register (MDR)
• Project Execution Plan
• Project Management Plan
• Project Controls plan & Quality Control Plan
• Health and Safety Management Plan
• Security Plan
• Environmental Plan
• Community Relations Management Plan
• Interface Plan
• Transport Management Plan
• Final Construction Schedule
• Construction march chart
• Co-ordination Procedures

The Core Team shall set up Temporary offices for own staff and COMPANY staff
within CONTRACTOR’S office premises at Lagos and Port Harcourt (closeness to
Company operational area).

4.3.2 Mobilization of Manpower – Phase – II

This phase shall take place after 30days of the ED. During this phase, key departments
such as engineering, procurement, project control and planning, QA/QC, etc, will be
beefed up with personnel sufficient to actualize the following goals within 150 days
after the ED:
1. Completion of Detail Engineering Design (DED).
2. Completion of commissioning of the Construction Camp/Office Facilities

PROJECT EXECUTION PLAN 22


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

3. Completion of Third Party interface documentation


4. Approved QA/QC Procedures
5. Approved HSE procedures
6. Approved Environmental Procedures
7. Approved Community Relation Procedures
8. Detailed Project Audit schedule for each of the following:
a. Detailed Engineering activities
b. Procurement activities
c. Health & safety
d. Environmental
e. Construction
In addition to the above, it is planned that the under listed activities will be completed
within this period:
- Completion of Geotechnical survey works
- Completion of all detailed engineering activities
- Procurement and receipt of:
• All long lead items (LLI)
• All bulk materials
• Procurement and receipt of electrical & instrumentation materials
• Procurement of steels, cement etc
• All consumables
• Procurement and receipt of all new plant & equipment, machinery &
tools
• Hiring of remaining plant & equipment & machinery
• Placement of all Technical and Services sub-contracts relevant
to execute the works.

4.3.3 Mobilization of Manpower – Phase – III

The third phase of mobilization will comprise of major manpower, sub-contractors,


vendors, service providers, third party agents, etc, and the relevant plant / equipment
and other resources necessary for the construction, installation of ancilliaries, testing
& pre-commissioning, commissioning and hand over of the project

CONTRACTOR will execute this phase in the following order:

2) Mobilize the completely resourced Project Management Team fully at Camp site
• Set up and fully equip own project management team offices and
accommodation at the Camp Site,
• Assemble all relevant construction plant, equipment, machinery and
tools at the camp site.
• Mobilize all major work force involving direct and indirect
manpower, and resources for the construction and installation of all

PROJECT EXECUTION PLAN 23


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

buildings, access roads and jetty. This group will also execute all
fabrication works; pipe spool, support, tie-ins, at the appropriate time
in conformity with weather conditions.
• Mobilize the relevant crew and tools

3) Closely followed to the above order will be the manpower for the installation of
cabling, fittings. This team will execute all the post-construction activities
incidental to a proper and acceptable demobilization.

CONTRACTOR has identified the under listed as POTENTIAL DISABLERS


for the successful and timely execution of the projects, viz:
• Community unrests
• Labour unrests
• Work stoppages
• Equipment Failure/Unavailability
• Un-scheduled / Un-planned Delays
• Interface schedules
• Un favorable weather
• Force majeure

Any / or all of the above will cause slippages in the execution of work unit and / or
sub-work unit packages, and this may cause a chain-link slippage in the overall project
schedule. To ensure adequate float is provided to ensure speedy recovery from any
such slippage, CONTRACTOR will mobilize all but not limited to the following crews
during this third phase:

 Welding crew, which will be resident at the camp site, and will be responsible for
all FABRICATION works as well as miscellaneous mechanical works.
 Electrical, Instrumentation and HVAC will also be resident on site
 fully equipped civil crew will handle all site civil works as follows:
- Civil Crew will be mobilized during the phase II mobilization to execute all
activities incidental to the commissioning and acceptance of the package and
camp site, erection of accommodation and office blocks for both COMPANY &
CONTRACTOR use, etc.
- Upon completion of welding crews, the civil crew will work simultaneously
with the mechanical teams to execute all civil activities pertaining to the
package.

In all, all-unskilled work force, including labour, shall be Nigerians and will be locally
sourced, as much as will be possible.

4.4 GENERAL ACTIVITIES WORK APPROACH

4.4.1 Engineering

PROJECT EXECUTION PLAN 24


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The Detail Engineering Design (DED) activities will be domiciled at already established
Makais Synergy Engineering facility at 4C louis Solomon Close, off Ahmadu Bello Way,
Victoria Island The engineering activities shall be coordinated by the Engineering Manager
on the project who will also report to the project manager. Refer to

Multi discipline engineering team shall provide the engineering services during project
execution in Makais Synergy office.
CONTRACTOR shall commence the execution of the Detailed Engineering Design by
reviewing available engineering drawings and other relevant handover documents from
COMPANY.
CONTRACTOR shall conduct site survey to collate relevant data from the facilities as part of
activities necessary to fulfil the scope specified in the invitation to tender letter

The following Makais Synergy engineering disciplines shall participate in the Engineering,
(DED) of the project:
 Civil/Structural
 Corrosion
 Mechanical/HVAC
 Electrical
 Quantity surveyor
 Document Control
 Quality Control/Quality assurance
Refer to section 5.0 for details on their approach to work.
The plan layout of Makais Synergy design office at No 4C Lois Solomon Close,Off Ahmadu
Bello Way, Victoria Island Lagos is as shown below:

PROJECT EXECUTION PLAN 25


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.4.1.1 Engineering Procedures

CONTRACTOR will utilize existing well established CONTRACTOR corporate Procedures


for the control of the engineering documents. Actions will be put in place to:
• Standardize the form of the engineering documents.
• Standardize the documents’ distribution matrix.
• interdisciplinary checking of documents within the Project Team to ensure cross-
department uniformity and consistency.
• Design Change Control.

The Contractor Corporate Procedures will be tailored to suit the Project needs as may be
required.
An Interface Procedure will be developed to manage adequately the communication protocol
between CONTRACTOR and COMPANY.

4.4.2 Construction

The works will be sub-divided into individual activities which will be undertaken in a logical
sequence to achieve the successful completion of the Project within the requested milestones.
This will involve detailed planning to accurately assess the requirements of manpower,
equipment and materials for all works. Meetings will be held with Client Project Management
Team to ensure that all work is planned and carried out to the correct procedures and in line
with all permits and approvals, which may be required.
This will involve:
 Listing by discipline and number the personnel required to perform individual
activities and ensuring said personnel are available at site prior to commencement of
works.

PROJECT EXECUTION PLAN 26


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Ensuring that all equipment required for the works are available at site and is fully
operable and complete with all permits, service records, spares, as may be required.
 Sorting, storing, tagging all materials required for installation of temporary and
permanent works.
 Ensuring all specifications, drawings, procedures and construction information as
required are available at site and are familiar to the construction personnel.
 Ensuring that all permits and approvals have been obtained and that construction
personnel are familiar with their content prior to commencing individual operations.

 Detail check-out of all facilities and equipment following installation and preparation
of "punch-lists" for completion.
 Ensuring all checks and tests are made on facilities to allow the Client to issue
Mechanical Completion Certificate.

The construction activities will be coordinated and controlled by the Construction Manager,
who will act to ensure that the execution process is in line with established procedures for the
Project.
The Site Management team reporting to him (as per Site Organization chart) has the
responsibility for ensuring that the site activities are coordinated and orientated towards
achievement of the goals for the overall Project. He will be actively involved in all procedural
aspects of the Project both with COMPANY and with the subcontractors.
The Construction Manager will serve as prime point of contact with COMPANY for all
aspects related to the project during the construction phase, and he will direct and keep a close
supervision on all contacts with COMPANY, to make sure that all requirement and mutual
contractual obligations are met, and that all COMPANY’s requirements are properly
considered.
CONTRACTOR's Site Organization will work closely with the COMPANY Site Team.
CONTRACTOR and COMPANY will jointly cooperate for quality inspections, testing,
meetings and any possible aspect involving the main objectives.
Site meetings between CONTRACTOR and COMPANY will be held periodically to discuss
the overall progress, safety and details related to the construction.
Construction will be controlled, with reference to the objectives, for quality, time and costs
established by the Contract.

PROJECT EXECUTION PLAN 27


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The progress of construction shall be controlled with reference to a construction program,


which expands the applicable parts of the detailed Project network, while maintaining its
milestones and objectives.
Particular care will be given to the control of the quality of the works executed.
For each discipline, the necessary QC Inspectors will always be on site to ensure that the
works are executed in accordance with the quality requirements.
CONTRACTOR will maintain a safe system of working by appointing the HSE Manager who
will be assisted by a Safety Supervisors/Officers. The Safety Officer will always be present at
all times on the working sites and will make sure that all safety regulations are observed and
implemented.
Construction/installation activities shall be planned to be carried out in a way to cause as little
disturbance as possible to local communities and to the environment.
To achieve this objective, the prefabrication of piping and structural components will be
carried out at WAV Fabrication Yard at portharcourt provided with all necessary equipment
and facilities including workshop/maintenance buildings, access to communication means etc.

CONTRACTOR will prepare a Mobilization plan and program, which will guide all actions
to enable the construction organization to become effective within the scheduled time. The
Plan will be based on the contractual requirements, on the information collected on site and in
any other way available, based on the extensive experience of CONTRACTOR in executing
similar work.
The plan will cover:
 Authorization by local authorities and entry permits.
 Temporary camp accommodation facilities.
 Temporary site offices.
 Temporary lay down and workshop area.

Prior to commencement of activities at the site, COMPANY’s representatives together with


the CONTRACTOR’s representatives will hold a meeting with the local community and pay
a courtesy call.

PROJECT EXECUTION PLAN 28


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

During this meeting, the nature and duration of the job, and its likely impact/consequences on
the community shall be explained and assistance offered to the community.
All community issues will be treated in full respect of COMPANY Sustainable Community
Development Program and under direct control of COMPANY.
Construction will be sub-divided into individual activities, which will be undertaken in a
logical sequence to achieve the successful completion of the WORK within the requested
milestones.

This will involve detailed planning to accurately assess the requirements of manpower,
equipment and materials for all works. Meetings will be held with COMPANY to ensure that
all work is planned and carried out to the correct procedures and in line with all permits and
approvals that may be required, especially those works that require tie-ins to existing
equipment/services.

This will involve the following:

 Ensuring by discipline and number of the personnel required to perform individual


activities are available at site prior to commencement of work.
 Ensuring that all equipment required for the work is available at site and is fully operable
and complete with all permits including COMPANY pre-mobilization inspection, service
records, spares, as may be required.
 Ensuring all specifications, drawings, procedures and construction information as
required are available at site and are familiar to the construction personnel.
 Ensuring that all permits and approvals have been obtained and those construction
personnel are familiar with their content prior to commencing individual operations.

4.4.3 Procurement

A Project Procurement team shall be mobilized immediately on award of contract. A


Procurement manager shall head the team. The Procurement Manager shall report to the
Project Manager. The Procurement Manager shall prepare the requisite procurement plan
for all project material. Also, the Project Manager, together with the Procurement
Manager shall plan, progress / monitor and report on all procurement work units and Sub-
work units, using a reporting procedure developed as per COMPANY guidelines.

The core procurement team will conduct market surveys and raise / issue purchase orders
to both local and International Vendors (where necessary) and Sub-Contractors, prior to

PROJECT EXECUTION PLAN 29


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

execution. The same procurement team will be responsible for both onshore and offshore
procurement activities, including transportation of materials to the approved areas, and to
site.

The Procurement team will work in close link with the Quality Control team to ensure all
the material has been manufactured as per Company approved project specifications
international procedures and standards. To this end and especially for all major equipment
procurement, CONTRACTOR shall arrange for all quality assurance activities (Inspection,
Tests, Insurance, all Certificates, etc). CONTRACTOR will strictly adhere to all
requirements, as specified in COMPANY standards & specifications.
The procurement team shall also be responsible for the purchase, certification and
delivering of all local supplies at site temporary office. Such SUPPLIES shall include but
not limited to:
 All electrical appliances, including telephone sets, computers, air-conditioners,
refrigerators, etc.
 All consumables – fuels, bed linens, etc. Only COMPANY pre-qualified Vendors,
Sub- Vendors and Sub-contractors will bid for the above SUPPLIES. COMPANY will
be involved in the contracting processes.

The Procurement Manager will be responsible for:


 Procurement Activities
 Purchasing
 Expediting
 Inspection & Testing
 Materials Tracking and Control
 Forwarding
 Customs Clearance

 Supply & Transportation Activities


 Supply of equipment such as steels bars, gravels, sand
 Supply of Bulk Materials
 Reception and Handling
 Transportation

 Supply of spares

MAKAIS Synergy will procure all other materials, equipment and spares required for the
project in-country to the largest extent possible. Those items not available locally shall be
procured outside Nigeria with the approval by the COMPANY. Any materials required to be
procured outside of Nigeria will be shipped directly to Portharcourt. Customs clearance of
the imported materials will be carried out by Government-approved Clearance Agencies.

PROJECT EXECUTION PLAN 30


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

All materials will be delivered to COMPANY’ facilities at Portharcourt. Receipt and


Inspection of ALL MATERIALS AND EQUIPMENTS will be carried out for visual damage.
Records stating the Contents/Quantities and Quality will be issued, as well as any damages on
materials when received. These records will form part of the Goods Inward Report. This
Report will be submitted to COMPANY within three days.

The materials will be stored and preserved in an appropriate shelter and in accordance with
the vendor/supplier’s specifications. The storage will be permanently secured and protected.
Any material collected to be installed will be recorded. The record will be made available for
the Client’s perusal at any moment of the project ‘lifetime’.

4.4.4 Fabrication

A fabrication team comprised of a welding crew (labour, tools, plant, equipment and machinery),
headed by a lead Engineer (preferably a Mechanical Engineer), shall be based in the workshop
located in the camp site while another fabrication team, where major fabrication shall be carried
out shall be based at CONTRACTOR fabrication yard situated at WAV facility at Portharcourt.
The team shall be responsible for all but not limited to the fabrication of the following:

 Platform handrails, stair cases, ladders etc


 branched spools
 supports
 support brackets
 hangers
 anchors

 All steel fabrication works required for the successful erection of the accommodation and
structures.
The fabrication team will build the required item(s) using appropriate raw materials
(c/s sheets, rods, angles, squares, etc) as per COMPANY approved design drawings.
The relevant Quality Control measure (e.g. NDT, X-ray) will be applied to ensure high
quality fabrication. Prior to fabrication works, site measurement shall be taken to
confirm measurements on drawings. All bare parts (i.e.) bare steels materials) shall be
grit blasted and primed, numbered as per Drawing number and orderly stacked in the
material warehouse for easy identification.
A lead mechanical Engineer shall supervise the workshop and fabrication works.
A site plan of CONTRACTOR (WAV) fabrication yard is as shown below:

PROJECT EXECUTION PLAN 31


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

PROJECT EXECUTION PLAN 32


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Pictorial view of CONTRACTOR fabrication yard is as shown above:

PROJECT EXECUTION PLAN 33


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.5 PROJECT MANAGEMENT ORGANIZATION

Upon Contract award, a Project Management shall be nominated / confirmed. A


management team comprising top management staff of all the various key disciplines
/departments, together their skeletal staff shall be assembled to form the PROJECT
MANAGEMENT TEAM (PMT).
The Project Manager shall be the communication link between the CONTRACTOR and
the COMPANY and shall be authorized to ACT on behalf of CONTRACTOR. He shall
also head the project management Team. The project management team shall be located
at the camp site after it has been fully commissioned after completion of Detail
Engineering Design.

The Project management at the camp site shall be responsible for the following:
 Regular co-ordination with COMPANY office at the camp site
 Regular co-ordination with CONTRACTOR’s site team and Home Office
 Procurement
 Project Financing
 Arrangement of additional resources like manpower/ material etc.

The various disciplines of the Project Management Team at the campsite shall perform
the following tasks:
 Planning/Monitoring/Co-ordination/Billing plans
 Preparation of plans and procedures and documentation.
 Co-ordination and finalization of Subcontracts.
 Contract Management.
 Identification and preparation of risk mitigation plans.
 Financial Management.
 Administration
 External Interfaces Management
 Engineering Co-ordination
 Procurement
 QA/QC & HSE
 Co-ordination, support, monitoring of construction activities.

The document control group shall assist the project management by providing a
comprehensive Document management system.
The planning team shall evaluate the Level 2 and 3 schedules. This shall bring emphasis
on the work requirements of the all the activities included & provided in project
schedule. Primary list of procedures / methods and plans shall be developed and
submitted to COMPANY and a copy of the same shall also be forwarded to the
concerned functional teams.

Parallel action shall be initiated for review of the cash budget and cash flow sheet
prepared at bid stage for adequacy. The cash forecast shall be generated and forwarded

PROJECT EXECUTION PLAN 34


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

to the corporate office for action. Cash flows shall be evaluated and updated on a
monthly basis. From the overall cash budget, budget allocation for procurement and
construction shall be distributed.

4.5.1 Organisation/Roles and Responsibility/Communication

In order to secure the complete success of the project; to maintain good coordination with
COMPANY, to measure and monitor performance and to complete the works in a satisfactory
manner, an experienced Project Team will be led by a competent Project Manager.

Under the authority of the Project Manager, a Project Liaison Office for facilitating supporting
activities will be established to undertake procurement of emergency items, collection of
COMPANY supplied materials; ensure effective communication between COMPANY and
CONTRACTOR, mobilization of equipment and recruitment of employees as required during
the execution of the project.

The responsibilities and functions of some of the key personnel in the PMT are represented
briefly as follows:

4.5.1.1 Project Manager

The Project Manager coordinates the activities covered by the execution of the contract and
as CONTRACTOR Representative, keeps the appropriate contracts with COMPANY for its
representatives. In particular, he is responsible for all but not limited to the following:

 Compliance with and fulfillment of, the project contractual obligations

 Coordination of the activities of the various departments involved in the execution


of the job, in order to guarantee conformity with the design criteria, programs and
cost estimates.

 Implementation of the Quality Assurance program

 Project detailed programming and the relevant updating together with the various
offices involved in the execution of the job.

 Analysis of the preliminary and/final estimates and the definition of possible


updates relating to the project.

 Supervision of purchasing, and subcontracts, including other issues, expediting

PROJECT EXECUTION PLAN 35


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

inspection and testing activities

 Analysis of work or change of the scope of work not covered by the contract, the
assessment of the consequent costs and agreement with COMPANY

4.5.1.2 Engineering Manager

The project Engineering Manager shall be responsible for all but not limited to the
following:

 Analysis of technical specifications issued by COMPANY and definition of a list of


engineering documents to be produced for the project.

 Preparation of work procedures related to operations directly carried out by


CONTRACTOR.

 Preparation of technical specifications for material procurement.

 Review of work procedures prepared by CONTRACTOR for their scope of work

 Interface with Technical Department at Head Office, requiring all necessary


documentation (i.e. drawings, computer calculations) and supplying
CONTRACTOR Energy’s input data.

 Ensure quality development of all engineering deliverables.

4.5.1.3 Quality Assurance Engineer

He shall be responsible for monitoring quality related activities of the project and their
documentation. He is under functional authority of the QA Manager at head office.
His duties are:

 Prepare the Project QA Plan in connection with the Project Manager and the QA
Manager at head office.

 Verify that the quality related activities are in accordance with applicable codes,
specifications and regulations.

 Ensure recording, updating and distribution of documents and information, i.e.


procedures, drawings, plans, reports and certificates.

 Identify any deficiency, promote corrective actions and verify their implementation.

PROJECT EXECUTION PLAN 36


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Verify that contract Quality requirements are specified to Vendors and


CONTRACTOR Energy Services.

 Ensure collection of documentation and certificates related to materials purchased


by CONTRACTOR and other subcontractors.

 Ensure that measures are taken in order to identify and prevent acceptance of
defective materials.

 Ensure collection of documentation and certificates related to materials purchased


by CONTRACTOR.

 Prepare QC plans for producing phases and review quality plans issued by
CONTRACTOR and vendors.

 Ensure the inspection and testing in compliance with established Q plans.

 Ensure the compliance of final documentation to be issued to COMPANY

4.5.1.4 Planning and Cost Control Manager

The Planning and cost Control Manager is responsible for all but not limited to the
following duties:

 Preparation, in cooperation with the Project Manager, of the overall and detailed
program.

 Management of all programming means and/or systems.

 Preparation and collection of data and working out of the job Monthly Report
taking information from other project functions.

 Analysis of the program of works carried out and to be carried out, by preparing
statistical reports and suggesting actions for improvement.
 Preparation and implementation in cooperation with the Project Manager of the cost
control system.
 Preparation of project executive estimate and its projection along project life.

 Preparation and collection of data of monthly cost control report taking information
from other project functions.

 Analysis of the cost deviation versus estimate by preparing statistical reports and
suggesting actions for improvement.

PROJECT EXECUTION PLAN 37


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Preparation of estimate for project change orders and claims.

4.5.1.5 Procurement and Material Coordinator

He shall be responsible for the logistic support required for performing the
construction/installation activities as provided in the contract.’

In particular he shall ensure the activities for:

 Purchasing and/or hiring of materials, equipment and operating means, their


transportation and customs clearance.
 Issuing of P.O on the basis of technical specifications.
 Supervising CONTRACTOR and/or COMPANY’s supplied materials
 Receiving material at the warehouse and their inspection against purchase order
documents.
 Handling, storage and shipping of materials as appropriate
 Filling of all material documentation and certification as specified in the P.O.
 Coordination of all project inspection and testing activities carried out by the
Inspection and Expediting Department.

4.5.1.6 Project Administration and Financial Manager

The Project Administration and Financial Manager shall be responsible for all but not
limited to the following:

 Carrying out the project financial programming


 Assuring the financial resources necessary for the project through banks or
COMPANY payments.
 Implementation and maintenance of the project accounting
 Administration of personnel including industrial relations
 Performing the control of vendors and CONTRACTOR invoicing
 Preparing expenditure and commitment curves for the project
 Maintaining a full and complete record of the cost breakdown, according to the
accounting codes agreed with COMPANY.
 Preparing invoices to COMPANY according to the contract modalities.

4.5.1.7 Construction Manager

The Construction Manager is responsible for the correct and economic fulfillment of
procedures and working program concerning the construction and installation activities.
In particular, he is responsible for the performance of the works according to the

PROJECT EXECUTION PLAN 38


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

planned data, safety conditions and in respect of the contractual terms.

He shall manage the personnel and equipment available to carry out the contractual
works and in particular, he shall coordinate the logistic activities necessary to support
the production line.

He shall coordinate and verify the activities of his assistants, who are responsible to
ensure that every phase of work (foundation, concrete, roofing , painting, coating, etc)
is properly executed, checked and recorded. The field superintendents for the various
project construction areas shall report to the Construction Manager.

4.5.1.8 Safety Officer

He shall be responsible for establishing all safety rules related to the project activities
on site and verifying their implementation. The Safety Coordinator will assist the
project Manager in safety matters and conduct safety awareness meetings established
under the direction of the Project Manager. He will check work plans and procedures
and advise the Project Manager on matters of safety, health and the environment.

Instructions for corrective action will be issued by the Safety Supervisor in case any
violations occur against the general rules and safety procedures.

His specific duties are all but not limited to the following:

 Check that all equipment are approved in compliance with the local law/regulation.
 Check that the protecting clothes utilized by personnel are in good conditions and
compatible with health and welfare.
 Check that during the execution of all phases of work hygiene and safety rules are
applied.
 Inform all the workers about health and safety rules by means of brochures, signal
meetings etc.

4.6 SUBCONTRACT PLAN

The CONTRACTOR shall be utilizing the services of specialist agencies with proven
track record for the work areas itemized below. The major areas of work to be
subcontracted includes all but not limited to the following:

 Geotechnical survey
 Soil investigation report
 Inland transportation
 Equipment Rentals

PROJECT EXECUTION PLAN 39


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Catering
 Housekeeping & Laundry
 Vehicle Hiring

All the works shall be subcontracted to various sub-contractors, vendors, suppliers, etc,
after in-house technical and commercial evaluation of and subsequent discussions with
the short-listed agencies. However, no subcontract will be finalized without approval
from COMPANY.

A detailed project execution plan which will also incorporate the proposed
subcontractor plan shall be developed after award of contract. Detailed project execution
plan shall also incorporate the method of co-ordination, reporting and list of periodic
submissions to the COMPANY. This plan shall be discussed in detail with the
COMPANY project team and once approved, shall be followed for the entire duration of
project.

4.7 TRANSPORTATION PLAN

Transportation of materials and personnel to site will include all but not limited to the
following:
 Inland transport from supplier delivery point to port of loading
 Export custom formalities
 Loading/onto low bed,
 Sea
 Unloading from sea
 Import custom formalities
 Loading on to trucks
 Inland transport from unloading point to job Site

The main terrain of transportation is LAND and SEA. It is common knowledge that
Nigerian roads have deteriorated extensively. Therefore, adequate safety habits and
traveling time will be incorporated into the plans. All relevant transportation permits
and licenses shall be obtained before such goods shall be transported.
In the case of marine movement, CONTRACTOR shall ensure that all shipping
arrangements are satisfactory met and shipment meets the transportation schedule.
CONTRACTOR will comply with COMPANY safety and marine transport procedures.
Adequate care will be exercised in the operation of marine craft to avoid damage to
fishing traps and nets set by the locals along the river routes, creeks and creek-let.
Additional care will be taken when passing near communities and settlements along the
riverbanks.
For both land and marine transportation, adequate security personnel shall be provided.

PROJECT EXECUTION PLAN 40


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.8 PROJECT CONTROL(6)

4.8.1 Schedule
CONTRACTOR shall deliver the project on time to meet COMPANY expectation. This is
scheduled to target less than 9 calendar months.
Please refer to Attachment 1.2.1 for Project Execution Schedule.
After CONTRACT Award, CONTRACTOR will issue for APPROVAL the
following schedules and schedule information:

 Overall Construction Schedule.


 Overall constructions “S” curve in A3 format, which will be based on CONTRACTOR’s
Overall Construction Schedule.
 Overall manpower histogram (in A3 format), which will be based on CONTRACTOR’s
Overall Construction Schedule.
 Schedule of assignment of heavy construction equipment.
 Staff assignment schedule.
 WORK to be subcontracted by CONTRACTOR
 Overall Network Schedule.
 Detailed Construction Schedule and S-curve.
 Two-month "Look-ahead" Guide Schedule.
 Two-weekly Work list.
 Other Schedules

4.8.1.1 CONTRACTOR’s Overall Construction Schedule

CONTRACTOR’s Overall Construction Schedule will show the MILESTONE DATES,


other important dates in the execution of the WORK such as submission dates of important
documents, as well as the COMPLETION DATE.

The Overall Construction Schedule will, as a minimum, identify the following activities:

 CONTRACT Award.
 Mobilization of CONTRACTOR’s Site and Facilities.
 Engineering, Planning and preparation.
 Procurement of CONTRACTOR’s SUPPLIED MATERIALS.
 All key discipline activities.
 Submission of Quality Control documentation.
 COMPLETION DATE.
 Demobilization and reinstatement.

PROJECT EXECUTION PLAN 41


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

CONTRACTOR will ensure that, in addition, all other activities which are critical to the proper
completion of the WORK, or whose importance is deemed sufficient, by COMPANY or
CONTRACTOR to warrant inclusion, will be shown regardless of the duration of such activities.

CONTRACTOR may not change his base plan, unless expressly APPROVED by COMPANY.
CONTRACTOR will promptly submit for COMPANY’s APPROVAL any proposed change.

CONTRACTOR will develop the Detailed Schedules for the WORK in close cooperation with
COMPANY. The WORK will be planned in detail in such a manner that construction activities
carried out by others engaged in the PROJECT are not affected.

The Detailed Schedules will be in a bar chart form based on logic network identifying a critical
path for the completion of the WORK.

The following Detailed Schedules will be developed and maintained by CONTRACTOR:

 Overall Network Schedule.


 Detailed Construction Schedule and S-curve.
 Two-month "Look-ahead" Guide Schedule.
 Two-weekly Work list.
 Other Schedules.

The Detailed Schedules will highlight all effects of proposed change to such schedules.

The Detailed Construction Schedule will show CONTRACTOR’s Overall Construction Schedule
down to the level of single activities.

The Detailed Construction Schedule will, in bar chart format, show the scheduled activities to be
performed in such detail, so that the actual performance of each and every of activity can be
quantified and monitored, taking into account the relative weightings in man-hours and
manpower histograms.

The Detailed Construction Schedule will be updated on a monthly basis.

The Overall graphical S-curve will be based on the Detailed Construction Schedule.

4.8.2 Progress Measurement

CONTRACTOR’s progress of the execution of the WORK will be measured and weighted in
accordance with the project Work Breakdown Structure (WBS) to be developed after award of
contract. Planned and actual progress measurement is obtained from total and installed physical
quantities converted in SMH through standard hours for each scheduled sub- construction
activities.
Total quantities are defined by engineering as total work volume of the project broken down by

PROJECT EXECUTION PLAN 42


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

WBS sub-construction activities.

Actual quantities are derived from engineering deliverables and scheduled to each construction
item (foundation, concrete, roofing, finishing, etc.) having the appropriate WBS codes.
The progress of the basic operations associated to each construction item will determine the
installed quantities.
Through the use of sub-construction activities hours, the ratio between standard man-hours
(SMH) gained from installed quantities and SMH determined from total projected quantities will
return the physical percent complete of the construction.
Since quantities and SMH are scheduled by WBS, the percent completed can be calculated
accordingly.
Total projected SMH will be updated when at least one of the following events will occur

 Significant changes of the volume of the work


 Progressive stages of the engineering (30%, 60% and 90% of each discipline progress)
 Better defined information/deliverables

Each update of the SMH will require a revision of the working level to be approved by Company .

4.8.3 Productivity Analysis

Standard manhours (SMH) a r e transformed, in planning phase, in expected manhours by


applying an estimated planned productivity factors (K).
The estimated productivity factor is determined for the CONTRACTOR and is based on
the historical records.
The ratio between the actual manhours (AMH) spent and the earned SMH of progress
gained returns the actual productivity factor.

4.8.4 Progress Reporting

After CONTRACT Award, CONTRACTOR will issue the following reports and documents:

 Weekly Progress Report.


 Weekly Safety Report.
 Weekly Report of Units Completed.
 Monthly Report.

After MOBILIZATION by CONTRACTOR to the JOBSITE, CONTRACTOR will issue the


following reports and documents:

 Daily Manpower and Equipment Report

PROJECT EXECUTION PLAN 43


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Weekly Progress Report

In its Weekly Report, CONTRACTOR will report the WORK completed to date in terms of a
percentage of the WORK. The progress will be further broken-down in various subjects, which
will be identical to break down of the progress weight factors as required by COMPANY.

CONTRACTOR will submit the weekly progress figures to COMPANY in the Weekly Progress
Meeting.
In addition, the Weekly Report shall in brief narrative to address the following matters:

 Safety and security.


 Milestones achieved last week (*).
 Milestones for next week.
 Reason for delay, if any.
 Reason for deviation of original schedule.
 Corrective actions or accelerated programs, as required.
 Average manpower by craft, including management and indirect staff.
 Engineering matters.
 Procurement/material matters.
 CONTRACTOR’s comments to general situation.
 QC matters.
 WORK progress.
 Planning – look ahead.
 Unusual occurrences, anomalies, areas of concern.

(*) Prior to mobilization by CONTRACTOR to the JOBSITE, this will primarily


relate to engineering, planning and preparation milestones achieved and prefabrication
progress.

Weekly Progress Meeting

A Weekly Progress Meeting will be held with the COMPANY at a fixed date and time,
during which the following topics (in general this will coincide with the contents of
CONTRACTOR’s Weekly Progress Report) will be discussed:

 Minutes of previous meeting.


 Safety and security.
 Milestones achieved last week.
 Milestones for next week.
 Reason for delay, if any.
 Reason for deviation of original schedule.
 Corrective actions or accelerated programs, as required.

PROJECT EXECUTION PLAN 44


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Average manpower by craft, including management and indirect staff.


 Engineering matters.
 Procurement/material matters.
 CLIENT’s comments to general situation.
 QC matters.
 WORK progress.
 Planning – look ahead.

Weekly Safety Report

In its Weekly Safety Report, CONTRACTOR will report the safety statistics of the
previous week with cumulative figures to date.

The following statistics will be reported

 Lost time incidents.


 First Aid Cases.
 Recordable Cases.
 Lost workday cases.
 Fatalities.
 Unusual occurrences, areas of concern.

CONTRACTOR will submit the weekly safety statistics to COMPANY in the Weekly
Progress Meeting.

4.9 OCCUPATIONAL HEALTH & SAFETY

CONTRACTOR IS FULLY COMMITTED TO ENSURING THE HEALTH, SAFETY AND


WELFARE OF ITS EMPLOYEES AT WORK AND TO PROTECT OTHER PERSONS,
INCLUDING THE GENERAL PUBLIC, AGAINST RISKS TO HEALTH, SAFETY,
ENVIRONMENT AND SECURITY ARISING IN CONNECTION WITH THE ACTIVITIES
OF THE CONTTRACTOR AND ITS EMPLOYEES AT WORK.

CONTRACTOR will constantly maintain the highest standards of Health, Safety, Environment
and Security in all its operations/activities, by promoting and ensuring safe work practices.
CONTRACTOR believes in the importance of healthy and safe working
conditions/environments and shall always ensure compliance by its sub-contractors.

PROJECT EXECUTION PLAN 45


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

CONTRACTOR will set up a HSE management system on the project as a subset of the
existing HSE-MS in the company. The HSE deliverables to be prepared on the project will
define and/or describe ways to demonstrate,

 Leadership and Commitment


 Policy and Strategic Objectives
 Organization, Resources & Documentation
 Manpower Resources & Competence Assurance
 Hazard and Effects Management
 Evaluation and Risk Management
 Standard, Procedures and Document Control
 Planning
 Implementation and Monitoring
 Audit and Management Review

CONTRACTOR goal for this project if awarded is zero fatalities, zero lost time injuries and
zero recordable incidents.. This shall be achieved by implementing standard HSE Procedure
during project execution.

In strict compliance to CONTRACTOR safety policy, all categories of workers shall be


provided with approved personal protective equipment throughout the period of shop
fabrication and site construction activities. The project HSE plan shall apply during all phases
of construction works.
At all times, CONTRACTOR HSE procedures as shall be approved by COMPANY shall
apply, namely:

a. HSE Plan
b. Security Plan
c. Medical First Aid plan
d. Emergency Response and Evacuation plan
e. Environmental Management Plan
f. Community affairs management plan
g. HSE meetings topics/ schedules
h. Job Hazard analysis/ HAZOP
i. Journey Management Plan
j. Waste Management procedure

PROJECT EXECUTION PLAN 46


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

k. Emergency Drill plan


l. Project Emergency bridging procedure

The following PPE shall be made available to the workers: -


a. Helmets
b. Coveralls
c. Safety boots
d. Eye goggles
e. Ear muffs/plugs

Specialized safety materials


f. Welding shields
g. Grinding visors
h. Welding hand gloves
i. Leather hand gloves
j. Welding aprons
k. General purpose hand gloves (Assorted)
l. Ear muffs
m. Signs
n. Harness belts
o. Respiratory mask
p. Dust mask

Safe and effective use of PPE shall be enforced.


CONTRACTOR will execute the WORK in accordance with all laws, rules, regulations and
recommendations issued by the relevant competent Authorities, by COMPANY and/or by
COMPANY pertaining to health, safety and welfare of all personnel engaged in the WORK
execution of the PROJECT and the environment.

It is the responsibility of CONTRACTOR to, at all times, carries out the WORK in a safe
manner. CONTRACTOR will take all necessary measures at to ensure that all rules and
regulations applicable at CONTRACTOR’s Facilities are strictly adhered to and that all-
necessary measures are implemented to avoid accidents.
CONTRACTOR will take all reasonable measures to prevent injury to CONTRACTOR’s
personnel and all other persons who may be affected by the WORK. This will include, but not
be limited to, erection and maintenance of reasonable safeguards, such as danger signs and
other hazard warnings, prominent display of safety regulations and the like.
CONTRACTOR will carry out the WORK in accordance with the requirements of:

i. COMPANY “CONTRACTOR’s HSE Requirements Manual”


ii Project HSE Plan.

PROJECT EXECUTION PLAN 47


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

iii COMPANYs’ regulations with regard to safety, health and environment.


Iv National and Local Authority requirements for health, safety and welfare of personnel.

CONTRACTOR is aware of the fact that its safety regulations on the PROJECT may be more
stringent than the requirements by applicable Law. The most stringent rules of the above-mentioned
documents as approved by COMPANY shall be used.
CONTRACTOR after CONTRACT Award, shall submit a signed copy of its HSE Requirements
Manual” and the PROJECT HSE manual, signed by CONTRACTOR on every page, as evidence
of acceptance thereof and full compliance with its contents.

4.9.1 Contractor Health, Safety and Environment (HSE) Program

After CONTRACT Award, CONTRACTOR will prepare and submit to COMPANY(CLIENT)


for APPROVAL, its detailed project specific Health, Safety and Environment (HSE) Program, the
purpose of which is to ensure that CONTRACTOR (and its SUBCONTRACTORS) will carry out
the WORK in accordance with the specific Health, Safety and Environment (HSE) requirements of
this CONTRACT.
The detailed project specific Health, Safety and Environment (HSE) Program, will include, but not
limited to, project specific HSE manual, project specific HSE plan, HSE procedures with sample
forms and flow diagrams.
The physical part of the WORK will not commence until the specific Health, Safety and
Environment (HSE) Program has been APPROVED by COMPANY.

4.9.2 Personnel Protective Clothing and Safety Accessories

CONTRACTOR will provide all its personnel with quality protective clothing including, but not
limited to, hard hats, steel toe capped safety boots, safety glasses with side shields, sturdy leather
gloves, protective coveralls and all other personal protection and protective clothing in
accordance with the requirements of this CONTRACT. Construction personnel shall not be
permitted to work in shorts, short sleeves, bare chested regardless of the height of the outside
temperatures. When working on heights, CONTRACTOR’s personnel will wear clicked-on safety
harness with chute.

4.9.3 Dedicated Safety Officer

For every two hundred of CONTRACTOR’s direct labor engaged in the WORK, CONTRACTOR
will assign to the WORK a dedicated Safety Officer. In the event of between two to four hundred
CONTRACTORS’s direct labor engaged in the WORK, CONTRACTOR will assign to the
WORK one dedicated Safety Officers.

4.9.4 Admission to the Jobsite, Safety Induction Course

CONTRACTOR's personnel will require passes for admission to the JOBSITE, in accordance with

PROJECT EXECUTION PLAN 48


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

PROJECT security procedures. In order to obtain said passes, each of CONTRACTOR’s personnel
will be required to attend a safety induction course.

4.9.5 Reporting of Unsafe Situations, Incident/Accident

CONTRACTOR will not permit a hazardous, unsafe, unhealthy or environmentally unsound


condition or activity over which it has control, to arise at its facilities.
If CONTRACTOR becomes aware of any hazardous, unsafe, unhealthy or environmentally unsound
condition at its facilities, CONTRACTOR will immediately notify COMPANY thereof, and take all
necessary steps to eliminate, terminate, abate or rectify the condition.
In the event of any incident, personal injury or accident arising out of the execution of the WORK,
CONTRACTOR will immediately notify COMPANY in accordance with the applicable PROJECT
procedure.

4.9.6 Safety Walks

In addition to independent weekly meetings, COMPANY shall be required to make “safety


walks” at and around COMPANY's facilities where the physical part of the WORK is
carried out.
COMPANY will take immediate corrective action in the event of any unsafe situations or
practices noted by COMPANY.

4.9.7 Joint CONTRACTOR / COMPANY Audits

Upon contract award, the HSE Department through the Project Manager shall invite
COMPANY responsible department for an audit of CONTRACTOR plants, equipment,
facilities proposed for the project. The result of this audit shall determine the date of
mobilisation for fabrication and site construction work.
Where minor deficiencies exist with respect to the audit, corrective action shall be implemented
and a follow-up audit executed.

Where COMPANY is satisfied with the safety audit, mobilization certificate shall be issued to
CONTRACTOR for initiation of shop fabrication and site construction. Subsequently, after
mobilization to site, CONTRACTOR responsible officers shall accompany COMPANY
representative on site audit.

4.9.8 CONTRACTOR Internal / Line Supervisors Audit

Frequent and regular inspections of machinery, plant, equipment, tools, material, work sites and
other facilities involved on the project will be made to eliminate hazards and to assure that all
conditions are in accordance with applicable requirements. Any unsafe or possible hazardous
situations will be reported and immediate steps taken to comply fully with the appropriate safety
standards.
Daily observations on safety shall be recorded, deficient equipment, shall be taken out of service

PROJECT EXECUTION PLAN 49


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

until either repaired or replaced. The actions taken shall be recorded in the equipment register.
Management HSE audit shall be held once every month. Members of the team shall include: The
Project Manager, Construction Manager, Site Construction Superintendent, HSE Lead, QA/QC
Lead etc. The team shall inspect all equipment and facilities using a standard inspection checklist.
The audit findings shall be documented and distributed to all action parties for any possible
corrective action.

A follow-up audit shall then be arranged to ensure that points raised in the previous audit have
been complied with.

Close-out reports shall be written and issued by the site HSE Lead if the conditions spotted and
highlighted in the audit report have been remedied.

Audit findings will be discussed in both site and Management HSE meetings with a view to
generating the awareness and eliminating the hazards form the work areas.

4.9.9 Toolbox Meetings

Tool box or safety meeting shall be held daily by all workforces. A meeting per work team
Shall be encouraged to discuss the day’s upcoming operations, highlight the major hazards,
which will be encountered and the precautions to be taken. (Job Safety Analysis)

4.9.10 Incentive Scheme

An incentive scheme, set up to encourage and reward safe practices shall be available on the
project. Giving incentive, for good safety performance, CONTRACTOR believes shall boost up
the already attained safety awareness / standards amongst workers. Such motivations include: -
 Man-hour Awards (for man-hours without LTI)
 Safety Slogan Awards
 Individual Safety Performance Award (which will be given Monthly)
 Non Accident Bonus.
 Crew Safety Performance award.
The HSE Department shall also issue certificate of merit every month to workers adjudged with
outstanding Safety Performances.
All safety matters shall be coordinated by the HSE Department.
Please refer below to CONTRACTOR HSE procedure in section 8 of this tender:
This procedure is attached for reference only. Specific project procedure will be submitted
for COMPANY's approval after contract award.

PROJECT EXECUTION PLAN 50


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.10 QUALITY MANAGEMENT PROGRAM (9)

Makais Synergy Limited is certified ISO 9001.


All the activities will be done fully in compliance with the prescription of ISO 9001.
Dedicated project quality procedure will be prepared at the beginning of the project in
accordance with CONTRACTOR Quality Manual.
CONTRACTOR shall be responsible for controlling the WORK.
CONTRACTOR will carry out the WORK in accordance with ISO 9000, requirements for
Quality Assurance and Quality Control.
CONTRACTOR will use its own standard forms for Quality Control, Inspection, Acceptance
and record purposes.
CONTRACTOR will compile, prepare and submit in accordance with the requirements of this
CONTRACT, as further detailed below, Quality Control documentation to COMPANY
progressively as and when portions of the WORK have been completed by CONTRACTOR,
and in addition, upon completion of the WORK.

4.10.1 CONTRACTORs Quality Assurance and Quality Control (QA/QC) Program

After contract Award, CONTRACTOR will prepare and submit to COMPANY for APPROVAL,
its detailed project specific Quality Assurance and Quality Control (QA/QC) Program, the
purpose of which is to ensure that COMPANY will carry out the WORK in accordance with the
Quality Assurance/Quality Control requirements of the CONTRACT.

The detailed project specific Quality Assurance and Quality Control (QA/QC) Program will
include, but not be limited to, project specific quality manual, project specific quality plan,
procedures with sample forms and flow diagrams. The project specific Quality Plan will address
in depth the manner in which CONTRACTOR will assure and control the WORK.

CONTRACTOR shall be responsible for developing procedures applicable to control of the work.
Some of the procedures to be developed shall include but not limited to the following:

 Handling of COMPANY issued drawings and documents.


 Organization i.e. organization chart, positions, names of responsible persons including
resumes, and responsibilities.
 MATERIAL control.
 Prefabrication procedures.
 Testing procedures.
 Surface preparation and painting procedures.
 Detailed Inspection, testing and related reporting.
 Quality Control Record forms.
 Material and Equipment Certification.
 Compliance with Authority requirements.
 Handover/turnover of the completed WORK.
 Engineering Design

PROJECT EXECUTION PLAN 51


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Procurement
 Manufacturing
 Manufacturers PTT, FT, FAT and UAT Tests if applicable
 Dock side Receiving & Clearance - Nigeria
 Site Clearance & Preparation
 Execution of Civil Work
 Painting/Surface Finishing
 Installation of Mechanical Equipment
 Completion of Construction
 Pre-Commissioning - Construction/Commissioning Teams Integration
 Commissioning
 Note:
CONTRACTOR will incorporate any forms used by COMPANY into its QA/QC manual.
Procedures will detail the personnel, equipment and services that CONTRACTOR i n t e n d s to
use to carry out these specific activities.
As far as possible, such procedures will be based on CONTRACTOR’s established systems and
procedures. Where applicable, CONTRACTOR will ensure that its procedures are compatible with
COMPANY’s procedures.
The procedures will include contingency plans, contingency procedures and details on back-
up equipment. The procedures will contain a comprehensive description of how
CONTRACTOR’s activities will interface and be coordinated with operations to be
performed by others.

4.10.2 Contractor’s Quality Assurance/Quality Control Staff

CONTRACTOR’s organization will include Quality Assurance/Quality Control staff that will
be responsible for the first line of inspection and the preparation and submission to COMPANY
of the required Quality Control documentation.
The number of CONTRACTOR’s staff engaged in Quality Control will be sufficient in terms
of number and experience, as to be able to carry out all inspection, to prepare timely all
required Quality Control documentation and to maintain all Quality Control records,
commensurate with the extent and nature of the WORK in accordance with the requirements of
the CONTRACT to COMPANY’s entire satisfaction.

4.10.3 Inspection

Immediately after CONTRACT Award, a "pre-inspection" meeting will take place, in which
the following inspection matters will be addressed in detail:
 Introduction of CONTRACTOR QA/QC Personnel assigned to the WORK.
 Introduction of COMPANY’S QC Staff and Inspectors.
 Quality Philosophy.
 CONTRACTOR's Quality Assurance and Quality Control Program.
 Compliance with the requirements of the local Authorities.
 Inspection Test Plans (ITP), defining the minimum of inspection, test and examination

PROJECT EXECUTION PLAN 52


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

activities to be carried out by CONTRACTOR


 CONTRACTOR Personnel Qualification Procedures, including Welders, Inspectors, NDE
Personnel.
 Presentation of the List of Documents required from CONTRACTOR for review and
comment.
 Inspection traveller procedure. (If applicable)
 All Procedures applicable to the discipline of the COMPANYS work activities.
 An example of COMPANY's Inspection and Test Plan (ITP), which will be used by
COMPANY’s, shop Inspectors. This identifies COMPANY's inspection points and the nature
and extent of inspection that COMPANY will carry out.
 Forms that COMPANY may use for recording certain QC data if COMPANY has no forms
available of its own.

Testing and examination at CONTRACTOR’s prefabrication shop (if applicable) will be carried
out by CONTRACTOR under its supervision and responsibility.
COMPANY's Shop Inspectors and QC staff will at all times have free access to COMPANY’s
prefabrication shop(s) and associated offices to inspect MATERIALS, documents and to witness
and monitor all testing and examination carried out by CONTRACTOR will give all
accompaniment and assistance as required by COMPANY.
CONTRACTOR will notify COMPANY in a timely manner prior to any inspection to be
witnessed by COMPANY. In the event that an inspection, test and/or examination cannot be
carried out at CONTRACTOR’(s) shop, COMPANY may consider preliminary acceptance.

CONTRACTOR will ensure that any of its expatriate personnel engaged in the WORK is in
compliance with the applicable immigration laws and that such personnel is in possession of a
valid residence and valid work permit. Details of such work permits will be submitted to
COMPANY on request.

4.10.4 Close out report


Refer to attachment 4.10.4 Close out report of previous projects

4.11 DOCUMENT CONTROL MANAGEMENT

DCC is the recipient and custodian of all Engineering, Fabrication and Construction
documents generated by CONTRACTOR as well as those received from COMPANY and
other stake holders of the project such as subcontractors, vendors etc

CONTRACTOR’s Document Control shall carry out its responsibilities on the project in
accordance with standards and procedures as agreed by CONTRACTOR and the COMPANY.

A system shall be established by means of an approved procedure to ensure that the following
are carried out:
 Setting-up and management of project document database.

PROJECT EXECUTION PLAN 53


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Documentation of Engineering Project documents, drawings and Vendor Prints etc.


 Checking to ensure that all documents issued comply with the details of the document
numbering procedure designed for the project.
 Transmitting and tracking of Engineering Project documents/drawings, except legal
document.
 Maintaining a document Register.
 Maintaining electronic and hard copy records of Project documents: drawings, Vendor Prints,
reports and transmittals etc.
 Reproducing Project documents and drawings when necessary.
 Keeping active copies of Project documents and drawings.
 Preparation of periodic reports on Project documents and progress.
 Ensure that a master copy of each document is maintained within DCC.
 Updating of project database with document revision status on regular basis
 Quality assurance.
 Archiving of project documents.

4.11.1 Document Deliverables/Activities

Document Control Activities on the project shall include but not limited to the following:
 Administration of all the project-related engineering documentation.
 Co-ordination of all other peripheral document control functions.
 Liaison and interface with COMPANY;
 Creation and maintenance of a central file for the project

DCC deliverables are:


 Master Document Register (MDR)
 Document Control procedure
 Document Distribution Matrix
 Document Numbering and Formatting Procedure
 Input to Weekly and Monthly/Close-out Report

4.11.2 DCC Software Requirement:


The following software for DCC shall be applicable during the project execution phase:
 Microsoft Office (Excel, Word, Access)
 PDF Adobe Professional
 Internet connectivity
 COMPANY’’s Electronic Document Management System (EDMS)(If applicable)

PROJECT EXECUTION PLAN 54


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.11.3 DCC Electronic File Transfer:

CONTRACTOR’s DCC shall be equipped to handle electronic file transfer between her Project
Team and COMPANY in a variety of ways:
 E-Mail: Small-size files could be exchanged as attachment to e-mails.
 FTP: Large files could be exchanged using FTP facility where such a facility is provided by
the Client for a project (EDMS).
 Scanner: Documents and/or Drawings could be scanned and converted to PDF, JPEG or any
other approved format specifically requested by the Client. They will be zipped and
forwarded to the Client.
 Electronic Storage Discs: CONTRACTOR shall install the facility to download electronic
files on to CDs, DVDs or USB Discs as part of the final packaging of deliverables to clients
as well as in-house safekeeping tradition.

4.11.4 DCC Quality System

Based on COMPANY’s approval, to maintain a high design integrity and quality, all
documentation on the project shall be issued at several levels of completion as follows:
 Issue for Disciplinary Check (IDC)
 Issue for Review (IFR)
 Issue for Approval (IFA)
 Approved for Construction(AFC)
 Issued for Information

4.12 INFORMATION TECHNOLOGY MANAGEMENT

At the inception of the project, a well-coordinated network of existing IT infrastructure will be


put up while meeting the specific needs of the project. This plan shall be submitted to
COMPANY within 30 days of the effective date of contract. The plan shall include voice and
data networking via LAN and WAN, e-mail, file transfer, and internet use in the fabrication
yard, construction site and other major location, in addition to COMPANY’s provided facility.

CONTRACTOR has a state-of-the art designed office complex equipped with modern facilities.
Some of these facilities will be available for use during project execution.

PROJECT EXECUTION PLAN 55


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

CONTRACTOR shall use state of the art computers and 3D software in its CAD design facilities
for producing accurate, high quality plans, sections, details and isometrics. The production of
these products is highly automated and accurate. Any changes to the 3D model shall be
automatically changed in all drawings. Bills of materials, Clash Detection, Real time Render
Walk – thru and isometric shall be generated at any time during the 3D modeling process.

4.13 COMMUNICATIONS

There shall be high frequency radio link between COMPANY Worksite, fabrication yard and
COMPANY representatives.

4.14 INTERFACE MANAGEMENT

CONTRACTOR is aware of the importance of communication and obtaining permits for all
activities to be carried out during the course of construction works. Based on CONTRACTOR
previous experience, an experienced Engineer will be dedicated to follow up all interface
management issues with COMPANY, other contractors and COMPANY operations personnel.
Before any work with great impact is carried out, adequate notice shall be given; especially in
cases of shut downs and simultaneous operations.
CONTRACTOR shall abide by COMPANY’s procedure on SIMOP and shall carry out adequate
orientation of her staff on various interface issues.

4.15 RISK MITIGATION

There are several risks identified during various stages of the project (refer to section 2.2 above),
which includes, but not limited to, Community disturbances, logistics, construction accidents,
etc.
A careful study of the community requirement shall be carried out in conjunction with
COMPANY’s Community Liaison Officer to address all issues relating to community affairs.
Before any activity is carried out, there shall be hazard analysis to identify any hazard associated
with such work item and find a way to mitigate such hazard.
CONTRACTOR shall introduce the use of colour cards to identify the number of people inside
the work area at any point in time in case of any emergency.

PROJECT EXECUTION PLAN 56


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Further evaluation and identification of various risks and hazards shall be submitted in due
course.

4.16 SECURITY

CONTRACTOR Policy on security, as contained in the HSE Policy Statement, can be


summarized as follows:
 To ensure adequate security of personnel and assets on site.
 To ensure workable and effective civil unrest procedures, put in place at all times.
 To ensure that procedures are developed to minimize the risk of robbery, and assaults, for
example in the movement of equipment, materials, and workers payroll.
 Guard House must be provided and adequate working tools provided for the security
personnel.
 The site shall be fenced to ensure protection of the site from intruders.
CONTRACTOR security arrangement shall be in line with COMPANY security operations.
CONTRACTOR security network shall be in constant contact with COMPANY security to
ensure adequate information dissemination on security on site. At all times, high level of
security shall be maintained throughout all stages of the project as follows:
 Mobilization stage
 Worksites other than COMPANY facility
 Campsite other than COMPANY facility
 Transit
 Cash movement
 Materials and equipment movement
 Personnel movement
 Control and protection of personnel in sites other than COMPANY facility
 Armed attack
 Communication
 Security tools equipment movement
 Training and drills.
CONTRACTOR shall utilize services of Private Security Company within the worksite and
Temporary Camp Facility.

PROJECT EXECUTION PLAN 57


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

4.17 SUSTAINABLE COMMUNITY DEVELOPMENT

CONTRACTOR will appoint a dedicated full time Community Interface officer. The
Community Interface officer will have full responsibility for community & third party
(NGO’s, interface and will report directly to the Project Manager in this regard.)

Project Manager and COMPANY representative will develop and implement community
interface management procedures for the proactive management of relationship with host
communities and government throughout the phases of the WORK. CONTRACTOR
will ensure SUB-CONTRACTORS comply with these procedures.
CONTRACTOR will strictly implement any COMPANY approved decisions reached
with communities to ensure hitch-free work environments.

4.18 NIGERIAN CONTENT PLAN

CONTRACTOR will maintain a Nigerian content plan throughout the contract duration.
This Plan will document all aspects of the CONTRACTORs strategy for achieving the
minimum commitment to Nigerian content in accordance with the contract and the
Nigerian Content Matrix specified in the technical bid.

The plan shall include details of the following:

 Specific proposals to prioritise and maximise the use of labour, goods and services and
equipment procured from Nigerian sources;

 The manner by which Nigerian owned companies will be encouraged to compete for
WORK under the CONTRACT;

 The proposed utilisation of Nigerian labour, goods and services for engineering design
elements of the WORK;

 The proposed utilisation of Nigerian labour, goods and services for fabrication and
assembly elements of the WORK;

 The proposed utilisation of Nigerian labour, goods and services for construction,
installation, pre-commissioning and commissioning elements of the WORK;

 The proposed utilisation of Nigerian representatives and/or agencies, to import those


goods and services and equipment originating from outside Nigeria;

 The proposed utilisation of competent Nigerian manufacturers and fabricators as


appropriate in the manufacture, assembly and fabrication of component parts;

 A comprehensive training and development plan covering the establishment of training

PROJECT EXECUTION PLAN 58


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

facilities and externally accredited training programmes for the development of skills
and competence amongst local labour hired for the WORK.The programmes shall cover
all skills required for the WORK, specifically including procurement, logistics,
fabrication, construction, inspection, testing, commissioning and project management;

 Proposals for the employment of local trainees on the WORK for a minimum of six
months after their training are complete or until COMPLETION, whichever is sooner,
subject always to such trainees meeting the required standards and their skills being
required for the WORK.

4.19 TRAINING AND TECHNOLOGICAL TRANSFER

During the execution of THE ENGINEERING, CONSTRUCTION, INSTALLATION


AND REHABILITATION OF THE CIVIL INFRASTRUCTURES AT EKULAMA 1&2,
AND AWOBA FLOWSTATIONS IN OML 24 OML FOR NEWCROSS EXPLORATION
AND PRODUCTION LIMITED/NNPC UPSTREAM AND INVESTMENT
MANAGEMENT SERVICES
CONTRACTOR (MAKAIS/BIL/WAV) shall organise and carry out training Programmes under
all but not limited to the following specialized areas:
 HSE Awareness
 Welding
 Scaffolding
 Painting
 Detailed Engineering Design
 Concrete work,
 Fabrication

The proposed training plan shall be in accordance with NCDMB requirements for trainees to
be engaged by MAKAIS/BIL/WAV throughout the duration of the project.
CONTRACTOR shall prepare a series of operating plans and procedures in accordance with
this Project Execution Plan to achieve the above objectives.

PROJECT EXECUTION PLAN 59


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

5.0 ENGINEERING(Method statement for execution of engineering activities)(1)

5.1 Approach to Work


The execution of detail engineering design shall be executed by Makais Synergy Limited. Makais
synergy is an Indigenous ISO 90001 company. Makais has executed several Engineering
Procurement and Construction (EPC) projects for several companies as follows:

5.1.1 Development of Detail Engineering Design

The development of the project will commence with Detail Engineering Design (DED). The scope
of this phase is to consolidate the documents/drawings issued with invitation to tender (ITT), to
complete the definition of the main engineering choices, to freeze studies and to issue the
requisitions for the major equipment of the facilities.
The CONTRACTOR (Makais and Consortium’s partners) shall ensure that all the necessary
engineering and design activities are planned and executed and that the multi-disciplined input
required for the various activities is provided as necessary. Errors or Omissions in design criteria,
specifications, data and information or the miss-description of WORK, which is necessary to carry
out the intent thereof, or which is customarily performed, shall not relieve the CONTRACTOR from
performing such omitted or miss-described WORK, but such WORK shall be performed by the
CONTRACTOR, as if fully and correctly set forth and described therein, and at CONTRACTOR's
cost.
The CONTRACTOR shall obtain a review and approval from COMPANY for all deviations from
such Criteria, Specifications, Data and Information prior to incorporating any such deviation into the
final design. CONTRACTOR may Sub-contract any aspect of its WORK to any
SUBCONTRACTOR upon client Approval. However, CONTRACTOR shall be responsible for the
supervision and management of the SUBCONTRACTOR, and accountable for the WORK of the
SUBCONTRACTOR.

5.1.1.1 Outline of the Detailed Engineering Scope of Work

The general outlines of this Engineering phase of the WORK shall include all but not limited to the
following:
• Review of FEED documents and development of DED engineering documentations within
the scope of work.
• Provision of all follow-on engineering personnel required for the performance of the
WORK.
• Review of all construction and installation drawings
• Verification of existing site conditions including surveying the construction sites and
performance of geotechnical testing and any other investigations related to establishing the
conditions of the construction SITES, establishment of the as-built status prior to the
commencement of the WORK.
 Update and validation of all vendor related engineering documents with nominated
Vendor data.

PROJECT EXECUTION PLAN 60


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

• Production of detailed construction drawings, datasheets, bills of material, detail technical


specifications and requisitions for all materials and equipment, including regular update of
equipment lists, drawing registers and VENDOR data registers.
• Review and approval of SUBCONTRACTOR / VENDOR drawings and documentation and
the compilation of VENDOR data manuals.
• Preparation of all pre-commissioning,test/inspection plans/procedures as well as the
commissioning and operation manuals.
• Preparation of all As-Built documentation including survey and installation drawings and
certification documentation for hand over to COMPANY.
• Provision of general and specific engineering support during Procurement, Construction, and
Installation
• All related activities to ensure completeness and adequate handover of the complete scope.
 Carry out Interface Engineering works to align with existing related projects and other
aspects of works such as fabrication and construction

5.1.1.2 Geophysical/Geotechnical Investigation and Report

The CONTRACTOR will engage the services of a subcontractor to carry out


Geophysical/Geotechnical investigation. Findings from the investigation will be applied to the Detail
Engineering Design activities. Geotechnical survey will cover all but not limited to the
following:
• Review all COMPANY-provided survey and geotechnical information, acknowledge
acceptance and perform all additional route survey and geotechnical work necessary to
ensure completion of detailed engineering design.
• Geophysical and Geotechnical survey along the proposed pillars of the buildings ,
foundation of septic tanks, overhead tanks etc platform corridor, roads as defined by the
Project Specifications and Scope of Work.
• Perform all detailed field survey work necessary for the Engineering design and
Construction of the facilities.
• Carry out a complete review of the field layout and general arrangements of the facilities
necessary for Engineering design and Construction.
• Carry out detailed site survey, taking potential measurements and establishing the soil
resistivity, textures, profile pH values and height of the water table etc..

PROJECT EXECUTION PLAN 61


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The scope of Geophysical/Geotechnical investigation shall include all but not limited to the
following:
a. FIELD WORKS
Field work shall include but are not limited to:
 Mobilization of personnel and equipment.
 Field identification and survey for boring position.
 Carry out as a minimum the under listed field test as applicable along the right of way of
pipeline

a. Boring and soil sampling.

b. SPT (Standard Penetration Test).

c. CPT (Cone Penetration Test).

d. Vane shear test (at borehole location).

e. In-situ Density.

f. Soil electrical resistivity measurements.

g. Soil thermal resistivity measurements.

h. Ground temperature measurements.

The SUB-CONTRACTOR may be requested by CONTRACTOR to continue boring to make sure that
the soil has the same property or is uniform and able to withstand the building loads.

b. LABORATORY TEST
Laboratory test will be conducted by the SUB-CONTRACTOR’s soil laboratory and should
conform to Eurocodes and International Standards.
Test of representative samples shall include but not limited to the following:
a. Natural moisture content and dry unit weight.

b. In-situ density.

c. Sieve analysis.

d. Atterberg limits.

e. Compaction test.

PROJECT EXECUTION PLAN 62


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

f. Ground water gravity.

g. Swell test.

h. Specific gravity and grain analysis for cohesion less soil.

i. pH.

j. Soil shear modulus, G.

k. CBR.

l. Oedometer test.

m. Soil resistivity test.

n. Modulus elasticity.

o. Unconfined and Triaxial compression test.

p. Consolidation test.

5.1.1.3 Engineering Software (3)

The CONTRACTOR shall utilize software for the job from the list below for execution of engineering
design

S/N Activities Applicable Software

1 3D-Models PDMS, Navis works

2 Drawings drafting AUTOCAD,

3 Architectural design and drawings from AUTOCAD, Revit


the FEED drawings

4 Civil / Structural Design, Structural Stadpro,


Design Analysis Full Package from the
foundations (piling) to superstructures

5 Geotechnical Investigation to obtain To be handled by Makais’ preferred client’s approved


engineering properties of sub-soil contractor

6 Process Engineering and Design Basis Microsoft office

PROJECT EXECUTION PLAN 63


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

for water treatment facilities

7 Process Engineering and Design Basis Microsoft office


for sewage treatment facilities

8 Corrosion Studies: Materials / Corrosion Microsoft office.


Engineering activities and deliverables

9 Complete Mechanical Design Microsoft office, PV Elite, Hourly Analysis Program


(HAP) for HVAC system

10 Instrumentation and Control System Microsoft office.


Design

11 Electrical Engineering Design ETAP, SKM, Microsoft office

12 Telecommunication design Microsoft office and CAD

13 Information and data management Microsoft Office (Excel, Word, Access), PDF Adobe
system. Professional
COMPANY’’s Electronic Document Management
System (EDMS)(If applicable)

14 Quality control systems. Microsoft office.

Other Software to be used shall be listed in the CONTRACTOR’s proposal for COMPANY review and
approval before commencement of WORK.

5.1.1.3.1 Ownership of Valid Software (3)

For ownership of software refer to attachment 2.4.3.

5.1.1.4. Engineering Design Project Management


The proposed organization chart for the execution of all the phrases of the project including
engineering is presented in Attachment 2. This shows how the project will be organized and the
resources to execute the Work.
CONTRACTOR shall provide office for the CLIENT representatives during the execution of the
detail-engineering phrase of the project at its office if required.

5.1.1.4.1Meetings/Reviews(5)
The following meetings shall be observed in executing this Project:

PROJECT EXECUTION PLAN 64


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Administrative/Technical Kick-off Meeting(1NOS)


 Bi-weekly Progress/Management Meetings
 Weekly Regular Discipline Engineer meetings (at the discretion of each
CLIENT/CONTRACTOR
discipline engineer)
 Design Review (60%, 90%)
 Constructability/Installation Review (1 NOS).
CONTRACTOR shall organize and scribe to all the above meetings. CONTRACTOR will host
the bi-weekly progress meetings at its facility while CLIENT will host kick-off meetings and
formal design reviews at its facility unless otherwise agreed by both parties.
CONTRACTOR shall issue draft Minutes of Meetings within 48 hrs. of each meeting.

5.1.1.4.2 Project Quality Management System during engineering


To manage the quality of work, CONTRACTOR shall apply its ISO 9001: 2015 Quality
management system, with its full complement of manual and procedures to assure and control the
quality of work.
CONTRACTOR shall put in place effective policies, procedures and systems covering all aspects
of the work and shall ensure that all HSE policies are adhered to.
CONTRACTOR shall have in place an effective change management system for all aspects of the
work.
CONTRACTOR shall establish a programme for audits throughout the course of the WORK to
ensure that the respective quality management systems and procedures are fully effective and are
being strictly adhered to.
The approved Project Quality Plan shall be the principal document that outlines the Project
quality management system and practice. And this will be updated during the execution of the
Project as necessary.
Quality reviews shall be held monthly to monitor project progress and ensure effectiveness of the
Quality Management System. Formal Reporting to CLIENT shall also be done monthly as part of
the project monthly report.

5.1.1.4.3Control of Documents during engineering


Documents and Data shall be controlled in accordance with the requirements of the Project
Document Controls Plan.
All project documents, including changes/revisions to same shall be prepared, checked, approved,
retained on file, and issued in a controlled, systematic manner.
Project documents shall be prepared, checked, and released by authorized personnel, in accordance
with applicable procedures.

PROJECT EXECUTION PLAN 65


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Reference or information documents and all effective changes/revisions are retained on file and or in
E-copy readily available to personnel performing the work. Such documents include:
 National / International codes, standards, specifications
 Nigerian statutory / regulatory requirements
 Project Specification and Standards
 Other company specifications and requirements as delineated in the MAKAIS/CLIENT
Contract and the Technical Handover Package.

5.1.1.4.4Control of Records
Records shall be identified, filed, archived, protected, retained and retrievable in accordance with the
Project Document Controls Plan.
All software to be used on the project shall be controlled accordingly. Only required software
demanded by disciplines shall be installed on workstations for such disciplines.

5.1.1.4.5Project Monitoring and Controls

CONTRACTOR’s Project Controls Team shall monitor and control schedule development, project
control change management, tracking and analysis of progress and expenditure, and development of
progress reports, based on the existing schedule. However, schedule review and update where
necessary shall be done to ensure accurate progress monitoring.
Makais shall also perform the following for the project:
 Establish project controls procedures and reporting medium in accordance with CLIENT
requirements, as outlined within this Scope of Work and as advised directly by the CLIENT.
 Ensure man-hours and costs are monitored, tracked via timesheets, and reported based directly
upon the agreed Engineering Deliverables; timesheets must specifically correlate to a specific
deliverable.
 Prepare weekly and monthly progress reports throughout project life cycle, which shall
incorporate the following:
 Progress man-hour tracking and reporting based upon agreed Deliverables (Period &
Cumulative: Planned, Actual, Deviation from Plan in man-hours and %).

PROJECT EXECUTION PLAN 66


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Cost monitoring, tracking via timesheets & invoices, and reporting shall be based upon
agreed Deliverables (Period & Cumulative: Planned, Actual, and Remaining Budget in
required monetary units / equivalents and %).
 Progress Reports shall reflect reporting Period and Cumulative Project status,
incorporating both timesheet and invoiced reconciliations.
 Cost tracking shall reflect reporting Period and Cumulative project status, incorporating
both timesheet and invoice reconciliations.
 A bar chart programme in weekly periods showing the duration of the main activities
required for carrying out the works and achieving timely completion of the project shall
be produced.
 A work programme in weekly periods, showing the order of precedence and method by
which, it is proposed to carry out the work considered necessary to achieve such targets.
 A schedule in weekly periods of numbers and grades of project personnel shall be
produced.
 Makais shall develop MS Excel based Man-Hour Tracking Spread sheet aligned with CTR
submittal and CLIENT Scope of Work and depicting man-hours per person per deliverable,
which shall include the following:
 Charge Code
 Weekly Master (Summary), which shall include:
 Respective Column for Budgeted Man hours
 Respective Column for Actual Man hours
 Respective Column for Remaining Man hours
 Man-Hours worked per week (daily with dates)
 Total Man-Hours
 CONTRACTOR’s Weekly Summary Timesheets shall be based upon project management
activities; and shall clearly indicate the activities; shall be subdivided by Employee ID No.
and discipline; and shall be provided to Project Controller in hard copy and MS Excel for
validation and approval by CLIENT Project Manager.
 CONTRACTOR’s shall prepare and submit to the CLIENT Invoices for Man-hour based on
approved timesheets and incurred Reimbursable Cost applying the appropriate Contract.

PROJECT EXECUTION PLAN 67


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Project Monitoring and Control activities take place in parallel with Project Execution activities so
that, while the project work is being executed, the project is being monitored and controlled by
implementing the appropriate level of oversight and corrective action.
The project is observed and measured regularly against the project plan to ensure that the project is
within acceptable variances of cost, schedule and scope, and that risk and issues are continually
monitored and corrected as needed.
The main purpose of monitoring and controlling activities is to be proactive in finding issues ahead
of time and taking corrective action. Corrective action can require revisiting Planning Processes and
updating the Project Management Plan as needed with the goal of bringing the project back in line
with project objectives and constraints and improving future execution to avoid repeating the same
issues.

5.1.1.4.6 Monitoring and Controlling Project Work

The Project Controls Team shall collect, measure, and disseminate performance information, and
assesses measures and trends to forecast potential items requiring corrective action. This includes
monitoring project risks/variations and ensuring that they are being managed according to the
project’s plans.

5.1.1.4.7 Schedule Control

The Project Control Engineer will monitor and control changes to the project schedule in the
Schedule Control Process to bring the Schedule back to track if there is deviation from original plan.
Alongside the Resource-loaded Level 4 Schedule, the team Lead Planning/Scheduling Engineer shall
prepare, update, maintain and monitor a deliverable-man-hour driven “Progress Measurement
System” (PMS) based on the review cycle gates for Start, Issue for Interdisciplinary check (IDC),
Issue for review (IFR), Issue for Approval (IFA). Approved for Construction (AFC).
The PMS shall be developed in a Microsoft Excel Spreadsheet and updated regularly. The earned
percentage per deliverable shall be pulled and migrated to the Resource-loaded Level 4 Engineering
Schedule produced using Microsoft Project, which tells whether the Project/deliverables/disciplines
are behind Schedule, on Schedule, or ahead of Schedule. The following outputs are also from the
PMS: Planned and Actual S-Curve and Planned and Actual Histogram.
Expected Outputs from Schedule Control include:

PROJECT EXECUTION PLAN 68


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Updates to the schedule model data and baseline


 Performance measurements
 Requested changes.
 Recommended corrective actions
 Activity list and activity attribute updates
 Updates to the Project Management Plan.

5.1.1.4.8 Cost Control


In the Cost Control process, the Senior Cost Controller will monitor and control costs and changes to
the project budget. CONTRACTOR’s Team shall prepare and update Work Breakdown Structure,
and Cost Tracking Resource sheet to ensure effective monitoring and controlling of Cost budget on
the project. All Cost related Invoices of this Project shall be prepared and submitted by
CONTRACTOR’s as duly required/stipulated in the Work Contract, to the CLIENT for payment
within Forty (45) working days from the date of submission.
Expected Outputs include:
 Cost estimate updates
 Cost baseline updates
 Performance measurements
 Forecasted completion
 Requested changes.
 Recommended corrective actions
 Updates to the Project Management Plan.

5.1.1.4.9Performance/Progress Reporting/measurement
CONTRACTOR shall provide accurate and timely Reports advising status of project management
and other deliverables.
Reports shall contain details on all aspects of the Contract performance over the reporting period
and provide an up-to-date progress and overall status of Work along with a monthly calendar of
anticipated events and meetings including Schedule and/or proposals for remedial action, revised
plans, schedules or projections as may be required by CLIENT.
CONTRACTOR shall monitor progress of the work against agreed schedules with progress based
upon aggregation of a weighted Maser Document Register (MDR).

A Quality Engineer will be appointed to make sure that quality of documentations will meet

PROJECT EXECUTION PLAN 69


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

CLIENT’s requirements. All activities will be performed according to the ISO 9001 certified
quality system, (Makais ISO 9001 certificate is available upon request) and in strict compliance
with CONTRACTOR’s policy which states that “any service undertaken by CONTRACTOR
shall be performed to the highest professional level, and shall be carried out in such manner that:
• The Client’s needs and requirements are understood and complied with.
• The results meet professional standards.
• The agreement is fulfilled.
• Environmental, social and health & safety aspects are considered”.
CONTRACTOR shall set up a project team to execute the project as shown on the attached
Organogram (Attachment 2).
The Project Manager in liaison with the Discipline Leads shall set up the Project Execution Plan
to guide all team members on the execution of the project.
Site visit to EKULAMA 1 and EKULAMA 2 will be arranged to verify the condition of the
acquired land for the project.
Progress Measurement
CONTRACTORs shall implement a Project Performance/Progress Measuring System
fourteen (14) days of contract award, CONTRACTOR’s shall report back to CLIENT on bi-
weekly basis. The system shall provide indications of the Project and disciplines performance and
productivity.

5.1.1.4.10 Project Manager Roles During Detail Design.

The responsibilities of the Project Manager shall include, but are not limited to those contained in the
following statements:
Responsible for the overall scope of work within the Project, with specific responsibility for:
 Reviews and approval of Engineering methods and procedures.
 Cost budget management.
 Leading safe behaviour and supporting open communication regarding safety issues.
 Supervision of all personnel seconded to him/her.
 Direct liaison with Managers/Supervisors who oversee Project services, and who are directly
responsible for all personnel/equipment allocated to the project.
 Responsible for the implementation, control and monitoring of overall Quality.
 Assurance in all project related activities as laid down in the Contractor’s Management
System (MS).
 Responsible for the preparation and maintenance of budgets for the Project.

PROJECT EXECUTION PLAN 70


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Responsible for ensuring variations between actual costs and budget are monitored and
controlled by the Project Control Engineer, periodically thereafter reviewing the budget for
planning and reporting purposes.
 Responsible for identifying and initiating any variations towards the Client or
Approve/reject variations from third parties based on the contract Terms & Conditions.
 Establish, manage and control the Project Organization defining the line of responsibility to
Project personnel and to Department Managers/Supervisors for Project services
 Liaise with the CLIENT and ensure that Project meetings are held with all relevant
personnel during the Project and record same on minutes of meetings.
 Liaise with Engineering and ensure Project Design Verification meetings are held with all
relevant personnel during the Project and record same on Minutes of Meeting
 Responsible for obtaining resources from departments needed to carry out the
 Project.
 Ensure that all aspects of Project Administration, Engineering and Operations fulfil the
Contract requirements and are conducted in a safe, efficient, and profitable manner.

5.1.1.4.11 Engineering Manager Roles during Detail Design.

The Engineering Manager who will report to the Project Manager will be nominated during the
Engineering. He will be temporarily located at Makais Synergy’s office complex in Lagos until
the completion of the detail engineering design, thereafter; he will re-locate to the project
management office at the camp site. The Engineering Manager shall be responsible for:
Interacting with COMPANY on Engineering matters Verification of, FEED and preparation of
Detailed Engineering deliverables.

The Engineering Manager shall be assisted by respective Lead Discipline Engineers who shall be
responsible for their various disciplines.
The entire Project shall be executed under the direction, control and supervision of the Project
Manager. The Project Manager shall be assisted by the respective departmental managers who shall
be responsible for their various departments.
The Project Manager shall ensure that the objectives of the project are met; the project schedule is
maintained and adhered to.

PROJECT EXECUTION PLAN 71


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The Project Manager shall ensure that the agreed project management, HSE management and quality
management systems for the project implementation are in place throughout the duration of project
execution.
Project audit shall be carried out for quality assurance during the Detail Engineering Design and
audit reports shall be produced according to the contractual requirements in accordance with the
Project Coordination Procedure.
Other Project Management activities shall include:
 Overall project strategy, direction, management and performance as per
CONTRACTOR/COMPANY Agreement.
 Design Coordination.
 Establishment of relevant measures of performance, such as schedules, etc.
 Overall coordination and liaison with the COMPANY, including administration of the
CONTRACTOR/COMPANY Agreement.
 Establishment and implementation of the Project Quality System.
 Delegation of authority, but not overall responsibility, for the implementation of the Project
Quality System to other members of the project team as appropriate to their particular functions.
 Implementing remedial and/or corrective action on matters affecting quality and project
performance.

The Project Manager shall interact with COMPANY’s Project Manager and liaises with Makais
Manager Engineering and Managing Director as necessary.

5.1.1.4.12 Lead Project Control Engineer.


The responsibilities of the Lead Project Control Engineer shall include, but are not
limited to the following:
 Developing and maintaining detailed product schedules.
 Monitoring cost and commitment through requisition and invoice review
 Ensuring adherence to recommended best practices such as the critical path method based on
PERT and the like.
 Ensuring adherence to quality standards such a Total Quality Management or Six Sigma by
ensuring employees follow quality standards and by using quality control checklists.

PROJECT EXECUTION PLAN 72


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Coordination and regulating various meetings such as project progress review meetings, quality
circles, and the like.
 Application of various project progress methods to ensure the project schedule is on track to
meet deadlines or deliverables
 Devising strategies to overcome roadblocks or delays through various methods such as using
industry related technical knowledge, innovating short cuts or alternative ways, improvising with
available resources, scheduling overtime to meet the deadline, and the like.
 Developing and monitoring project cost forecasts

5.1.1.4.13 Lead Document Control Engineer


The responsibilities of the Lead Document Control Engineer shall include, but are not
limited to, those contained in the following statements:
 Supervises and operates the document management system for the Project.
 Generates and maintains the Project Master Document Register (MDR), ensuring it is always up
to date.
 Ensures that all documentation is provided as per Contractor format requirements.
 Create and maintain Document Control folders for Project.
 Registers all incoming Project documents.
 As instructed by document author, issue Document Review Register with document details and
distribute document for review. File on completion.
 Assists with preparation of Close Out report for Project Manager.
 Transmittals: ensure all documents and drawings are provided with transmittals when
appropriate. Recording document distribution by transmittals. Ensure signed transmittals have
been received.
 Completes all electronic Projects archiving as directed by Administration Supervisor

5.1.1.4.14 Lead Discipline Engineers


The responsibilities of the Design Lead/Engineering Leads shall include, but are not limited to, those
contained in the following statements:
 Responsible for all activities pertaining to the assigned task, as set by the Project Manager.
 Identify and supervise all technical resources needed to complete the task. Assign and coordinate
scopes of work, review work done and ensure each resource stays within assigned schedule and

PROJECT EXECUTION PLAN 73


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

cost targets. Ensure that all personnel under their control are suitably qualified to undertake the
work assigned to them.
 Responsible for all engineering activities associated with the task, which shall be reviewed and
approved accordingly. This also includes, but is not limited to, documentation such as
Specifications, Procedures, Calculations, Reports, etc. The Lead Engineer is also responsible for
the final dossier.
 Responsible for all interfaces relevant to the task under their responsibility. This includes, but is
not limited to, Client, Subcontractors, Internal Entities etc.
 Ensures that the Cost Controller/Planner is provided with adequate information to enable correct
and accurate preparation of Project status report for the task under their responsibility.
 Responsible for initiating actions to prevent non-conforming condition or product.
 Initiating, recommending, or providing solutions to non-conformances. Verifying the
implementation of corrective action and ensuring that these have been effective and controlling
further work until the deficiency or unsatisfactory condition has been corrected and the root
cause resolved.
 Conducts all activities within the management system, Policy, Procedures and work Instructions.
 Performs engineering tasks assigned by the Project Engineer, when applicable, in order to
complete scopes of work as identified by the Project Manager.

5.1.1.5 Engineering Disciplines

CONTRACTOR shall be responsible for provision of engineering services leading to preparation of


deliverables listed under her scope of work.

The following services shall be provided by multi discipline engineering team during project
execution in Makais Synergy office.
 Review of relevant FEED documents received from COMPANY.
 Preparation of Detailed Engineering design deliverables including all reports, analysis and
drawings for the construction for the project
Contractor shall commence the execution of the validation of FEED followed by Detail
Engineering Design scope by reviewing available engineering documents and other relevant
handover documents from COMPANY.

PROJECT EXECUTION PLAN 74


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

CONTRACTOR shall conduct site survey to collate relevant data from the existing facilities as
input to part of activities necessary to fulfill the scope specified in the invitation to tender letter.
Data / information gathered during site survey will be used during the Detail Engineering Design
and PCI (procurement construction and Installation).
The following Makais Synergy engineering disciplines shall participate in the FEED validation and
DED documents.
 Civil/Structural
 Architectural
 Mechanical/HVAC
 Electrical
 Corrosion
 Instrumentation & Control
 Telecommunication
 Process
 Project management (Project control, DCC QAQC, IT etc)

CONTRACTOR shall execute the engineering services in compliance with the contractual
documentations, Newcross EP /NUIMS engineering general specifications, relevant codes &
standards, local laws, regulations and good engineering practice.
CONTRACTOR Quality Assurance/Control Engineer shall develop a Project Quality Plan for the
project upon award. This will define the project quality management system for all aspects of the
agreement and describes the actions taken by CONTRACTOR and its endorsement on the
engineering documents before submitting for COMPANY review and approval. The Quality plan
shall form the key document controlling the activities of all disciplines on the project.
Project Quality Plan shall define the organization, resources and responsibilities of key personnel
and functions on the project. The Quality Plan shall list the applicable procedures, schedules of
Surveillance and Audits plan to ensure compliance with COMPANY Quality Management System. .
CONTRACTOR Quality Assurance scope of work shall include the following:
 Prepare Project Quality Plan
 Review all Project Procedures
 Review Project Deliverables to ensure compliance with Project and Contract requirements.

PROJECT EXECUTION PLAN 75


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Ensure the provision of Quality awareness and induction training where necessary or required to
the Project team.
 Carry out Project Quality Audit
 Prepare Audit Report
 Evaluation and review of Customer satisfaction survey and Feedback.
 Documentation of Project Lesson Learned.

5.1.1.5.1 Method Statement for Architectural /Civil/Structural Engineering

On award of contract, CONTRACTOR Architectural/ Civil/Structural group will request for all
available documents and drawings relevant to the defined scope and study them carefully before
commencing the job.
The structural group shall apply National and International Recommended Practices & Standards in
the execution of the project.
The Civil Structural Scope of Work (SOW) shall include but not limited to:
 Site visit
 Development of Civil/Structure Basis of Design
 Review of Geotechnical Investigation Report Survey
 Preparation of Technical Specifications
 Preparation of DED Design Reports & Drawings
Preparation of Input to Construction Scope of Work

To perform the engineering design, the Civil Structural team will require the following input from
client:
 Project Design Philosophy/Basis of Design
 Geotechnical Investigation Report
 Topographical Survey
 ANY Relevant Company Documentation
 FEED documents

Deliverables
For Architectural

PROJECT EXECUTION PLAN 76


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Architectural Design Drawings for all the proposed buildings

For Civil/Strutural
The Civil / Structural engineering deliverables shall include but not limited to the following:
GENERAL DOCUMENTS
 Civil/Structural Basis of Design
 Specification for Concrete
 Specification for Foundation
 Specification for Structural Steel Works
 Specification for Site Preparation
 Review of Geotechnical Survey Report
 Review of Bathymetric Survey Report
 Input to Site Visit Report.

DESIGN & CALCULATION REPORTS

 Pile Foundation Design Calculation & Report


 Structural Steel In-place Analysis Report
 Proposed buildings Calculations & Reports
 Water treatment plant foundation calculation and reports

DRAWINGS
 Civil Drawings Index
 Civil General Notes
 Pile Foundation Layout Drawings
 Pile Foundation Plan, Elevation & Section Details Drawings
 Structural Drawings Layout
 Structural Drawings Reinforced Concrete Details (Slabs, Beams, Columns etc)
 Structural Drawings Miscellaneous Items Details (Staircase etc)
 Water Treatment Plant Plan, Elevation & Section Details Drawings.

MTO

 Material Take-off

PROJECT EXECUTION PLAN 77


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Software Requirements
The civil discipline computer software to be used for the execution of the project shall include:
 AutoCAD 2012 - 2D drawings production
 STAAD.Pro V8i - Structural analysis
 Microsoft Office Tools - Reporting and calculations
 Revet -Architectural drawings

5.1.1.5.2 Method Statement for Materials and Corrosion Engineering

Based on the work scope highlighted above, the deliverables to be produced by the materials and
Corrosion discipline shall include the following:
 Materials Selection report
 Materials Selection Diagram
 Cathodic Protection Design Report for jetty piles (if required)
 Cathodic Protection System Materials Specification
 Preliminary Cathodic Protection System Data Sheets
 Preliminary Cathodic Protection System MTO
 Cathodic Protection Anode Installation Details
 Cathodic Protection Schematic Wiring Drawings
 Painting and coating specification
IT Requirements
Software shall be customized to meet project requirements at the start of the project, and shall
continue throughout the project. This is to ensure effective file transfer, exchange and integration
during the project. All software used shall be validated in accordance with the overall project Quality
Assurance Procedures.
The following software shall be required:
 Microsoft Office Suite
 AutoCAD

5.1.1.5.3 Method Statement for Mechanical /HVAC Engineering

PROJECT EXECUTION PLAN 78


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The Mechanical/HVAC discipline will generate all but not limited the following deliverables :
 Calculation Note for Overhead Water Storage Tank
 Datasheet Sheet for Overhead Water Storage Tank
 Specification for Overhead Water Storage Tank
 Requisition for Overhead Water Storage Tank
 Calculation Note for Surface Water Pump
 Datasheet for Surface Water Pump
 Specification for Surface Water Pump
 Requisition for Surface Water Pump
 Datasheet for Water Treatment Package
 Specification for Water Treatment Package
 Requisition for Water Treatment Package
 Calculation Note for Fuel oil Storage Tank
 Datasheet Sheet for Fuel oil Storage Tank
 Specification for Fuel Oil Storage Tank
 Requisition for Fuel Oil Storage Tank
 Potable Water Piping Layout Drawing
 Sewage Water Piping Layout Drawing
 Fire Hydrant Piping Layout Drawing
HVAC Documents & Drawings
 HVAC Basis of Design and Philosophy
 HVAC Equipment list
 Datasheet for Air Handling unit
 Datasheet for balancing Dampers
 Datasheet for Fire and gas dampers (IT Battery Room)
 Datasheet for exhaust Fans
 Ventilation Calculation Report
 HVAC Thermal Heat calculation Report.
 Specification for HVAC Equipment
 HVAC Block Flow Diagram
 HVAC Single line Air Flow Diagram

PROJECT EXECUTION PLAN 79


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 HVAC Legend Sheet


 HVAC D&ID
 HVAC Equipment Room Arrangement Drawing
 HVAC Duct Layout Drawing
 Datasheet for Water cooled Chillers
 Datasheet for VAV Boxes
 HVAC Duct Construction Drawing
 Datasheet DX precision Unit for Server Room

IT Requirements
The software to be used by the Mechanical team includes the following:
 Microsoft Office Suite
 Auto CAD
 Pvlite
 Any other software as may be required by Client.

5.1.1.5.4 Method Statement for Process Engineering

The scope of the process activities is to produce an engineering design package which establishes the
design, operating conditions and equipment necessary for the sewage and water treatment plant
package.
Execution Methodology
On award of contract to CONTRACTOR, the process group shall engage in carrying out all process
engineering and related activities in order to meet the aim and objective of the project. This shall
involve producing quality deliverables in line with project scope, review vendor document and
providing technical assistance to ensure timely and acceptable project handover.
i. The process engineering activities to be carried out shall include:

1) UFD for water treatment facilities


2) UFD for Sewage treatment facilities

3) Utilities Sizing

Deliverables

PROJECT EXECUTION PLAN 80


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

o Utility flow Diagram


o Utility Piping and Instrumentation Diagrams
o Utilities Sizing Calculation and report

Software
The following software will be required by the Process discipline.
 Auto CAD
 Microsoft Office

5.1.1.5.5 Method Statement for Instrumentation and Telecommunication

The Instrumentation and Telecommunication scope of work shall cover the provision of
instrumentation and telecommunication detail design for the proposed project.
Instrumentation & Telecommunication engineering/design shall include the following:
 Determine the requirements for instrumentation and telecommunication for the proposed
structures.
 Identify instrument types that would be required.
 Provide Instrumentation and Control System for the relevant facilities.
Instrumentation and control system design shall comply with COMPANY’s Standards and relevant
local/ international codes and standards. Relevant industry codes and standards shall be used to
determine Instrumentation and Control systems requirements.
Deliverables:
For instruments:
 Design basis
 Field instruments specification
 Junction box
 Package instruments specifications
 Package control system
For Telecommunication
 Basis of design
 Block control system drawings
 LAN specification

PROJECT EXECUTION PLAN 81


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Software Requirement
 Microsoft Office
 AutoCAD for 2D drawings

5.1.1.5.6 Method Statement for Electrical Engineering

Electrical scope of work shall cover the provision of the following electrical deliverables:
 Electrical Symbol and Legend Sheet
 Electrical Load List
 Single Line Diagrams
 Equipment Sizing Calculation and Selection
 Lighting and Small Power Layout
 Lighting Layout (Outdoor/Car park)
 Electrical (Outdoor Routing
 Cable Sizing
 Cable Schedule
 Lighting Calculation Note
 Lighting Circuit Booklet
 Distribution Board Panel Schedule
 Equipment Specifications
 Electrical material Take-off
 Electrical Room Layout
 Earthing Layout
 Protection and Metering Key Diagrams
Software Requirements
a) AutoCAD for 2D drawings
b) Microsoft Excel: for all Spread sheets
c) Microsoft Word: for other documentation (e.g. reports)
d) ETAP/SKM

5.1.1.6 Engineering Location and Facilities

PROJECT EXECUTION PLAN 82


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The Detailed Engineering design of the project shall take place at Makais Synergy office located at
4C Solomon Close, off Ahmadu Bello Way, Victoria Island .

Picture showing a part of the work stations at the Engineering Centre

PROJECT EXECUTION PLAN 83


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

Picture showing another view of the workstations at the Engineering centre

The engineering office is housed on a 1000 square meter facility comprising both administrative
wing and an open space for engineering office seating about 70 personnel.
This facility is available for all the engineering activities during the execution of the project.

6.0 PROCUREMENT MANAGEMENT

The procurement of all major project items, equipment and materials shall be coordinated from
Makais Head office in Victoria Island and sourced from COMPANY’s approved local vendors in
Nigeria and countries of original equipment manufacturer (OEM) approved by COMPANY.
The main procurement functions such as procurement of civil, electrical, mechanical, safety, piping
etc materials shall be conducted from Makais Head Office with the procurement team comprising of
technical personnel from the in-house design team as well as procurement buyers and expeditors.
The team at Makais home office is to be led by a dedicated procurement manager assigned for the
project.
The Procurement Manager shall also oversee and coordinate localized procurement from the branch
and site offices. Procurement functions from site office are principally for sourcing of construction
consumables, local subcontract services, local manpower and resources, etc. including the sourcing
of local machinery and equipment rentals.

6.1 Material Expediting

The Procurement Manager shall also oversee expediting of materials and equipment supply from
vendors. In this area, he would be assisted by the technical support from the engineering design team
during initial procurement right through to the delivery.
During delivery, whether by sea freight, airfreight or land transportation expediting is supported by
logistic and control engineers at Makais Head office, logistic officers at Branch office and the
logistics personnel at campsite.

6.2 Delivery, Packing and Shipment

The packaging and delivery of equipment and project materials will be scheduled for consolidated
consignments, which are planned for containerized cargo loads. This would enhance delivery
logistics, especially in terms of port transshipment, protection during shipment, damage protection,
security and pilferage, ease of port and customs clearance, minimized handling to site.
Logistics and expediting will be handled from Makais Head Office where personnel will liaise with
relevant authorities for all import customs clearances.

PROJECT EXECUTION PLAN 84


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The procurement, materials expediting, delivery packing and shipments shall be in accordance with
the Makais Procurement Procedure. Please refer to section 10 of this tender for Makais Procurement
Procedure.

7.0 CONSTRUCTION

7.1 Construction Mobilisation

The construction will be sub-divided into individual activities, which will be undertaken in a logical
sequence to achieve the successful completion of the WORK within the requested milestones.
This will involve detailed planning to accurately assess the requirements of manpower, equipment
and materials for all works. Meetings will be held with COMPANY to ensure that all work is
planned and carried out to the correct procedures and in line with all permits and approvals that may
be required, especially those works that require tie-ins to existing equipment/services.
This will involve:
Ensuring by discipline and number of the personnel required to perform individual activities and
ensuring said personnel are available at site prior to commencement of work.
Ensuring that all equipment required for the work is available at site and is fully operable and
complete with all permits including COMPANY pre-mobilization inspection, service records,
spares, as may be required.
Ensuring all specifications, drawings, procedures and construction information as required are
available at site and are familiar to the construction personnel.
Ensuring that all permits and approvals have been obtained and those construction personnel are
familiar with their content prior to commencing individual operations.
The mobilization of Contractor shall be executed in accordance with the project schedule.
The site activities shall include but not limited to the following:
 Construction of Temporary Construction Camp
 Sandfilling and Piling works.
 Substructure
 Roofing
 Plumbing and mechanical engineering
 Piping works
 Civil works
 Painting

 Electrical works
 Water treatment plant installation

PROJECT EXECUTION PLAN 85


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

The above shall be achieved with the listed cadres of personnel and equipment below.

The equipment / facilities to be mobilized may include all but not limited to the following:

7.1.1 Civil Facilities

 Dozer type cat D7


 Grader type cat 120 G
 Front end loader type cat 936
 Small compactor 1,5 tons
 Compactor vibrating 12 tons
 Compactor tyre 12 tons
 Mini excavator bob cat
 Excavator type cat 235
 Road finisher
 Bitumen sprayer 10000 lit
 Front end loader type Cat 936
 Concreting
 Batching plant 30 m3/hour
 Concrete mixers 7-8 m3
 Concrete pumps
 Mobile cranes 25-35 tons

7.1.2 Mechanical Facilities

 Prefabrication workshop.
 Painting workshop
 Hydraulic crane 35 ÷ 100 tons capacity
 Diesel welding set
 Automatic welding machines “circomatics”
 Automatic welding machines for tank bottom
 Electric welding machines
 Air compressor 7 ÷ 11000 lt/min. capacity
 Power generators 200 Kw. capacity
 Tractor with trailers
 Forklifts
 Sandblasting machines
 Power Generating Set
 Dewatering Pumps

PROJECT EXECUTION PLAN 86


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Mechanical Toolbox
 Scaffolds
 Rolling Machine
 4-Wheel Drive Transport Vehicles
The personnel to be mobilized will include all but not limited to the following:
 Project Manager
 Construction Manager
 Project Site Engineers
 Construction superintendent
 QAQC Lead
 QAQC Officers
 Document Controller
 Planning Engineer
 HSE Lead
 HSE officer
 Site Nurse
 Logistics Coordinator
 Procurement Lead
 Procurement/Material Officer
 Project Accountant
 Administrative Officer
 Storekeeper
 Lead Design Engineer
 Design Engineer
 CAD Operator
 Welders
 Fitters
 Mates
 Riggers
 Scaffolders
 Rolling Machine Opeartors
 Painters
 Blasters
 Helpers
 Scaffolders
 Quantity Surveyor
 Technical Officer
 Mason (Foreman)
 Mason
 Iron Bender (Foreman)
 Iron Bender

PROJECT EXECUTION PLAN 87


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

 Carpenter (Foreman)
 Carpenter
 Concrete Mixer Operator
 Pay-loader Operator
 Backhoe Operator
 Bitumen/Sand Mix Layer
 Plate Compactor Operator
 Surveyor
 E&I Technicians

7.2 Construction Management

The purpose of Construction Management is to ensure that construction is in compliance with


project requirements and AFC designs; compliance with respect to health, safety and environment
aspects.
In order that Construction Management is always in full control on the Project, all requests,
comments and queries shall be channeled through the Construction Manager. The Construction
Manager shall implement the following key activities:
• Plan allocation of manpower resources;
• Progress measurement & reporting;
• Allocation of construction responsibility;
• Schedule Control
• Cost & Quality Control
• Material Control

7.3 Construction Resources & Subcontracts

CONTRACTOR will undertake the WORKS with its own field construction crew and construction
machinery and field equipment together with some direct hire from suitably skilled local and
expatriate people.
CONTRACTOR shall maintain a comprehensive range of fabrication yard and field construction
equipment that is required for the entire scope of work. The equipment shall be well maintained and
kept in ready for use condition by a full maintenance crew for equipment & machinery, including
mechanics and electricians at the construction campsite.

7.3 Construction Procedures

PROJECT EXECUTION PLAN 88


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

A complete set of CONTRACTOR construction procedures to be used for the project will be
submitted for approval after award of contract.

7.4 Construction Camp & Site Facilities

CONTRACTOR will rent/construct a campsite with full facilities nearest to site area.
CONTRACTOR will maintain a full crew construction team at the campsite for the entire duration
of the project. Power generation, water storage and basic amenities will also be implemented.

7.4.1 Pre-Inspection & Calibration

Upon arrival of the equipment at the jobsite, these will be inspected against the specifications.
Vendor data will also be verified to ensure all requested documents are provided. Equipment that
requires calibration will be calibrated and witnessed by COMPANY (client) if required. Certified
test equipment shall be used to perform the calibration check. Calibrated equipment will be tagged in
accordance with client’s procedures. Bidder or Client’s calibration forms will be completed and
signed. Faulty equipment if any will be clearly identified tagged and returned to the vendor for
replacement.

PROJECT EXECUTION PLAN 89


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

7.5 Subcontract Strategy

Although CONTRACTOR intends to construct the project within house resources and direct
hired personnel, there would be instances whereby CONTRACTOR will consider sub-
contracting some portions of work scope to local sub-contractors, especially where such work
scopes involve large manpower resources or heavy equipment and machinery.
It is envisaged that the sub-contact content may also involve specialist for painting works, third
party NDT /Calibration services that are not available from local subcontractor.

7.6 Structural Works

Upon approval of AFC drawings and material delivery, the shop fabrication shall begin. All
shop drawings will be provided to fabricators. It is envisaged that all structures will be
prefabricated to permit site erection with minimum welding works.

concrete, similar testing will take place onsite in order, to ensure quality and conformity of the
supplied concrete to the tender requirements.

In areas where Transit mixers are not suitable for concrete pouring, a mobile concrete pump
will be utilized. Transit mixers will mainly pour concrete of foundations, footings and the slab
on grade. Other areas will be poured by using mobile pumps / mobile cranes depending on its
location and dimension.
To prevent the concrete from drying and shrinkage cracks, wet curing shall be utilized for all
concrete elements either by water or using a special curing compound.

Finishes

Finishes works will proceed according to Specifications, Shop Drawings previously prepared
and the Quality and Safety Plans.
All finishing works will be carried out by CONTRACTOR’s experienced staff except for some
tasks to be carried out by reputable specialized subcontractors as per the proposed
Subcontractors list.

Electromechanical Equipment

CONTRACTOR shall assign its finest specialized personnel to carry out the various E/M scope
in accordance with project technical requirements and given standards.
Electromechanical works shall be given special attention especially in the early stages where
close co-ordination for imbeds and under slab utilities is a must.
Electromechanical items shall be executed on a priority basis. This is especially important since
vital submittal information is required during the civil shop drawings preparation phase.

PROJECT EXECUTION PLAN 90


Provision for Engineering Design,
Construction and Installation of
Building/Civil Infrastructure in
Document Type Ekulama 1, Ekulama 2 And Awoba
Organisation and Key Personnel Flowstations – OML 24

All manufacturers’ recommendations shall be followed during the installation and/or


commissioning and testing.
Care will be taken to provide the required O & M manuals for all supplied equipment to the
satisfaction of the project requirements.

PROJECT EXECUTION PLAN 91


PROJECT EXECUTION PLAN 92
PROJECT EXECUTION PLAN 93

You might also like