Project : MTB - PRODUCTION PLAN

ITEM DESCRIPTION Qty DEPARTMENT ETA @ WADA


Aluminium Extusion 14.4 Ton POWDER COATING March 7, 2024
Powder RAL 9006 360 Kg POWDER COATING March 7, 2024

1.2mm Aluminium Sheet 239 No's SHEARING / BENDING March 10, 2024
0.8mm Glavanized Sheet 230 No's SHEARING / BENDING March 10, 2024

MS - Bracket Material 37 No's SHEARING / WELDING March 10, 2024

UCW - Panel Machining 280 Panels PRODUCTION

1.2mm Aluminium Sheet 560 No's POWDER COATING


0.8mm Glavanized Sheet 560 No's POWDER COATING

MS Bracket - HDG 1120 No;s HDG

Dispatch - 1st Lot UCW Panels | Brackets


Dispatch - 2nd Lot Bal Panels | SB | Tray | BKT
FWO RELEASE PROD - START DATE PROD-END DATE
March 9, 2024 March 14, 2024
March 9, 2024

March 12, 2024 March 16, 2024 March 18, 2024


March 12, 2024 March 16, 2024 March 18, 2024

March 7, 2024 March 12, 2024 March 15, 2024

March 12, 2024 March 16, 2024 March 18, 2024

March 20, 2024 March 21, 2024


March 20, 2024 March 21, 2024

March 16, 2024 March 19, 2024

March 19, 2024 March 19, 2024


March 23, 2024 March 23, 2024
Project : MTB - PRODUCTION PLAN PLAN DATE
ITEM DESCRIPTION Qty DEPARTMENT FWO REL.NO FWO REL.DATE PLAN-START
ZONE 1 - SUBSILL - 1ST FLOOR 27 Completed FWO-06 March 13, 2024
MS STARTER BRACKET&WASHER 1550 Completed FWO-07 March 13, 2024
ZONE 1 - SUBSILL - 2ND FLOOR 64 50% Balance FWO-08 March 13, 2024
ZONE-1 MS BRACKET & WASHER 1939 PRODUCTION FWO-09 March 16, 2024
ZONE-1 CORNER PANELS 18 PRODUCTION FWO-10 March 20, 2024
ZONE-1 OPENABLE PANELS 46 PRODUCTION FWO-11 March 21, 2024
ZONE-1 TYPICAL | END PANELS 216 PRODUCTION FWO-12 March 26, 2024

Project : MTB - PRODUCTION PLAN (ZONE-2) WADA DATE


ITEM DESCRIPTION Qty DEPARTMENT FWO REL.NO FWO REL.DATE Qty
EXTUSION - RAL 9006 SPM 13.8 Ton COATING FWO-17 April 17, 2024
ALUMINIUM TRAY - RAL 6003 209 COATING FWO-18 April 18, 2024
GI TRAY - RAL 9006 209 COATING FWO-19 April 23, 2024
MS Bracket 221 MS FWO-13 March 22, 2024
MS Bracket 227 MS FWO-14 April 1, 2024
MS Bracket 213 MS FWO-15 April 13, 2024
ZONE-2 CORNER PANELS 14 PRODUCTION FWO-17 April 17, 2024
ZONE-2 OPENABLE PANELS 34 PRODUCTION FWO-18 April 18, 2024
ZONE-2 TYPICAL | END PANELS 161 PRODUCTION FWO-19 April 23, 2024
PLAN DATE WADA DATE
PLAN-END TARGET-START TARFET-END

WADA DATE BANGALORE DATE


Delivered Date Qty Target Supply Date
Project : MTB-06 ALUMINIUM SCHEDULE
PLANNED QTY PANEL QTY ALUMINIUM SUPPLY TARGET SUPPLY TARGET
LOT ZONE (Ton) TONS PO Date PO Status DATE (WADA) DATE
As per BOM (Bangalore)
Zone-1 14.4 284 14.4 09.02.24 Done Completed 12.04.24
1 Zone-2 6.9 212 Done
13.7 01.03.24 20.04.24 11.05.24
Zone-3 6.8 205 Done
Zone-4 6.3 167
2 Zone-5 7.9 205 21.8 02.04.24 30.04.24 21.05.24
Zone-6 7.6 205
Zone-7 6.8 54
3 Zone-8 8.3 207 23.1 20.04.24 18.05.24 08.06.24
Zone-9 8.0 207
Zone-10 7.7 207
4 Zone-11 8.0 207 22.8 11.05.24 08.06.24 29.06.24
Zone-12 7.1 207
Zone-13 8.0 207
5 Zone-14 10.4 233 23.2 01.06.24 29.06.24 20.07.24
Zone-15 4.8 227
Total 119.1 3034 119.1

PREPARED BY : ELAVENDAN MTB-06 PROJECT PROCUREMENT TRACKER PAGE : 5


GLASS SCHEDULE
WADA CKD (SKN & ST ) SUPPLY TARGET
TARGET DATE SQ.MTR PO Date DATE
(Bangalore)
09.04.24 1560.0 15.03.24 10.04.24

08.05.24 1911.0 10.04.24 05.05.24

18.05.24 2870.0 24.04.24 15.05.24

05.06.24 2894.0 12.05.24 02.06.24

26.06.24 3061.0 08.06.24 23.06.24

17.07.24 2666.0 23.06.24 14.07.24

14962.0

PREPARED BY : ELAVENDAN MTB-06 PROJECT PROCUREMENT TRACKER PAGE : 6