User Drawing Number Drawing Title Activity Revision Master Planned Start Planned End Planned Hours Schedule Status
PFM-RC-MALL-217/222/227 PRESTIGE FORUM MALL-Basement-2-1 & Ground Floor Beam Layout & Details Draft P6 29-04-2024 30-04-2024 16.00 Planned Completed
Soumya BFN-RC-VN-201/205/205A VANANTARA NIRVANA- Footing Layout /Retaining wall layout and Sections Draft P3 02-05-2024 02-05-2024 8.00 Unplanned Completed
GDAB-RC-FLAT-225 GINA-COMPOUND WALL LAYOUT AND SECTIONS Draft P0/P1 03-04-2024 03-04-2024 8.00 Planned Completed
TPLVG-ST-EPPR-301&302 PEDESTAL & BASE PLATE ANCHORING DETAILS Draft R0 29-04-2024 29-04-2024 4.00 UNplanned Completed
TPLVG-ST-EPRACKSTRE-301.302&303 and ADDITIONAL PIPE RACK SUPPORT GA & CONNECTION DETAILS and EXTERNAL PIPE RACK
Draft R0 29-04-2024 29-04-2024 5.00 UNplanned Completed
TPLVG-RC-EPPR-201 FOUNDATION, GA PLAN & CONNECTION DETAILS
MALAGOWDA
AGPN2-RC-STP-201 STP FOUNDATION LAYOUT & DETAILS Draft P0 30-04-2024 02-04-2024 12.00 Planned Completed
AGPN2-RC-MRL-201 MHE RAMP LAYOUT & SECTIONS Draft R1 02-04-2024 02-04-2024 3.00 Planned Completed
AGPN2-RC-RAMP-201/ MAIN ROADS RAMP LAYOUT & DETAILS AT GATE-1 Draft P0 03-04-2024 03-04-2024 6.00 Planned Completed
EARLY LEAVE 2.00
BBPL-RC-AB-204/205/206 FIRST ,SECOND , TERRACE FLOOR BEAM LAYOUT & BEAM DETAILS Draft CA0 29-04-2024 29-04-2024 8.00 PLANNED COMPLETED
BBPL-RC-AB-204A/205A/206A FIRST,SECOND,TERRACE FLOOR TOP & BOTTOM REINF. Draft CA0 30-04-2024 30-04-2024 3.00 PLANNED COMPLETED
VLSPL-RC-TWA-229 5TH ,6TH ,7TH FLOOR BEAM LAYOUT SECTIONS Draft CA2 30-04-2024 30-04-2024 5.00 PLANNED COMPLETED
SHASHI AGPNM-RC-EPB-201 ELECTRICAL PANEL ROOM DETAILS Draft R1 02-05-2024 02-05-2024 2.00 UNPLANNED COMPLETED
BBPL-RC-AB-204/205/206 FIRST/SECOND & TERRACE LVL BEAM DETAILS Draft CA0 02-05-2024 02-05-2024 6.00 PLANNED COMPLETED
VLSPL-RC-TWA-214 GROUND FLOOR BEAM LAYOUT Draft CA2 03-05-2024 03-05-2024 5.00 PLANNED COMPLETED
VLSPL-RC-TWA-217/220/223/226 FIRST/SECOND/THIRD & 4 & 5TH FLOOR Draft CA2 03-05-2024 03-05-2024 3.00 PLANNED COMPLETED
SIDDESH H A PRC-ST-MODEL-CBL-2000 PRESTIGE ROCKCLIFF ANALYSIS AND DESIGN DESIGN CA0 29-04-2024 03-05-2024 32 PLANNED COMPLETED
PFM-STMODEL-ETABS-2000 MODELLING FOR FORUM MALL Design CA0 29-04-2024 29-04-2024 4.00 PLANNED COMPLETED
General Activity BAGAMANE FREE STANDING WALL Design CA0 29-04-2024 29-04-2024 4.00 UNPLANNED COMPLETED
PFM-STMODEL-ETABS-2000 MODELLING FOR FORUM MALL Design CA0 30-04-2024 30-04-2024 8.00 PLANNED COMPLETED
KARTHIK R PFM-STMODEL-ETABS-2001 MODELLING FOR FORUM MALL Design CA0 02-05-2024 02-05-2024 4.00 PLANNED COMPLETED
BBPL-STMODEL-PB-2000 STAAD MODEL CHECK AND FOUNDATION DESIGN Design CA0 2/5/2024 2/5/2024 4.00 UNPLANNED COMPLETED
BBPL-STMODEL-PB-2000 STAAD MODEL CHECK AND FOUNDATION DESIGN Design CA0 3/5/2024 3/5/2024 4.00 UNPLANNED COMPLETED
AGPN2-RC STP-LAYOUT AND DETAILS Design CA0 3/5/2024 3/5/2024 4.00 PLANNED PENDING
VLSPL-RC-TWA-206 RETAINING WALL LAYOUT AND SECTIONS Design CA0 2/5/2024 2/5/2024 8.00 PLANNED PENDING
BFN-STMODEL-CBL-2000 MODELLING FOR VANANTARA NIRVANA Design CA0 2/5/2024 2/5/2024 8.00 UNPLANNED COMPLETED
THIPPESWAMY
BFN-STMODEL-CBL-2000 MODELLING FOR VANANTARA NIRVANA Design CA0 3/5/2024 3/5/2024 6.00 UNPLANNED COMPLETED
BBPL-STMODEL-PB-2000 STAAD MODEL CHECK AND FOUNDATION DESIGN Design CA0 3/5/2024 3/5/2024 3.00 UNPLANNED COMPLETED