Unit 3
Unit 3
Unit 3
EOQ =
√ 2 DO
D = Annual Demand
S
Problem – 5
From the following information calculate EOQ and also calculate no of orders
per annum.
Quarterly Consumption 4000 units
Cost of placing one order Rs. 100
Cost per unit is Rs. 80
Storage and carrying cost 8% of inventory
Problem – 6
From the following information calculate EOQ and also calculate no of orders
per annum.
Quarterly Consumption 2000 units
Cost of placing one order Rs. 50
Cost per unit is Rs. 40
Storage and carrying cost 8% of inventory
Problem – 7
ABC ltd requires 1,500 units of materials per month costing Rs. 27 Per unit.
Cost per order is Rs. 150 and Inventory carrying cost works out to 20% of
Average inventory. Find EOQ and no of orders to be placed in a year.
Problem – 8
Calculate EOQ and the total cost of EOQ from the following
Quantity 50 units per month
Ordering cost Rs.12 per order
Carrying cost 20%
Price per unit Rs. 20
Problem – 9
About 50 items are required every day for a machine. A fixed cost of Rs. 50 per
order is incurred for placing one order. The inventory carrying cost per item
amounts to Rs. 0.02 per day. The lead time is 32 days. Calculate EOQ. (Consider
365 working days per annum)
Problem – 10
Annual demand 2,400 units
Unit price Rs. 2.40
Ordering cost per order Rs. 4
Storage cost 2% per annum
Interest rate 10% per annum
Calculate EOQ and the number of orders placed during the year
Problem – 11
From the following particulars, calculate EOQ, number of orders and time gap
between two orders
Annual requirements
Cost of materials per unit Rs. 40
Cost of placing and receiving one order Rs. 100
Annual carrying cost of inventory 10%
Problem – 12
A manufacturer buys certain components from outside suppliers at Rs. 30 per
unit. Total annual need is 800 units. Annual return on investment is 10%. Rent,
insurance, taxes, etc. per unit per annum is Rs. 1, and cost of placing one order
is Rs.100. Determine EOQ, number of orders placed during the year, the Time
gap between one order and the other; and the total cost of EOQ.
Storage of Materials
Methods of Storing
1. ABC Method: is a method where the materials are classified into three
categories viz., A, B and C, based on value and volume of materials and
stored accordingly
A = Materials which are low in volume but have high value
B = Materials which have moderate volume and value
C = Materials which are high in volume but low in valve
3. FSN Method:
F = Fast Moving Materials
S = Slow Moving Materials
N = Non -Moving Materials
Stock Levels
1. Re-order Level
2. Minimum Level
3. Maximum Level
4. Average Level
5. Danger Level
3. Maximum Level: It refers to the level to stock above which the materials
should not be piled up.
Problem – 2
Two Components A and B are used as follows
Normal Usage 50 units per week each
Minimum Usage 25 units per week each
Maximum Usage 75 units per week each
Re-Order Quantity A: - 300 units, B: - 500 units
Re-Order Period A – 4 to 6 Weeks and B – 2 to 4 Weeks
Maximum Lead time for emergency purchases A – 2 weeks, B – 1 Week
Calculate Re-Order Level, Maximum Level, Minimum Level, Average Level and
Danger Level of Stock for each component.
Solution
1. ROL = Maximum Consumption X Maximum Lead Time
Component - A = ROL = 75 X 6 = 450 Units
Component - B = ROL = 75 X 4 = 300 Units
Problem – 3
Two materials X and Y are used as follows
Minimum usage 50 units per week each
Maximum usage 150 units per week each
Normal usage 100 units per week
Re-order quantity X – 600 units; Y – 1000 Units
Delivery Period: X – 4 to 6 weeks; Y – 2 to 4 weeks
Calculate Re-order level, Maximum Level, Minimum Level and Average Level
Solution
Problem – 4
Calculate the Maximum level and Minimum Level of stock from the following
particulars
Ordering quantity 800 units
Maximum consumption 30 units per week
Minimum consumption 10 units per week
Delivery period – Maximum 30 weeks and minimum 20 weeks
Problem – 5
In manufacturing its product, a company ses three raw materials A, B, and C in
respect of which the following information is given as follows
Usage Re- Re-
Raw
per unit order Price Delivery order Minimu
Material
of quantity per Kg Period level m Level
s
output (kg) (kg)
A 10 10,000 10 1-3 8,000 -
B 4 5,000 30 3-5 4,750 -
C 6 10,000 15 2-4 - 2,000
Weekly production varies from 175 units to 225 units. What would you except
the quantity of the following to be Minimum Level of A, Maximum Level of B,
Re-Order Level of C and Average Level of A?
Problem – 6
From the following data, calculate Re-ordering level, Maximum Level and
Minimum Level
Re-order Quantity 3,000 units
Re-order period 4 – 6 weeks
Maximum consumption 800 units per week
Minimum consumption 500 units per week
Normal consumption 600 units per week
Management of Issue
First In First Out (FIFO)
Last In First Out (LIFO)
Simple Average Method
Weighted Average Method
Problem – 1
The following transaction took place in A Ltd in respect of purchase and issue of
Material X
January 2 Purchased 4,000 units at Rs. 4 per unit
January 20 Purchased 500 units at Rs. 5 per unit
February 5 Issued 2,000 units
February 10 Purchased 6,000 units at Rs. 6 per unit
February 12 Issued 4,000 units
March 2 Issued 1,000 units
March 5 Issued 2,000 units
March 15 Purchased 4,500 units at Rs. 5.50 per unit
March 20 Issued 3,000 units
Prepare Stores ledger account under FIFO and LIFO
Solution
Store Ledger Account Under First In First Out (FIFO)
Receipts Issues/Payments Balance
Date Particulars Rat Rat
Qty Rs. Qty Rs. Qty Rate Rs.
e e
January 16,00
Purchases 4,000 4 - - - 4,000 4 16,000
2 0
January 4,000 4 16,000
Purchases 500 5 2,500 - - -
20 500 5 2,500
Februar 2,000 4 8,000
Issues - - - 2,000 4 8,000
y5 500 5 2,500
2,000 4 8,000
Februar 12,00
Purchases 6,000 6 - - - 500 5 2,500
y 10 0
6,000 6 36,000
2000 4 8,000
Februar
Issues - - - 500 5 2,500 4,500 6 27,000
y 12
1500 6 9,000
March
Issues - - - 1000 6 6,000 3,500 6 21,000
2
March 12,00
Issues - - - 2,000 6 1,500 6 9,000
5 0
March 24,75 1,500 6 9,000
Purchases 4,500 5.50 - - -
15 0 4,500 5.50 24,750
March 1,500 6 9,000
Issues - - - 3,000 5.50 16,500
20 1,500 5.50 8,250
Problem – 2
The stock in hand of material as on September 1, in the stores Ledger of B ltd.,
was 500 units at Rs. 1 per unit. The following purchases and issues were
subsequently made.
Purchases Issues
September 100 units @ Rs. 1.10 p.u September 9 500 units
6
September 700 units @ Rs 1.20 per September 22 500 units
20 unit
September 400 units @ Rs. 1.30 per September 30 500 units
27 unit
October 13 1000 units @ Rs. 1.40 per October 15 500 units
unit
October 20
500 units @ Rs. 1.50 per October 22 500 units
unit
November 400 units @ Rs. 1.60 per November 11 500 units
17 unit
You are required to prepare the stores ledger under LIFO and FIFO
method.
Solution
Store Ledger Account Under First In First Out (FIFO)
Receipts Issues/Payments Balance
Date Particulars Rat Rat
Qty Rs. Qty Rs. Qty Rate Rs.
e e
Sep – 1 Opening Bal - - - - - - 500 1 500
500 1 500
Sep – 6 Purchases 100 1.1 110 - - -
100 1.1 110
Sep – 9 Issues - - - 500 1 500 100 1.1 110
Sep – 100 1.1 110
Purchases 700 1.20 840 - - -
20 700 1.20 840
Sep – 100 1.1 110
Issues - - - 300 1.20 360
22 400 1.20 480
Sep – 300 1.20 360
Purchases 400 1.30 520 - - -
27 400 1.30 520
Sep – 300 1.20 360
Issues - - - 200 1.30 260
30 200 1.30 260
Oct – 200 1.30 260
Purchases 1000 1.40 1400 - - -
13 1000 1.40 1400
Oct – 200 1.30 260
Issues - - - 700 1.40 980
15 300 1.4 420
Oct – 700 1.40 980
Purchases 500 1.5 750 - - -
20 500 1.5 750
Oct – 200 1.40 280
Issues - - - 500 1.40 700
22 500 1.5 750
Nov – 200 1.40 280
Issues - - - 200 1.5 300
11 300 1.5 450
Nov – 200 1.5 300
Purchases 400 1.60 640 - - -
17 400 1.6 640
Problem – 3
C Ltd uses copper wire as a raw material which is purchased form the market
as and when necessary. The following particulars are available in respect of the
transactions for January 2018.
Jan – 1: Opening balance 300 kg at Rs. 25 per kg
Jan – 2: Purchased 500 kg at Rs. 26.60 per kg
Jan – 4: Issued 220 kg
Jan – 10: Issued 440 kg
Jan – 20: purchased 490 kg at Rs. 23 per kg
Jan – 25: Issued 300 kg
Jan – 27: surplus 20 kg returned to stores out of quantity issued of Jan 4
There was a shortage of 25 kg on Jan 15. Prepare Stores Ledger for these
transactions under LIFO and FIFO
Problem – 4
Following particulars are available from the cost records of E Ltd., for the
month of March 2018, in respect of raw materials X
March 1: Opening balance 25 units worth Rs. 162.50
March 4: Issued 8 units
March 6: Received 50 units at Rs. 5.75 per unit
March 7: Issued 12 units
March 10: Returned to vendor 10 units
March 12: issued 15 units
March 13: Issued 20 units
March 15: Received 25 units at Rs. 6.10 per units
March 17: issued 10 units
March 19: received replacement 10 units
March 20: Return to stores 5 units
March 22: Transferred 5 units from job 182 to job 187
March 26: issued 10 units
March 29: Transferred 5 units from Dept A to Dept B
March 30: Shortage 2 units treated as abnormal loss
Prepare Store ledger under LIFO and FIFO methods
Problem – 5
The following transactions look place in respect in respect of raw materials in
the books of G ltd during September 2024
Date Receipts Rate per units Issues (units)
September - 2 200 2.00 -
September – 10 300 2.40 -
September – 15 - - 250
September – 18 250 2.60 -
September -20 - - 200
September – 25 400 2.70 -
September – 30 - - 400
You are required to record the above transaction in stores ledger pricing the
issues under
Simple Average Method
Weighted Average Method
Problem – 6
Following are the receipts and issues of a raw materials in I Ltd. During April
2024
April 1: Opening balance 1,000 units at Rs. 50 per units
April 3: Issued 140 units
April 4: Issued 200 units
April 8: Issued 160 units
April 13: received 400 units Rs. 48 per unit
April 16: Issued 360 units
April 18: return of surplus from work order 30 units at Rs. 48 per untin
April 20: Received 480 units at Rs. 52 per unit
April 24: Issued 608 units
April 25: Received 640 units at Rs. 50 per unit
April 26: Issued 524 units
April 28: Refund of surplus from a work order 24 units (issued on April 3)
April 30: Received 200 units at Rs. 54 per unit
You are required to record the above transaction in store Ledger, pricing the
issues under
Simple Average
Weighted Average method