TYROLEAN WEIR INTAKES PERU
TYROLEAN WEIR INTAKES PERU
TYROLEAN WEIR INTAKES PERU
HAZARDOUS WATERSHEDS
J. Arbolí*, C. Polimanti **
*
Lombardi Group (**Formerly Lombardi Group)
Av. Javier Prado Oeste, 390, San Isidro, Lima, Peru
e-mail: info@lombardi.group, webpage: www.lombardi.group
The project consists of two water intakes located in two different rivers that convey the
flow to the forebay and the penstock by means of two large box culverts. The starting
point for both intakes is a Tyrolean weir, which safely provides the water intake point
while minimizing the harmful debris normally occurring in the catchment areas. Flow
debris events, referred to as “huaicos” by locals, represent a breakpoint in which a
Tyrolean weir is a good option to cope with the presence of a strong flow of mud and
boulders that may damage and leave out of operation the hydro-mechanical equipment of
a classic gated weir.
This paper introduces the main aspects considered for the design of the intake works,
explaining the final solution adopted for construction and its main key component s.
1 INTRODUCTION
Currently under construction, this Hydropower Project is located in a remote valley, a
3-hour drive away from the closest city. As a result of the transition between the
Amazonian Jungle and the Andes, the valley appears in the Peruvian orography. The area
presents heavy rains during the wet season, from December to May, which can also
originate landslides and debris flows. These circumstances combined with the seismic
activity of the area define the main challenges of the Project.
The Project is composed of two water intakes, located in two different rivers. Both
intakes consist of a bottom intake and a desander. Further on, a reinforced concrete box
culvert conveys the water flow from the intake to the forebay. A PRFV penstock
connects it with the powerhouse, which is equipped with two Francis units of 10 MW
each.
1
J. Arbolí, C. Polimanti.
2 GEOMORPHOLOGY
The Project is located on a highly mountainous semi-jungle environment with
elevations ranging from 1’100 to 1’400 m asl, upstream the confluence of the valleys
eroded by the flow of each river, whose directions are W-SW and N-S, respectively.
The valleys are divided by a promontory that reaches an elevation of 2’300 m asl on
its peak in the SE sector that creates V-shaped valleys with slopes between 20° and 70°,
see Figure 1. The valleys are characterized by steep rock slopes on the proximities of the
river beds. Close to the axis of the headrace canals, cultivated terrains by local
inhabitants are mainly observed, while the highest part of the mountains is predominantly
covered by dense vegetation.
The existing streams, aligned with the maximum gradient, cut the valley slopes and
are fed by direct rainfalls and temporal natural springs, such that during summer most of
them present a dry condition. Some of the streams show cone-shaped deposits mainly
formed by “huaicos” (meaning debris flows in local terminology), which represent the
greatest geodynamic activity in the area and the highest risk for water intakes on both
rivers.
The morphology of the bottom of the valleys is characterized by the activity of the two
rivers, whose riverbeds are covered by big grain deposits and boulders reaching
diameters greater than several meters. This is a clear sign of the torrential flow of both
rivers, see Figure 2.
2
J. Arbolí, C. Polimanti.
Figure 2: Views of both the riverbeds at their respective Tyrolean weir locations.
At some points, the main river widens in low slope stretches, created by the
accumulation of recent alluvium material. On the other hand, the other river does not
present meanders, having an almost rectilinear trajectory with greater slopes than the
main river. Both rivers merge immediately downstream the Powerhouse on an area
primarily characterized by boulders, alluvium terraces reaching heights of 25 m above the
actual riverbed and rock outcrops. It is important to highlight that the bedrock is mostly
covered by superficial deposits, mainly from colluvium and old landslide deposits.
The geological and geotechnical characteristics of the valleys encountered along the
project have to be carefully studied in order to understand the main risks that any
structure located over the riverbed will need to cope and overcome while its operation.
Figure 3 shows a simple sample of typical roads and patterns presented on the project
area.
Figure 3: a) Existing access road to the project; b) Main access path to one of the intakes.
3 HYDROLOGY
Figures 4 and 5 showcase the daily flow discharge and the flood statistics as a function
of the return periods for both the rivers of the Project. These statistics have been
3
J. Arbolí, C. Polimanti.
calculated based on existing daily flow measurements from the hydrometric station
closest to the project location for a period of 21 years (1978-1998).
Figure 4: Daily water discharge of the rivers, extrapolated at the water intake of both rivers.
Figure 5: Flow statistics at the water intakes, blue and orange respectively.
4 PRECEDENTS
4
J. Arbolí, C. Polimanti.
Figure 6: Remains of a damaged water intake located downstream of the Project after experiencing a
“huaico” event during March 2016.
As part of the scope of the final design stage, a final geotechnical exploration
campaign was designed and carried out in order to better understand the geology and the
geotechnics of the construction area along the whole project. As a result, the main intake
was moved upstream in order to avoid a major landslide that had not been characterized
during the feasibility stage.
5 TYROLEAN WEIR
5
J. Arbolí, C. Polimanti.
inside the weir body. The bars of the rack are laid in the direction of the current and
inclined in the direction of the tail water so that coarse bed load is kept out of the
collection canal and transported further downstream. Particles smaller than the opening
between the rack bars will enter into the collection canal together with the water. Due to
the latter, a flushing device downstream, such as desander, is required in order to
guarantee the constraints of the power generation equipment.
Figure 7: Tyrolean weir conceptual profile and typical discharge coefficients depending on bar shape.
6
J. Arbolí, C. Polimanti.
(1)
(2)
where,
c: rack shape coefficient, (2)
μ: discharge coefficient for the rack based on the shape of the bars, see Figure 6
B: width of the rack
L: length of the rack
h: initial water depth at the beginning of the rack, (3)
a: interior width between bars
b: distance between internal axes of the bars
β: slope angle of the rack with respect to the horizontal
In order to characterize the initial water depth, h, measured orthogonally to the rack at its
base, as shown in Figure 7, the LCH of the EPFL4 has proposed the following relationship
with respect to the critical water depth, hcr,
(3)
(4)
(5)
where kc is a correction factor (5) for slope angles of racks greater than 30°, as it is the case
for both the water intakes of the Project.
7
J. Arbolí, C. Polimanti.
Figure 8: Geological characterization and borehole location at the main water intake axis.
The main design challenge to face, regarding this intake as well as along the whole
river, is the appearance of “huaico” events that originate in the upstream part of the
watershed and wildly flow along the riverbed.
Figure 9: Final geometry developed for the main water intake, 3D render.
8
J. Arbolí, C. Polimanti.
Figure 10: Geological characterization and borehole location at the water intake axis.
Figure 11: Final geometry developed for the water intake, 3D render.
9
J. Arbolí, C. Polimanti.
8 CONCLUSIONS
The concept phase of engineering solutions within the scope of hydropower projects is
critical and should take into consideration all the possible associated risks, not only
during construction but also during the operational phase. The scheme has to be tailored
to the characteristics of the project, increasing the importance of understanding the real
site conditions over the application of classical concepts.
According to this principle, site conditions were very deeply studied for the Project in
order to achieve a long-lasting solution that will operate properly in the future, even under the
influence of hazardous site conditions and yearly harmful events. As a result, a different water
intake concept was introduced to the project for both the intakes, leading not only to a simpler
scheme, but also a more economical solution, both in terms of construction and maintenance
activities.
REFERENCES
[1] GTZ - Planning of Water and Hydropower Intake Structures, 1989.
[2] Schleiss A. J., Aménagements Hydrauliques, Génie civil 3e année, LCH, EPFL, Nouvelle
éditon, 2004.
[3] Frank, J., Hydraulische Untersuchungen für das Tirle Wehr, Der Bauingenieur 1956,
Heft 3.
[4] Laboratoire de Constructions Hydrauliques - EPFL, Communication 26 : Standardization
of civil engineering works of small high-head hydropower plants and development of an
optimization tool, Lausanne 2006.
10