Lecture Notes
Lecture Notes
Production System
Input goes into the system. When going through the system, it becomes
transformed in some way making the output different than what came in,
resulting in something with different characteristics. Of course, a system
may have more than one input and output.
There are usually five types of ways of transforming input into output:
One should note that the classification of any production system relies on
many factors. These factors include type and volume of production.
Generally, there are three types of production systems divided into two
categories:
1. Intermittent production
Job Production
Batch Production
2. Continuous Production
Mass and Flow Production
Intermittent production
The following are the industries where the intermittent production system
is used:
Hospitals
Workshop
Film making
Building and bridge construction
Furniture manufacturing companies
The intermittent system is much more complex than continuous
production because every product has to be treated differently under the
constraint of limited resources.
Job Production
1. Only once
2. At irregular intervals
3. At regular intervals
Examples: Boutique, Automobile service center, typing shops, etc.
Continuous Production
For example, the production system of the food industry is based on the
demand forecast. The production of food is done on a large scale and on a
continuous basis. Similarly, in the fuel industry, large-scale production and
processing of crude oil and other raw sources takes place on a continuous
basis to get the usable form of fuel and compensate global energy
demand.
The continuous system, however, is very rigid and if there is a fault in one
operation the entire process is disturbed. Due to continuous flow, it
becomes necessary to avoid piling up of work or any blockage on the line.
Unless the fault is cleared immediately, it will force the preceding as well
as the subsequent stages to be stopped. Moreover, it is essential to
maintain stand-by equipment to meet any breakdowns resulting in
production stoppages. Thus investments in machines are fairly high.
2. Process/Flow Production:
1. Layout Type: In the case of job and batch production process layout
is appropriate. Whereas for mass or flow production system product
layout is best.
2. Product type and design: In the case of job and batch systems, a
wide range of products are produced but in small quantities. Hence,
product design changes as per the specifications of the product. In
contrast, for a continuous production system, either a few or one
product is produced in bulk. And the design of the product is
standardized, in which changes do not occur at frequent intervals.
3. Machine set up time: Machine set up time is high in the continuous
production system as compared to the intermittent system of
production. This is due to the frequent changes in the specification
of products and design.
4. Order size: Order size is small in the intermittent products. Whereas
the same is large in continuous production.
5. Machine Investment: High in case of intermittent production and low
for continuous production.
6. Material Handling cost: High in the intermittent production system.
However, material handling cost is low in the case of continuous
production.
7. Production capacity: In an intermittent production system, the
production capacity is not fully utilized. But, in the continuous
production system, it is completely utilized.
Table distinguishes between intermittent production system and
continuous production system:
PPC is affected by the different factors, which all are discussed below:
1) Use of Computers:
Modern factories are using office automation equipment like PC, punch
cards, etc. It helps accurate computation of required of men and
machines.
2) Seasonal Variations:
3) Test Marketing:
Losses occur due to accidents, fire, and theft of production inputs, mainly
materials and components. These are unpredictable. Shortage of input
due to such factors upset the planned production schedule in time and
quantity.
7) Production of Order:
8) Design Changes:
Design changes are issued by R & D and the engineering department. This
will necessarily force production planning control to change the input
materials and process.
Functions of PPC
f
unction of ppc
(A) Planning Phase:
Prior Planning:
In any type of work activity the following steps are necessary for planning
details of the work to be done:
Corrective Action:
1. Expediting. If the data collected from the production unit indicates that
there is a significant deviation from the plan and the plan cannot be
changed, then some action must be taken to get back on plan.
2. Replanning. It should be emphasized that the plan is not to be changed
but to be followed, however, if after expediting to correct deviation it is
found that, it is impossible to perform according to plan. It would be
necessary to replan the whole affair. It may also be found that there were
errors made while developing the original plan. In all such cases
replanning is necessary.
-scheduling production,
-personnel and
-inventory levels
-aggregate production,
inventory and
personnel levels
Benefits of PPC
As a best practice for quality assurance and quality control, the main goal
of production planning and control is to maximize the materials,
workforce, productivity time, and other resources used in the process of
manufacturing. With this technique, production managers also primarily
aim to ensure that production results are according to set quality,
quantity, and schedule.