Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

JSA 13 Backfilling

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

JOB SAFETY ANALYSIS

Name of Work: Fabrication, Erection, Testing and Commissioning of Mild Steel Vertical Storage Tanks (IFRVT &
CRVT) and Horizontal Underground Tanks, Including Tank Foundation and Allied Works for the Upcoming
Petroleum Storage Terminal at Hinauti, Mirzapur, Uttar Pradesh,
Work Order No.- 29494330 date 20.12.2023.
Project :IOCL TOP Project, Hinauti, Mirzapur, Uttar Pradesh

PART-A: Date: Work Permit No: Date:


JSA No: IOCL/MZP/2023-
2024/13
Unit: CIVIL/ Area: Location: Work Permit Type: HOT Work
MECHANICAL
Job Title: BACKFILLING WORK JSA Done By: Sign with Date
1

Job to be Executed by:


Department Contractor
CIVIL / MECHANICAL Adarsh Noble Corp Ltd

JSA Reviewed by (Name, Designation, Sign with Date)


1.

2.
JSA Approved by (Name, Designation, Sign with Date)
JOB SAFETY ANALYSIS
Name of Work: Fabrication, Erection, Testing and Commissioning of Mild Steel Vertical Storage Tanks (IFRVT &
CRVT) and Horizontal Underground Tanks, Including Tank Foundation and Allied Works for the Upcoming
Petroleum Storage Terminal at Hinauti, Mirzapur, Uttar Pradesh,
Work Order No.- 29494330 date 20.12.2023.
Project :IOCL TOP Project, Hinauti, Mirzapur, Uttar Pradesh

Sr. No. Sequence of Steps Potential Hazards Control Measures Person responsible

1 Training/Awareness to Accident hazard due to unqualified/ 1. Check qualification / experience. Permit


Supervisor/Operator and inexperienced operator and 2. Job responsibility to be clearly defined for each Receiver/Contractor
Job all Location precautions to be taken not known to individual.
workers. 3. Area should be cordoned off and only trained and
Injury/ fatality due to confusion and at authorized person to be allowed at site.
work site 4. Conduct tool box talk.
Job performed by untrained and
unauthorized person
2 Issuance of valid Work Injury/ fatality when start work without 1. Ensure Cold work permit before commencement of Permit
permit for Back filling & permit. work. Receiver/Contractor
Sub grade Work

3 Use of PPEs Non-use of PPEs may cause injury to 1. Ensure that all the relevant PPEs are used before Permit
workers commencement of work. Receiver/Contractor

4 Clearance before start of Proper clearance to be given to prevent any 1. Necessary precautions shall be taken for underground Permit
work. damage to the cables, sewer, Underground utility lines like cables, sewers, pipelines etc. and shut off Receiver/Contractor
pipelines drains and other Utilities. or disconnect if necessary.
2. Check for cable route markers and refer cable route
Proper clearance to avoid electrocution due layout etc.
to cutting of any cable 3. Approvals/ clearances from the concerned dept. shall be
obtained before commencement of the excavation job.
JOB SAFETY ANALYSIS
Name of Work: Fabrication, Erection, Testing and Commissioning of Mild Steel Vertical Storage Tanks (IFRVT &
CRVT) and Horizontal Underground Tanks, Including Tank Foundation and Allied Works for the Upcoming
Petroleum Storage Terminal at Hinauti, Mirzapur, Uttar Pradesh,
Work Order No.- 29494330 date 20.12.2023.
Project :IOCL TOP Project, Hinauti, Mirzapur, Uttar Pradesh

5 Manpower Mobilization Untrained operator 1. Only inducted worker shall be deputed at the work Permit
place. Receiver/Contractor
Lack of awareness 2. Given tool box talk to all workers.
3. Work should carry under supervision.
4. Safety induction should be given to all workers.
5. Gates pass & required PPE’S Safety helmet, safety
shoes, reflective jacket, hand gloves, safety goggle etc.
Must be provided
6 Transport the excavated Slips, Trips and falls 1. Clear the walkways, work area of equipment Mark, Permit
materials identify or barricade other obstruction. Receiver/Contractor
2. Deploy only authorized drivers to operate the vehicles.
3. Wear proper personal protective equipment (Hard
hats, reflective jackets, and safety shoes.)
4. Operators and helpers are to be equipped with valid
driver’s/ Operator’s license.
5. During the rain work should be stop.
6. Only authorized drives or operators should be to
operate the machinery/Equipment.
7. Vehicle/machinery should have valid legal documents
(RC book, fitness certificate, Insurance & Pollution).
7 Back fill the excavated soil Struck by /Against Heavy Equipment, 1. Isolate the equipment while back filling the soil. Permit
flying soil, protruding objects 2. Ensure all the electrical cables should be remove
/Overhead. Receiver/Contractor
3. Switch on the reverse horn while reversing the vehicle.
4. Understand and review hand signals.
5. Vehicle area should be clear from the objectives.
8 Compacting the soil Vibration 1. Wear proper personal protective equipment (Hard Permit
hats, reflective jackets and safety shoes.) Receiver/Contractor
2. Rotate the compaction tasks to minimize the worker
exposure to equipment vibration.
3. Use compactors with vibration dampening devices.
JOB SAFETY ANALYSIS
Name of Work: Fabrication, Erection, Testing and Commissioning of Mild Steel Vertical Storage Tanks (IFRVT &
CRVT) and Horizontal Underground Tanks, Including Tank Foundation and Allied Works for the Upcoming
Petroleum Storage Terminal at Hinauti, Mirzapur, Uttar Pradesh,
Work Order No.- 29494330 date 20.12.2023.
Project :IOCL TOP Project, Hinauti, Mirzapur, Uttar Pradesh

High Noise levels 4. Use anti- vibration gloves.


5. Use hearing protection when exposed to excessive
noise levels (greater than 85DBA over an 8-hours work
period.
9 In case of Emergency Confusion 1. Give awareness about emergency evacuation plan, Permit
keep emergency contact Number. Aware about Receiver/Contractor
Assembly Point.
10 Housekeeping Accident due to Non-use of PPE’s 1. Ensure work site clean after work completion. Permit
Accident due to waste materials at 2. Use Proper PPE’s for housekeeping. Receiver/Contractor
work place 3. Ensure every use and waste materials segregate
properly.

Part–B:Compliance audit by the Location In-charge / DSO while the job is being executed

Sl. Recommended Observation Compliance Status Checked by Officer with sign, Remarks
No. Action /Procedures & date, and time
Control measure

You might also like