Unit Cost Analysis
Unit Cost Analysis
FOR
4. REINFORCEMENTS
4.1 dia. 6 & dia. 8 mm. plain bars kg. 8.83 Birr/kg.
4.3 dia. 18 mm. and above deformed bars " 7.88 Birr/kg. 0.00
-1-
1.2 20cm. Clearing on wet & black soil. " 3.77 Birr/m2
1.3 Bulk excav. to a depth not exceeding 150cm loose and d m3 9.52 Birr/m3
1.4 Ditto. but on wet and black soil. " 15.38 Birr/m3
1.5 Trench excavation not exceeding 150cm. in loose and dr " 13.33 Birr/m3
1.6 Trench excavation not exceeding 150cm. in loose and dr " 22.22 Birr/m3
1.8 Excavation foundation pits to adepth not exceeding 150cm.on wet and b " 22.22 Birr/m3
1.10 Ditto. but, 150cm. - 300cm. But, on wet clay and black s " 33.33 Birr/m3
1.11 Excavation on soft rock to a depth not exceeding " 36.67 Birr/m3
1.13 Back fill excavated materials from the site. " 5.79 Birr/m3
1.14 Back fill selected excavated mats. from out side th " 35.21 Birr/m3
1.15 Cart away surplus excavated mats. 1km. from the " 12.18 Birr/m3
13.2 WC. Low Flash ( Tabor Ceramics ) " 610.83 Birr/pcs. 0.00
13.21 1/2 " Galvanaized Steel Pipe ( GSP ) ml. 35.36 Birr/ml.
- 16 -
13.32 75 mm. dia. PVC Pipe " 57.00 Birr/ml. Average of 13.31%13.33
13.43 1 m3 cap. Water tank ( Black Iron Sheet ) pcs. 864.72 Birr/pcs.
13.44 2 m3 cap. Water tank ( Black Iron Sheet ) " 1456.58 Birr/pcs.
13.45 1 m3 cap. Water tank (Galvanized Sheet Metal) " 1486.46 Birr/pcs.
13.46 2 m3 cap. Water tank ( Galvanaized Sheet Metal " 2450.37 Birr/pcs.
5.4 For Suspended slab & shear wall. " 68.18 Birr/m2
-7-
7. ROOFING WORKS
7.1 G32 CIS Roofing ( Including Truss & Purlins ) M2 59.37 Birr/m2
7.2 G30 CIS Roofing ( Including Truss & Purlins ) " 64.34 Birr/m2
7.3 G28 CIS Roofing ( Including Truss & Purlins ) " 75.70 Birr/m2
7.4 G32 C I S Roofing ( Without Truss & Purlin ) " 36.25 Birr/m2
7.5 G30 C I S Roofing ( Without Truss & Purlin ) " 41.23 Birr/m2
7.6 G28 C I S Roofing ( Without Truss & Purlin ) " 52.59 Birr/m2
7.7 10 cm. dia. Upper & Lower Chords Eucaliptus ml. 5.37 Birr/ml.
7.8 6 cm. dia. Vertical & Diagonal Members of a Tru " 3.52 Birr/ml.
7.10 EGA 300 & 4mm. Thick Roof cover m2 58.49 Birr/m2
7.11 Steel Truss & Purlin With RHS kg. 15.03 Birr/kg.
- 14 -
12.4 Three coats of synthetic paint to metal surface. " 12.44 Birr/m2
12.5 Two coats of varnish paint to wooden surface. " 12.82 Birr/m2
11.3 2 Coats of cement plastering to exposed beams and c " 19.70 Birr/m2
11.5 Cement pointing to brick wall surface (1:3). " 10.86 Birr/m2
11.7 Recessed pointing to dressed masonry wall surf " 4.44 Birr/m2
11.8 3cm. Thick cement screed flooring (1:3). " 23.43 Birr/m2
11.9 5cm. Thick cement screed flooring (1:3). " 39.00 Birr/m2
11.12 2cm. thick granolythic tile flooring (1:3). " 75.35 Birr/m2
11.13 2cm thick Harar marble flooring (1:3). " 267.11 Birr/m2
11.14 2cm thick white marble flooring (1:3). " 420.11 Birr/m2
11.22 10cm. High cement tile skirting (1:3). ml. 10.64 Birr/ml
11.23 10cm. High terrazzo tile skirting (1:3). " 13.16 Birr/ml
11.24 10cm. High Granolythic tile skirting (1:3). " 11.91 Birr/ml
- 12 -
11.29 8cm. high PVC tile skirting.( ITALY) " 13.83 Birr/ml
11.30 8cm. high PVC tile skirting.( ENGLAND) " 14.08 Birr/ml
11.33 30mm. thick terrazo window cill (1:3) on HCB. " 29.38 Birr/ml
11.34 30mm. thick terrazo window cill (1:3) on brick. " 32.70 Birr/ml
11.35 30mm. thick terrazo window cill (1:3) on stone. " 42.68 Birr/ml
11.36 30mm. thick Granite window cill (1:3) on HCB. " 118.63 Birr/ml
11.37 30mm. thick Granite window cill (1:3) on brick. " 138.58 Birr/ml
11.38 30mm. thick Granite window cill (1:3) on stone. " 191.08 Birr/ml
11.39 30mm. thick white marble window cill (1:3)on HCB " 103.33 Birr/ml
11.40 30mm.thick white marble window cill (1:3) on Bri " 119.08 Birr/ml
11.41 30mm. thick white marble window cill (1:3) on S " 165.88 Birr/ml
11.42 30mm. thick HARAR marble window cill (1:3)on " 80.38 Birr/ml
11.43 30mm. thick HARAR marble window cill (1:3)on B " 92.19 Birr/ml
11.44 30mm. thick HARAR marble window cill (1:3)on " 127.63 Birr/ml
11.45 30mm.thick granolythic window cill (1:3) on HCB " 56.15 Birr/ml
11.46 30mm.thick granolythic window cill (1:3) on Brick " 87.22 Birr/ml
11.51 20mm. thick Granite marble riser. (1:3). " 107.06 Birr/ml
11.52 20mm. thick white marble riser. (1:3). " 94.31 Birr/ml
- 13 -
11.53 20mm. thick Harar marble riser. (1:3). ml. 63.71 Birr/ml
11.54 20mm. thick Granolythic marble riser. (1:3). " 47.56 Birr/ml
11.55 20mm. thick Granite marble trechholds. (1:3). " 116.34 Birr/ml
11.56 20mm. thick white marble trechholds. (1:3). " 103.59 Birr/ml
11.62 2cm. thick Granite wall marble (1:2) . " 480.54 Birr/m2
11.63 2cm. thick Harar wall marble (1:2). " 263.79 Birr/m2
11.64 2cm. thick white Gojam wall marble (1:2). " 416.79 Birr/m2
11.65 Semi dressed stone pavement on 20cm. thick granular " 46.49 Birr/m2
11.66 C-15 8cm thick mass concrete pavement under hard c " 47.87 Birr/m2
-3-
3. CONCRETE WORKS
3.1 C-7 Lean Concrete (Hand mix) 1:2:7 m2 17.85 Birr/m2 5 cm. Thick
3.7 C-20 Concrete Slab 10 cm. thick (Hand mix) 1:2 m2 46.66 Birr/m2 10 cm. Thick
3.8 C-20 Concrete Slab 10 cm. thick (Mech. Mix) 1: " 51.03 Birr/m2 10 cm. Thick
-9-
9. METAL WORKS
9.1 Fully metal doors of 28LTZ without grill Pcs. 253.07 Br./m2
9.2 Fully metal doors of 38LTZ without grill " 268.95 Br./m2
9.6 90 cm high verndah grill & RHS post . " 150.20 Br./m2
-6-
6 . WALLING
6.1 Chicka Wall ( 18 cm. Thick ) m2 33.03 Birr/m2
6.4 12cm. thick Brick Wall Both Sides Left For Plastering. " 75.18 Birr/m2 Mortar Ratio ( 1:3 )
6.5 12cm. thick Brick Wall One Side Left For Plast. The Other For " 76.78 Birr/m2 " "
6.6 25cm. thick Brick Wall Both Sides Left For Plastering. " 144.21 Birr/m2 " "
6.7 25cm. thick Brick Wall One Side Left For Plast. The Other For " 147.69 Birr/m2 " "
6.8 10 cm. thick HCB Wall Both Sides Left For Plaste " 45.40 Birr/m2 " "
6.9 15 cm. thick HCB Wall Both Sides Left For Plaste " 64.56 Birr/m2 " "
6.10 15cm. thick HCB Wall One Side Left For Plast. The Other For " 65.73 Birr/m2 " "
6.11 20 cm. thick HCB Wall Both Sides Left For Plaste " 71.82 Birr/m2 " "
6.12 20cm. thick HCB Wall One Side Left For Plast. The Other For " 73.16 Birr/m2 " "
6.13 20 cm.thick HCB Wall Both Sides Left For Point " 74.70 Birr/m2 " "
6.14 10 cm. thick Solid Bloket Wall Both Sides Left For Plas " 59.95 Birr/m2 " "
6.15 10cm. thick Solid Blocket Wall One Side Left For Plast. The O " 61.29 Birr/m2 " "
6.16 10 cm.thick Solid Blocket Wall Both Sides Left Fo " 62.84 Birr/m2 " "
6.17 15 cm. thick Solid Bloket Wall Both Sides Left For Plas " 71.00 Birr/m2 " "
6.18 15cm. thick Solid Blocket Wall One Side Left For Plast. The O " 72.34 Birr/m2 " "
6.19 15 cm.thick Solid Blocket Wall Both Sides Left Fo " 73.89 Birr/m2 " "
- 17 -
14.14 Flourecent fitting type philips TMS 012/136 with 1xTLD No. 182.75 Birr/No.
14.15 Flourecent fitting type philipsTMW 065/136 with 1xTLD No. 320.25 Birr/No.
14.16 Flourecent fitting type philipsTMW 065/236 with 1xTLD No. 570.25 Birr/No.
14.17 Fitting type Simense 5NL-510 with 60 wattglobe No. 57.75 Birr/No.
-2-
2 . MASONRY WORKS
2.1 50cm. thick masonry foundation (B.G.L). M3 196.19 Birr/m3
2.3 40cm. thick elevation wall (One side dressed) . M2 132.66 Birr/m2
2.4 40cm. thick elevation wall (Two side dressed). " 144.83 Birr/m2
-8-
8.4 Tanged & Groved ( T & G ) Tidwood Ceiling. " 186.38 Birr/m2 0.00
8.5 (90x210 cm.) Flush wooden door Coverd With Kerero " 274.13 Birr/m2
8.6 (90x210 cm.) Flush wooden door Coverd With Mahogo " 489.15 Birr/m2
8.7 Framed & Panelled solid Doors & Windows . " 293.26 Birr/m2 0
8.8 Built In Cupboard ( Four drawers & openings ) . " 625.98 Birr/m2
-1-
A= Materials Unit Cost 21.193 Birr/m2 B= Manpower Unit Cost 7.04 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 28.23 Birr/m2
Over head cost : 7% 1.98 "
Profit Cost: 10% 2.82 "
Total Unit Cost : 33.03 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
A= Materials Unit Cost 58.267 Birr/m2 B= Manpower Unit Cost 1.90 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 60.17 Birr/m2
Over head cost : 10% 6.02 "
Profit Cost: 15% 9.02 "
Total Unit Cost : 75.21 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Materials Unit Cost 45.167 Birr/m2 B= Manpower Unit Cost 1.90 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: ___________________
Direct Cost of Work Item = A+B+C = 47.07 Birr/m2
Over head cost : 10% 4.71 "
Profit Cost: 15% 7.06 "
Total Unit Cost : 58.83 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Materials Unit Cost 44.761 Birr/m2 B= Manpower Unit Cost 15.38 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 60.15 Birr/m2
Over head cost : 10% 6.01 "
Profit Cost: 15% 9.02 "
Total Unit Cost : 75.18 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15% Wastage = 0.026 m /m
3 2
-5-
A= Materials Unit Cost 44.761 Birr/m2 B= Manpower Unit Cost 16.67 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 61.43 Birr/m2
Over head cost : 10% 6.14 "
Profit Cost: 15% 9.21 "
Total Unit Cost : 76.78 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15% Wastage = 0.026 m /m
3 2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-6-
A= Materials Unit Cost 93.15 Birr/m2 B= Manpower Unit Cost 22.22 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 115.37 Birr/m2
Over head cost : 10% 11.54 "
Profit Cost: 15% 17.31 "
Total Unit Cost : 144.21 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15% Wastage = 0.062 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-7-
A= Materials Unit Cost 93.15 Birr/m2 B= Manpower Unit Cost 25.00 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 118.15 Birr/m2
Over head cost : 10% 11.81 "
Profit Cost: 15% 17.72 "
Total Unit Cost : 147.69 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15% Wastage = 0.062 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 8-
A= Materials Unit Cost 25.07 Birr/m2 B= Manpower Unit Cost 11.25 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 36.32 Birr/m2
Over head cost : 10% 3.63 "
Profit Cost: 15% 5.45 "
Total Unit Cost : 45.40 Birr/m2
Remarks : Mortar Quantity ( 1:3 ) With 15 % Wastage =0.0092 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-9-
A= Materials Unit Cost 37.59 Birr/m2 B= Manpower Unit Cost 14.06 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 51.65 Birr/m2
Over head cost : 10% 5.16 "
Profit Cost: 15% 7.75 "
Total Unit Cost : 64.56 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage = 0.0138 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 10 -
A= Materials Unit Cost 37.59 Birr/m2 B= Manpower Unit Cost 15.00 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 52.59 Birr/m2
Over head cost : 10% 5.26 "
Profit Cost: 15% 7.89 "
Total Unit Cost : 65.73 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage = 0.0138 m /m
3 2
- 11 -
A= Materials Unit Cost 42.45 Birr/m2 B= Manpower Unit Cost 15.00 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 57.45 Birr/m2
Over head cost : 10% 5.75 "
Profit Cost: 15% 8.62 "
Total Unit Cost : 71.82 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage =0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 12 -
A= Materials Unit Cost 42.45 Birr/m2 B= Manpower Unit Cost 16.07 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 58.52 Birr/m2
Over head cost : 10% 5.85 "
Profit Cost: 15% 8.78 "
Total Unit Cost : 73.16 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage = 0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 13 -
- 14 -
- 15 -
A= Materials Unit Cost 32.96 Birr/m2 B= Manpower Unit Cost 16.07 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 49.03 Birr/m2
Over head cost : 10% 4.90 "
Profit Cost: 15% 7.36 "
Total Unit Cost : 61.29 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage = 0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 16 -
A= Materials Unit Cost 32.96 Birr/m2 B= Manpower Unit Cost 17.31 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 50.27 Birr/m2
Over head cost : 10% 5.03 "
Profit Cost: 15% 7.54 "
Total Unit Cost : 62.84 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage =0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 17 -
A= Materials Unit Cost 41.80 Birr/m2 B= Manpower Unit Cost 15.00 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 56.80 Birr/m2
Over head cost : 10% 5.68 "
Profit Cost: 15% 8.52 "
Total Unit Cost : 71.00 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage =0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 18 -
A= Materials Unit Cost 41.80 Birr/m2 B= Manpower Unit Cost 16.07 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 57.87 Birr/m2
Over head cost : 10% 5.79 "
Profit Cost: 15% 8.68 "
Total Unit Cost : 72.34 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage = 0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 19 -
A= Materials Unit Cost 41.80 Birr/m2 B= Manpower Unit Cost 17.31 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 59.11 Birr/m2
Over head cost : 10% 5.91 "
Profit Cost: 15% 8.87 "
Total Unit Cost : 73.89 Birr/m2
Remark : Mortar Quantity ( 1:3 ) With 15 % Wastage =0.0184 m3/m2
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
A= Materials Unit Cost 6600.00 Birr/Pcs B= Manpower Unit Cost 68.00 Birr/Pcs C=Equipment Unit Cost 0 Birr/Pcs
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 6668.00 Birr/Pcs
Over head cost : 10% 666.80 "
Profit Cost: 15% 1000.20 "
Total Unit Cost : 8335.00 Birr/Pcs
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Materials Unit Cost 1300.00 Birr/Pcs B= Manpower Unit Cost 68.00 Birr/Pcs C=Equipment Unit Cost 0 Birr/Pcs
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 1368.00 Birr/Pcs
Over head cost : 10% 136.80 "
Profit Cost: 15% 205.20 "
Total Unit Cost : 1710.00 Birr/Pcs
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
A= Materials Unit Cost 44.75 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 74.25 Birr/Pt
Over head cost : 10% 7.43 "
Profit Cost: 15% 11.14 "
Total Unit Cost : 92.81 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Materials Unit Cost 38.75 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 68.25 Birr/Pt
Over head cost : 10% 6.83 "
Profit Cost: 15% 10.24 "
Total Unit Cost : 85.31 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
A= Materials Unit Cost 31.25 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 60.75 Birr/Pt
Over head cost : 10% 6.08 "
Profit Cost: 15% 9.11 "
Total Unit Cost : 75.94 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-6-
A= Materials Unit Cost 104.50 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 134.00 Birr/Pt
Over head cost : 10% 13.40 "
Profit Cost: 15% 20.10 "
Total Unit Cost : 167.50 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-7-
A= Materials Unit Cost 102.00 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 131.50 Birr/Pt
Over head cost : 10% 13.15 "
Profit Cost: 15% 19.72 "
Total Unit Cost : 164.38 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-8-
A= Materials Unit Cost 36.08 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 65.58 Birr/Pt
Over head cost : 10% 6.56 "
Profit Cost: 15% 9.84 "
Total Unit Cost : 81.98 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-9-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: ELECTRICAL INSTALLATION LABOUR HOURLY OUTPUT: 0.5 Pt/hr
WORK ITEM: (14.9 ) Telephone point EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 83.63 Birr/Pt
A= Materials Unit Cost 37.40 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 66.90 Birr/Pt
Over head cost : 10% 6.69 "
Profit Cost: 15% 10.04 "
Total Unit Cost : 83.63 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 10 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: ELECTRICAL INSTALLATION LABOUR HOURLY OUTPUT: 0.5 Pt/hr
WORK ITEM: (14.10 ) TV point EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 104.63 Birr/Pt
A= Materials Unit Cost 54.20 Birr/Pt B= Manpower Unit Cost 29.50 Birr/Pt C=Equipment Unit Cost 0 Birr/Pt
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 83.70 Birr/Pt
Over head cost : 10% 8.37 "
Profit Cost: 15% 12.56 "
Total Unit Cost : 104.63 Birr/Pt
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-11-
A= Materials Unit Cost 905.00 Birr/No. B= Manpower Unit Cost 36.88 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 941.88 Birr/No.
Over head cost : 10% 94.19 "
Profit Cost: 15% 141.28 "
Total Unit Cost : 1177.34 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 12 -
A= Materials Unit Cost 1060.00 Birr/No. B= Manpower Unit Cost 36.88 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 1096.88 Birr/No.
Over head cost : 10% 109.69 "
Profit Cost: 15% 164.53 "
Total Unit Cost : 1371.09 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 13 -
A= Materials Unit Cost 1480.00 Birr/No. B= Manpower Unit Cost 36.88 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 1516.88 Birr/No.
Over head cost : 10% 151.69 "
Profit Cost: 15% 227.53 "
Total Unit Cost : 1896.09 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 14 -
A= Materials Unit Cost 140.00 Birr/No. B= Manpower Unit Cost 6.20 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 146.20 Birr/No.
Over head cost : 10% 14.62 "
Profit Cost: 15% 21.93 "
Total Unit Cost : 182.75 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 15 -
A= Materials Unit Cost 250.00 Birr/No. B= Manpower Unit Cost 6.20 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 256.20 Birr/No.
Over head cost : 10% 25.62 "
Profit Cost: 15% 38.43 "
Total Unit Cost : 320.25 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 16 -
A= Materials Unit Cost 450.00 Birr/No. B= Manpower Unit Cost 6.20 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 456.20 Birr/No.
Over head cost : 10% 45.62 "
Profit Cost: 15% 68.43 "
Total Unit Cost : 570.25 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 17 -
A= Materials Unit Cost 40.00 Birr/No. B= Manpower Unit Cost 6.20 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 46.20 Birr/No.
Over head cost : 10% 4.62 "
Profit cost 15% 6.93 "
Total Unit Cost : 57.75 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 18 -
A= Materials Unit Cost 180.00 Birr/No. B= Manpower Unit Cost 6.20 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 186.20 Birr/No.
Over head cost : 10% 18.62 "
Profit Cost: 15% 27.93 "
Total Unit Cost : 232.75 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 19 -
A= Materials Unit Cost 3.00 Birr/No. B= Manpower Unit Cost 3.10 Birr/No. C=Equipment Unit Cost 0 Birr/No.
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 6.10 Birr/No.
Over head cost : 10% 0.61 "
Profit Cost: 15% 0.91 "
Total Unit Cost : 7.63 Birr/No.
Remark :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
________
-1-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT : REINFORCEMENT BARS LABOUR HOURLY OUTPUT: 9 kg/hr.
WORK ITEM: ( 4.1 ) dia. 6 & dia. 8 mm. plain bars EQUIPEMENT:
A= Materials Unit Cost 6.28 birr/kg B= Manpower Unit Cost 0.79 Birr/kg. Equipment Unit Cost 0.00 Birr/kg.
Total of (1:02) Total of (1:03)
hourly output: 7.08/9=0.79 Hourly output: ____________
Direct Cost of Work Item = A+B+C = 7.06 Birr/kg.
Over head cost : 10% 0.71 "
Profit Cost: 15% 1.06 "
Total Unit Cost : 8.83 Birr/kg.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT : REINFORCEMENT BARS LABOUR HOURLY OUTPUT: 12.5 kg./hr
WORK ITEM: ( 4.2 ) dia. 10 - dia. 16 mm. deformed bars EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: _ 1 kg RESULT: 7.45 Birr/kg.
A= Materials Unit Cost 5.06 Birr/kg.B= Manpower Unit Cost 1.00 Birr/kg. C= Equipment Unit Cost 0 Birr/kg.
Total of (1:02) Total of (1:03)
Hourly Output 12.5/12.5=1.00 Hourly output: ____________
Direct Cost of Work Item = A+B+C = 6.06 Birr/kg.
Over head cost : 15% 0.91 "
Profit Cost: 15% 0.91 "
Total Unit Cost : 7.88 Birr/kg.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.38 pcs./hr.
WORK ITEM: ( 13.1 ) Low flash WC ( Italy made ) EQUIPEMENT: Drill ( hand held ) = 4.53 Birr/hr
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 1150.83 Birr/pcs.
-2-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.38 PCS./hr.
WORK ITEM: ( 13.2 ) WC. Low Flash ( Tabor Ceramics ) EQUIPEMENT: Drilling Machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 610.83 Birr/pcs.
-4-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.38 PCS./hr.
WORK ITEM: ( 13.4 ) WC with high level flashing ( Turkish ) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: _ 1 pcs. RESULT: 632.53 Birr/pcs.
-5-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.38 pcs./hr.
WORK ITEM: ( 13.5 ) Hand wash basine ( Italy made ) EQUIPEMENT: Drilling machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 556.83 Birr/pcs.
-6-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.38 pcs./hr.
WORK ITEM: ( 13.6 ) 50 X 60 HWB ( Italy ) EQUIPEMENT: Drilling machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 706.83 Birr/pcs.
A= Materials Unit Cost 550 Birr/pcs. B= Manpower Unit Cost 27.11 Birr/pcs. C= Equipment Unit Cost 11.92 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 10.3/0.38 = 27.10 Hourly output: 4.53/0.38 = 11.90
Direct Cost of Work Item = A+B+C = 589.03 Birr/pcs.
Over head cost : 10% 58.90 "
Profit Cost: 10% 58.90 "
Total Unit Cost : 706.83 Birr/pcs.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-7-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.18 pcs./hr.
WORK ITEM: ( 13.7 ) Bath tab ( Italy ) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 1148.67 Birr/pcs.
A= Materials Unit Cost 900 Birr/pcs. B= Manpower Unit Cost 57.22 Birr/pcs. C= Equipment Unit Cost 0.00 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 10.3/0. .18 =57.22 Hourly output: _____________
Direct Cost of Work Item = A+B+C = 957.22 Birr/pcs.
Over head cost : 10% 95.72 "
Profit Cost: 10% 95.72 "
Total Unit Cost : 1148.67 Birr/pcs.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-8-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.38 pcs./hr.
WORK ITEM: ( 13.8 ) Bidet EQUIPEMENT: Drilling machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 556.83 Birr/pcs.
A= Materials Unit Cost 425 Birr/pcs. B= Manpower Unit Cost 27.11 Birr/pcs. C= Equipment Unit Cost 11.92 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 10.3/0.38 = 27.10 Hourly output: 4.53/0.38 = 11.90
Direct Cost of Work Item = A+B+C = 464.03 Birr/pcs.
Over head cost : 10% 46.40 "
Profit Cost: 10% 46.40 "
Total Unit Cost : 556.83 Birr/pcs.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-9-
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.3 pcs./hr.
WORK ITEM: ( 13.9) Shower plate EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 545.20 Birr/pcs.
A= Materials Unit Cost 420 Birr/pcs. B= Manpower Unit Cost 34.33 Birr/pcs. C= Equipment Unit Cost 0.00 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 10.30/0.30=34.33 Hourly output: ___________
Direct Cost of Work Item = A+B+C = 454.33 Birr/pcs.
Over head cost : 10% 45.43 "
Profit Cost: 10% 45.43 "
Total Unit Cost : 545.20 Birr/pcs.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 10 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.28 pcs./hr.
WORK ITEM: ( 13.10 ) urinals EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 545.98 Birr/pcs.
A= Materials Unit Cost 400 Birr/pcs. B= Manpower Unit Cost 36.79 Birr/pcs. C= Equipment Unit Cost 0.00 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 10.30/0.28 =36.79 Hourly output: ___________
Direct Cost of Work Item = A+B+C = 436.79 Birr/pcs.
Over head cost : 10% 43.68 "
Profit Cost: 15% 65.52 "
Total Unit Cost : 545.98 Birr/pcs.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 11 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.28 pcs./hr.
WORK ITEM: ( 13.11 ) Kitchen sink ( singel bowel) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 548.14 Birr/pcs.
- 12 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.24 pcs./hr.
WORK ITEM: ( 13.12 ) Kitchen sink ( double bowel) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 747.50 Birr/pcs.
- 13 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.88 pcs./hr.
WORK ITEM: ( 13.13 ) Towel rack EQUIPEMENT: drilling machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 57.29 Birr/pcs.
- 14 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.88 pcs./hr.
WORK ITEM: ( 13.14 ) Toilet paper holder EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 57.10 Birr/pcs.
- 15 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.88 pcs./hr.
WORK ITEM: ( 13.15 ) soap holder EQUIPEMENT: .
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 50.85 Birr/pcs.
- 16 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1 pcs./hr.
WORK ITEM: ( 13.16 ) Glass mirror EQUIPEMENT: drilling machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 161.91 Birr/pcs.
- 17 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.25 pcs./hr.
WORK ITEM ( 13.17 ) Floor drain EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT 97.80 Birr/pcs.
- 18 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.19 pcs./hr.
WORK ITEM: ( 13.18 ) Water heatr ( 50 Lit. Cap. ) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT 1097.34 Birr/pcs.
- 19 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.19 pcs./hr.
WORK ITEM: ( 13.19 ) Water heatr ( 80 Lit. capacity ) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT 1235.34 Birr/pcs.
- 20 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.19 pcs./hr.
WORK ITEM: ( 13.20 ) Water heatr (120 Lit. capacity ) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT 1442.34 Birr/pcs.
- 21 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.85 ml./hr.
WORK ITEM: ( 13.21 ) 1/2 " Galvanaized Steel Pipe ( GSP ) EQUIPEMENT: Flera + Kaabaleto
TOTAL QANTITY OF WORK ITEM: 21 m. RESULT: 35.36 Birr/ml.
- 22 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.85 ml./hr.
WORK ITEM: ( 13.22 ) 3/4" Galvanaized Steel Pipe ( GSP ) EQUIPEMENT: Flera + Kaabaleto
TOTAL QANTITY OF WORK ITEM: 34 ml. RESULT: 31.71 Birr/ml.
A= Materials Unit Cost 17.184 Birr/ml. B= Manpower Unit Cost 6.02 Birr/ml. C= Equipment Unit Cost 2.16 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 11.13/1.85 = 6.02 Hourly output: 4/1.85 = 2.16
Direct Cost of Work Item = A+B+C = 25.36 Birr/ml.
Over head cost : 10% 2.54 Birr/ml.
Profit Cost: 15% 3.80 Birr/ml.
Total Unit Cost : 31.71 Birr/ml.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 23 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.5 ml./hr.
WORK ITEM: ( 13.23 ) 1" Galvanaized Steel Pipe ( GSP ) EQUIPEMENT: Flera + Kabaleto
TOTAL QANTITY OF WORK ITEM: 49 ml. RESULT: 39.53 Birr/ml.
Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)
- 24 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.5 ml./hr.
WORK ITEM: ( 13.24) 2" Galvanaized Steel Pipe ( GSP ) EQUIPEMENT: Flera + Kabaleto
TOTAL QANTITY OF WORK ITEM: 50 ml. RESULT: 67.38 Birr/ml.
Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)
- 25 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1 ml./hr.
WORK ITEM: ( 13.25) 3" Galvanaized Steel Pipe ( GSP ) EQUIPEMENT: Flera + Kabaleto
TOTAL QANTITY OF WORK ITEM: 100 ml. RESULT: 95.40 Birr/ml.
- 26 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1 pcs./hr.
WORK ITEM: ( 13.26) Gate Valves 1/2" EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 23.75 Birr/pcs.
- 27 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1 pcs./hr.
WORK ITEM: ( 13.27) Gate Valves 3/4" EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 27.50 Birr/pcs.
- 28 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1 pcs./hr.
WORK ITEM: ( 13.28) Gate Valves 1" EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 37.50 Birr/pcs.
A= Materials Unit Cost _______________________ B= Manpower Unit Cost ________________ C= Equipment Unit Cost ____________
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: ________________
Direct Cost of Work Item = A+B+C =
Over head cost :
Profit Cost:
Total Unit Cost : 44.00 + 70.00 = 114/2 = 57 Birr/ml
Remark : Taken Average Of Item No. ( 13.31 ) And ( 13.33 )
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 33 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.93 ml./hr.
WORK ITEM: ( 13.33) 100 mm. Dia. PVC Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 6.51 ml. RESULT: 70.67 Birr/ml.
A= Materials Unit Cost 12.343 Birr/ml.B= Manpower Unit Cost 3.91 Birr/ml. C= Equipment Unit Cost 0.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/6.88 = 3.91 Hourly output: _______________
Direct Cost of Work Item = A+B+C = 16.25 Birr/ml.
Over head cost : 10% 1.63 "
Profit Cost: 15% 2.44 "
Total Unit Cost : 20.32 Birr/ml.
Remark : _________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 35 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 6.88 ml./hr.
WORK ITEM: ( 13.35 ) 15 cm. dia. Concrete Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 26.10 Birr/ml.
- 36 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 6.88 ml./hr.
WORK ITEM: ( 13.36 ) 20 cm. dia. Concrete Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 31.81 Birr/ml.
A= Materials Unit Cost 21.536 Birr/ml. B= Manpower Unit Cost 3.91 Birr/ml. C= Equipment Unit Cost 0.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/6.88 = 3.91 Hourly output: ________________
Direct Cost of Work Item = A+B+C = 25.45 Birr/ml.
Over head cost : 10% 2.54 "
Profit Cost: 15% 3.82 "
Total Unit Cost : 31.81 Birr/ml.
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 37 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 6.88 ml./hr.
WORK ITEM: ( 13.37 ) 30 cm. dia. Concrete Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 43.30 Birr/ml.
- 38 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 3.13 ml./hr.
WORK ITEM: ( 13.38 ) 40 cm. dia. Concrete Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 60.65 Birr/ml.
A= Materials Unit Cost 39.922 Birr/ml. B= Manpower Unit Cost 8.59 Birr/ml. C= Equipment Unit Cost 0.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/3.13 = 8.60 Hourly output: ________________
Direct Cost of Work Item = A+B+C = 48.52 Birr/ml.
Over head cost : 10% 4.85 "
Profit Cost: 15% 7.28 "
Total Unit Cost : 60.65 Birr/ml.
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 39 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 3.13 ml./hr.
WORK ITEM: ( 13.39 ) 60 cm. dia. Concrete Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 99.57 Birr/ml.
A= Materials Unit Cost 71.065 Birr/ml. B= Manpower Unit Cost 8.59 Birr/ml. C= Equipment Unit Cost 0.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/3.13 = 8.60 Hourly output: _______________
Direct Cost of Work Item = A+B+C = 79.66 Birr/ml.
Over head cost : 10% 7.97 "
Profit Cost: 15% 11.95 "
Total Unit Cost : 99.57 Birr/ml.
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 40 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 3.13 ml./hr.
WORK ITEM: ( 13.40 ) 80 cm. dia. Concrete Pipe EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 163.59 Birr/ml.
A= Materials Unit Cost 122.28 Birr/ml. B= Manpower Unit Cost 8.59 Birr/ml. C= Equipment Unit Cost 0.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/3.13 = 8.60 Hourly output: _____________
Direct Cost of Work Item = A+B+C = 130.87 Birr/ml.
Over head cost : 10% 13.09 "
Profit Cost: 15% 19.63 "
Total Unit Cost : 163.59 Birr/ml.
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 41 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.25 ml./hr.
WORK ITEM: ( 13.41 ) 100 cm. dia. Concrete Pipe EQUIPEMENT: Self Propelled Crane
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 270.27 Birr/ml.
A= Materials Unit Cost 173.5 Birr/ml. B= Manpower Unit Cost 21.52 Birr/ml. C= Equipment Unit Cost 40.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/1.25 = 21.52 Hourly output: 50.00/1.25 = 40.00
Direct Cost of Work Item = A+B+C = 235.02 Birr/ml.
Over head cost : 5% 11.75 "
Profit Cost: 10% 23.50 "
Total Unit Cost : 270.27 Birr/ml.
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 42 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 1.25 ml./hr.
WORK ITEM: ( 13.42 ) 120 cm. dia. Concrete Pipe EQUIPEMENT: Self Propelled Crane
TOTAL QANTITY OF WORK ITEM: 1 ml. RESULT: 307.36 Birr/ml.
A= Materials Unit Cost 205.75 Birr/ml. B= Manpower Unit Cost 21.52 Birr/ml. C= Equipment Unit Cost 40.00 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output 26.90/1.25 = 21.52 Hourly output: 50.00/1.25 =40.00
Direct Cost of Work Item = A+B+C = 267.27 Birr/ml.
Over head cost : 5% 13.36 "
Profit Cost: 10% 26.73 "
Total Unit Cost : 307.36 Birr/ml.
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 43 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.19 pcs./hr.
WORK ITEM: ( 13.43 ) 1 m3 cap. Water tank ( Black Iron Sheet ) EQUIPEMENT: Welding Machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 864.72 Birr/pcs.
A= Materials Unit Cost 560.15 Birr/pcs. B= Manpower Unit Cost 46.54 Birr/pcs. C= Equipment Unit Cost 179.41 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 8.75/0.188 = 46.54 Hourly output: 33.73/0.188 =179.42
Direct Cost of Work Item = A+B+C = 786.11 Birr/pcs.
Over head cost : 5% 39.31 "
Profit Cost: 5% 39.31 "
Total Unit Cost : 864.72 Birr/pcs.
Remark : __________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 44 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.13 pcs./hr.
WORK ITEM: ( 13.44 ) 2 m3 cap. Water tank ( Black Iron Sheet ) EQUIPEMENT: Welding Machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. RESULT: 1456.58 Birr/pcs.
A= Materials Unit Cost 984.32 Birr/pcs. B= Manpower Unit Cost 70.00 Birr/pcs. C= Equipment Unit Cost 269.84 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 8.75/0.125 = 70 Hourly output: 33.73/0.125=269.84
Direct Cost of Work Item = A+B+C = 1324.16 Birr/pcs.
Over head cost : 5% 66.21 "
Profit Cost: 5% 66.21 "
Total Unit Cost : 1456.58 Birr/pcs.
Remark : __________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 45 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.19 pcs./hr.
WORK ITEM: ( 13.45 ) 1 m3 cap. Water tank (Galvanized Sheet Metal) EQUIPEMENT: Welding Machine
TOTAL QANTITY OF WORK ITEM: 1 pcs. = 6.3m2 RESULT: 1486.46 Birr/pcs.
- 46 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.13 pcs./hr.
WORK ITEM: ( 13.46 ) 2 m3 cap. Water tank ( Galvanaized Sheet Metal ) EQUIPEMENT: Welding Machine
TOTAL QANTITY OF WORK ITEM: 1 pcs.=10.5m2 RESULT: 2450.37 Birr/pcs.
- 47 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: SANITARY INSTALLATION LABOUR HOURLY OUTPUT: 0.19 pcs./hr.
WORK ITEM: ( 13.47 ) 1 m3 cap. Water tank ( Aluminium ) EQUIPEMENT: Welding Machine
TOTAL QANTITY OF WORK ITEM: 1 pcs.=6.3m2 RESULT: 1593.59 Birr/pcs.
A= Materials Unit Cost 1236.1 Birr/pcs. B= Manpower Unit Cost 33.24 Birr/pcs. C= Equipment Unit Cost 179.41 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output 6.25/0.188 = 33.25 Hourly output: 33.73/0.188=179.42
Direct Cost of Work Item = A+B+C = 1448.72 Birr/pcs.
Over head cost : 5% 72.44 "
Profit Cost: 5% 72.44 "
Total Unit Cost : 1593.59 Birr/pcs.
Remark : __________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
5 = 40.00
-1-
A= Materials Unit Cost 0 Birr/m2B= Manpower Unit Cost 1.618 Birr/m2 C= Equipment Unit Cost 0.18 Birr/m2
Total of (1:02) 1.44 Total of (1:03)
Hourly Output: 0.89 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 1.80 Birr/m2
Over head cost : 10% 0.18 "
Profit Cost: 15% 0.27 "
Total Unit Cost : 2.25 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Materials Unit Cost 0 Birr/m2B= Manpower Unit Cost 2.717 Birr/m2 C= Equipment Unit Cost 0.30 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
Direct Cost of Work Item = A+B+C = 3.02 Birr/m2
Over head cost : 10% 0.30 "
Profit Cost: 15% 0.45 "
Total Unit Cost : 3.77 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
A= Materials Unit Cost 0 Birr/m3B= Manpower Unit Cost 11.08 Birr/m3 C= Equipment Unit Cost 1.23 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 12.31 Birr/m3
Over head cost : 10% 1.23 "
Profit Cost: 15% 1.85 "
Total Unit Cost : 15.38 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
-6-
-7-
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 18 Birr/m3 C= Equipment Unit Cost 2.00 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _____________
Direct Cost of Work Item = A+B+C = 20.00 Birr/m3
Over head cost : 10% 2.00 "
Profit Cost: 15% 3.00 "
Total Unit Cost : 25.00 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-8-
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 16 Birr/m3 C= Equipment Unit Cost 1.78 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ____________
Direct Cost of Work Item = A+B+C = 17.78 Birr/m3
Over head cost : 10% 1.78 "
Profit Cost: 15% 2.67 "
Total Unit Cost : 22.22 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-9-
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 10.29 Birr/m3 C= Equipment Unit Cost 1.14 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ____________
Direct Cost of Work Item = A+B+C = 11.43 Birr/m3
Over head cost : 10% 1.14 "
Profit Cost: 15% 1.71 "
Total Unit Cost : 14.29 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 10 -
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 24 Birr/m3 C= Equipment Unit Cost 2.67 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
Direct Cost of Work Item = A+B+C = 26.67 Birr/m3
Over head cost : 10% 2.67 "
Profit Cost: 15% 4.00 "
Total Unit Cost : 33.33 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 11 -
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 24 Birr/m3 C= Equipment Unit Cost 5.33 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 29.33 Birr/m3
Over head cost : 10% 2.93 "
Profit Cost: 15% 4.40 "
Total Unit Cost : 36.67 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-12 -
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 130 Birr/m3 C= Equipment Unit Cost 18.29 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
Direct Cost of Work Item = A+B+C = 148.72 Birr/m3
Over head cost : 10% 14.87 "
Profit Cost: 15% 22.31 "
Total Unit Cost : 185.89 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-13 -
A= Materials Unit Cost 0 Birr/m3 B= Manpower Unit Cost 4.23 Birr/m3 C= Equipment Unit Cost 0.40 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 4.63 Birr/m3
Over head cost : 10% 0.46 "
Profit Cost: 15% 0.69 "
Total Unit Cost : 5.79 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-14 -
-15 -
-16 -
-1-
A= Materials Unit Cost 4.503 Birr/m2 B= Manpower Unit Cost 2.53 Birr/m2 C= Equipment Unit Cost 0.09 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 7.12 Birr/m2
Over head cost : 10% 0.71 "
Profit Cost: 15% 1.07 "
Total Unit Cost : 8.90 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2 -
A= Materials Unit Cost 3.411 Birr/m2 B= Manpower Unit Cost 1.26 Birr/m2 C= Equipment Unit Cost 0.04 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ____________
Direct Cost of Work Item = A+B+C = 4.71 Birr/m2
Over head cost : 10% 0.47 "
Profit Cost: 15% 0.71 "
Total Unit Cost : 5.89 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
A= Materials Unit Cost 4.287 Birr/m2 B= Manpower Unit Cost 3.17 Birr/m2 C= Equipment Unit Cost 0.11 Birr/m2
Total of (1:02) 4.75 Total of (1:03)
Hourly Output: 1.5 Hourly output: _______________
Direct Cost of Work Item = A+B+C = 7.56 Birr/m2
Over head cost : 10% 0.76 "
Profit Cost: 15% 1.13 "
Total Unit Cost : 9.45 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Materials Unit Cost 6.304 Birr/m2 B= Manpower Unit Cost 3.65 Birr/m2 C= Equipment Unit Cost 0.00 Birr/m2
Total of (1:02) 4.75 Total of (1:03)
Hourly Output: 1.3 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 9.95 Birr/m2
Over head cost : 10% 1.00 "
Profit Cost: 15% 1.49 "
Total Unit Cost : 12.44 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
A= Materials Unit Cost 6.328 Birr/m2 B= Manpower Unit Cost 3.8 Birr/m2 C= Equipment Unit Cost 0.13 Birr/m2
Total of (1:02) 4.75 Total of (1:03)
Hourly Output: 1.25 Hourly output: _____________
Direct Cost of Work Item = A+B+C = 10.26 Birr/m2
Over head cost : 10% 1.03 "
Profit Cost: 15% 1.54 "
Total Unit Cost : 12.82 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-6-
A= Materials Unit Cost 3.335 Birr/m2 B= Manpower Unit Cost 5.59 Birr/m2 C= Equipment Unit Cost 0.19 Birr/m2
Total of (1:02) 4.75 Total of (1:03)
Hourly Output: 0.85 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 9.11 Birr/m2
Over head cost : 10% 0.91 "
Profit Cost: 15% 1.37 "
Total Unit Cost : 11.39 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-7-
A= Materials Unit Cost 16.80 Birr/ml.B= Manpower Unit Cost 2.76 Birr/ml. C= Equipment Unit Cost 0 Birr/ml.
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 19.56 Birr/ml.
Over head cost : 10% 1.96 "
Profit Cost: 15% 2.93 "
Total Unit Cost : 24.45 Birr/ml.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
A= Materials Unit Cost 41.05 Birr/m2 B= Manpower Unit Cost 12.89 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 53.94 Birr/m2
Ov Over head cost : 10% 5.39 Birr/m2
Prof Profit Cost: 15% 8.09 Birr/m2
Total Total Unit Cost : 67.42 Birr/m2
Remark _______________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
-4-
- 22 -
A= Materials Unit Cost 14.94 Birr/m B= Manpower Unit Cost 2.76 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output 7.73/2.8 = 2.75 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 17.70 Birr/m.
Over Head : 10% 1.77 Birr/m.
Profit Cost: 15% 2.66 Birr/m.
Total Unit Cost : 22.13 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-17 -
A= Materials Unit Cost 17.7 Birr/mB= Manpower Unit Cost 2.28 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/3.4 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 19.98 Birr/m.
Over head cost : 10% 2.00 Birr/m.
Profit Cost: 15% 3.00 Birr/m.
Total Unit Cost : 24.97 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 18 -
A= Materials Unit Cost 20.85 Birr/m B= Manpower Unit Cost 2.28 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/3.4 Hourly output: ________________
Direct Cost of Work Item = A+B+C = 23.13 Birr/m.
Over head cost : 10% 2.31 Birr/m.
Profit Cost: 15% 3.47 Birr/m.
Total Unit Cost : 28.91 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 19 -
A= Materials Unit Cost 25.58 birr/m. B= Manpower Unit Cost 2.28 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/3.4 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 27.85 Birr/m.
Over head cost : 10% 2.79 Birr/m.
Profit Cost: 15% 4.18 Birr/m.
Total Unit Cost : 34.81 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 20 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: ROOFING WORKS LABOUR HOURLY OUTPUT: 3.4 m/hr
WORK ITEM: (7.20) Down Pipe Development Size 60 cm. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 m RESULT: 40.06 Birr/m.
A= Materials Unit Cost 29.78 birr/m. B= Manpower Unit Cost 2.28 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/3.4 Hourly output: __________________
Direct Cost of Work Item = A+B+C = 32.05 Birr/m.
Over head cost : 10% 3.21 Birr/m.
Profit Cost: 15% 4.81 Birr/m.
Total Unit Cost : 40.06 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 12 -
A= Materials Unit Cost 17.7 birr/m. B= Manpower Unit Cost 2.98 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/2.6 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 20.68 Birr/m.
Over head cost : 10% 2.07 Birr/m.
Profit Cost: 15% 3.10 Birr/m.
Total Unit Cost : 25.84 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 13 -
A= Materials Unit Cost 20.85 birr/m. B= Manpower Unit Cost 2.98 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/2.6 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 23.83 Birr/m.
Over head cost : 10% 2.38 Birr/m.
Profit Cost: 15% 3.57 Birr/m.
Total Unit Cost 29.78 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 14 -
A= Materials Unit Cost 25.58 birr/m. B= Manpower Unit Cost 2.98 Birr/m C=Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/2.6 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 28.55 Birr/m.
Over head cost : 10% 2.86 Birr/m.
Profit Cost: 15% 4.28 Birr/m.
Total Unit Cost : 35.69 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 15 -
A= Materials Unit Cost 29.78 birr/m. B= Manpower Unit Cost 2.98 Birr/m C= Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 7.73/2.6 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 32.75 Birr/m.
Over head cost : 10% 3.28 Birr/m.
Profit Cost: 15% 4.91 Birr/m.
Total Unit Cost : 40.94 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 16 -
- 23 -
- 24 -
A= Materials Unit Cost 23.62 birr/m. B= Manpower Unit Cost 4.17 Birr/m C= Equipment Unit Cost 0 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: 10.88/7 Hourly output: ________________
Direct Cost of Work Item = A+B+C = 27.78 Birr/m.
Over head cost : 10% 2.78 Birr/m.
Profit Cost: 15% 4.17 Birr/m.
Total Unit Cost : 34.73 Birr/m.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
A= Materials Unit Cost 41.17 Birr/m2 B= Manpower Unit Cost 2.21 2.28 1.83 6.32 C= Equipment Unit Cost
-2-
A= Materials Unit Cost 45.15 Birr/m2 B= Manpower Unit Cost 2.21 2.28 1.83 6.32 C= Equipment Unit Cost
-3-
A= Materials Unit Cost 54.24 Birr/m2 B= Manpower Unit Cost 2.21 2.28 1.83 6.32 C= Equipment Unit Cost
-7-
A= Materials Unit Cost 3.19 Birr/ml.B= Manpower Unit Cost 1.10 Birr/ml. C= Equipment Unit Cost
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 4.29 Birr/ml.
Over head cost : 10% 0.43 "
Profit Cost: 15% 0.64 "
Total Unit Cost : 5.37 Birr/ml.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Materials Unit Cost 26.79 Birr/m2 B= Manpower Unit Cost 2.21 Birr/m2 C= Equipment Unit Cost 0
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 29.00 Birr/m2
Over head cost : 10% 2.90 "
Profit Cost: 15% 4.35 "
Total Unit Cost : 36.25 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
A= Materials Unit Cost 30.77 Birr/m2 B= Manpower Unit Cost 2.21 Birr/m2 C= Equipment Unit Cost 0
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 32.98 Birr/m2
Over head cost : 10% 3.30 "
Profit Cost: 15% 4.95 "
Total Unit Cost : 41.23 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-6-
A= Materials Unit Cost 39.86 Birr/m2 B= Manpower Unit Cost 2.21 Birr/m2 C= Equipment Unit Cost 0
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 42.07 Birr/m2
Over head cost : 10% 4.21 "
Profit Cost: 15% 6.31 "
Total Unit Cost : 52.59 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 8 -
-9-
A= Materials Unit Cost 7.82 Birr/ml.B= Manpower Unit Cost 1.56 Birr/ml. C= Equipment Unit Cost
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 9.37 Birr/ml.
Over head cost : 10% 0.94 "
Profit Cost: 15% 1.41 "
Total Unit Cost : 11.72 Birr/ml.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-10 -
A= Materials Unit Cost 41.97 Birr/m2 B= Manpower Unit Cost 4.82 Birr/m2 C= Equipment Unit Cost
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
41.97+4 Direct Cost of Work Item = A+B+C = 46.79 Birr/m2
Over head cost : 10% 4.68 "
Profit Cost: 15% 7.02 "
Total Unit Cost : 58.49 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-11 -
A= Materials Unit Cost 10.91 Birr/kg. B= Manpower Unit Cost 0.44 Birr/kg. C= Equipment Unit Cost 0.67 Birr/kg.
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
41.97+4 Direct Cost of Work Item = A+B+C = 12.03 Birr/kg.
Over head cost : 10% 1.20 "
Profit Cost: 15% 1.80 "
Total Unit Cost : 15.03 Birr/kg.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
A= Materials Unit Cost 73.78 Birr/m2 B= Manpower Unit Cost 3.38 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) 5.23 Total of (1:03)
Hourly Output: ________ 1.55 Hourly output: _________________
Direct Cost of Work Item = A+B+C = 77.16 Birr/m2
Over head cost : 10% 7.72 "
Profit Cost: 15% 11.57 "
Total Unit Cost : 96.45 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
-6-
-1-
A= Materials Unit Cost 11.825 Birr/m2 B= Manpower Unit Cost 8.98 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 20.80 Birr/m2
Over head cost : 10% 2.08 "
Profit Cost: 15% 3.12 "
Total Unit Cost : 26.01 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Materials Unit Cost 6.33 Birr/m2 B= Manpower Unit Cost 10.05 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 16.38 Birr/m2
Over head cost : 10% 1.64 "
Profit Cost: 15% 2.46 "
Total Unit Cost : 20.47 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
A= Materials Unit Cost 8.10 Birr/m2 B= Manpower Unit Cost 7.65 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 15.76 Birr/m2
Over head cost : 10% 1.58 "
Profit Cost: 15% 2.36 "
Total Unit Cost : 19.70 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Materials Unit Cost 4.02 Birr/m2 B= Manpower Unit Cost 2.26 Birr/m2 C= Equipment Unit Cost 1.78 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 8.06 Birr/m2
Over head cost : 10% 0.81 "
Profit Cost: 15% 1.21 "
Total Unit Cost : 10.07 Birr/m2
Remark 3.Coats of rendering ( 3+4 ) 29.77
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
A= Materials Unit Cost 0.37 Birr/m2 B= Manpower Unit Cost 8.31 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 8.69 Birr/m2
Over head cost : 10% 0.87 "
Profit Cost: 15% 1.30 "
Total Unit Cost : 10.86 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-6-
- 7-
A= Materials Unit Cost 0.72 Birr/m2 B= Manpower Unit Cost 2.83 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 3.55 Birr/m2
Over head cost : 10% 0.36 "
Profit Cost: 15% 0.53 "
Total Unit Cost : 4.44 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-8-
A= Materials Unit Cost 15.24 Birr/m2 B= Manpower Unit Cost 3.50 Birr/m2 C= Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 18.74 Birr/m2
Over head cost : 10% 1.87 "
Profit Cost: 15% 2.81 "
Total Unit Cost : 23.43 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-9-
- 10 -
- 11 -
- 12 -
- 13 -
- 14 -
- 15 -
- 16 -
- 17-
- 18 -
- 19 -
A= Materials Unit Cost 83.38 Birr/m2 B= Manpower Unit Cost 2.06 Birr/m2 C= Equipment Unit Cost 0.00 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 85.44 Birr/m2
Over head cost : 10% 8.54 "
Profit Cost: 15% 12.82 "
Total Unit Cost : 106.80 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 20 -
- 21 -
- 22 -
- 23 -
- 24 -
- 25 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 2.5 ml/hr
WORK ITEM: (11.25) 15 x 75mm. Marble skirting ( 1: 3 ). EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml RESULT : 32.66 Birr/ml
- 26 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 2.5 ml/hr
WORK ITEM: (11.26) 15 x 100 mm. Marble skirting ( 1: 3 ). EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ml RESULT : 43.16 Birr/ml
- 33 -
- 34 -
- 35 -
A= Materials Unit Cost 26.62 Birr/ml B= Manpower Unit Cost 5.53 Birr/ml C= Equipment Unit Cost 1.99 Birr/ml
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 34.14 Birr/ml
Over head cost : 10% 3.41 "
Profit Cost: 15% 5.12 "
Total Unit Cost : 42.68 Birr/ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 36 -
A= Materials Unit Cost 87.38 Birr/ml B= Manpower Unit Cost 5.53 Birr/ml C= Equipment Unit Cost 1.99 Birr/ml
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 94.90 Birr/ml
Over head cost : 10% 9.49 "
Profit Cost: 15% 14.24 "
Total Unit Cost : 118.63 Birr/ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 37 -
A= Materials Unit Cost 103.34 Birr/ml B= Manpower Unit Cost 5.53 Birr/ml C= Equipment Unit Cost 1.99 Birr/ml
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 110.86 Birr/ml
Over head cost : 10% 11.09 "
Profit Cost: 15% 16.63 "
Total Unit Cost : 138.58 Birr/ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 38 -
A= Materials Unit Cost 145.34 Birr/ml B= Manpower Unit Cost 5.53 Birr/ml C= Equipment Unit Cost 1.99 Birr/ml
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 152.86 Birr/ml
Over head cost : 10% 15.29 "
Profit Cost: 15% 22.93 "
Total Unit Cost : 191.08 Birr/ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 39 -
A= Materials Unit Cost 75.14 Birr/ml B= Manpower Unit Cost 5.53 Birr/ml C= Equipment Unit Cost 1.99 Birr/ml
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 82.66 Birr/ml
Over head cost : 10% 8.27 "
Profit Cost: 15% 12.40 "
Total Unit Cost : 103.33 Birr/ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 40 -
- 41 -
- 42 -
- 43 -
- 44 -
- 45 -
- 46 -
- 47 -
- 48 -
- 49 -
- 50 -
- 51-
- 52 -
A= Materials Unit Cost 62.93 Birr/ml B= Manpower Unit Cost 9.20 Birr/ml C= Equipment Unit Cost 3.32 Birr/ml
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 75.45 Birr/ml
Over head cost : 10% 7.55 "
Profit Cost: 15% 11.32 "
Total Unit Cost : 94.31 Birr/ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
- 53-
- 54 -
- 55 -
- 56 -
- 57-
- 58 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 0.98 m2 /hr
WORK ITEM: (11.58) 20x20 cm. Ceramic wall tile.(1:3). EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 m2 RESULT : 90.00 Birr/m2
- 59 -
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 0.98 m2 /hr
WORK ITEM: (11.59) Supply and fix mosaic tile. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 m2 RESULT : 181.80 Birr/m2
- 65 -
- 66 -
A= Materials Unit Cost 30.80 Birr/m2 B= Manpower Unit Cost 7.50 Birr/m2 C= Equipment Unit Cost 0.00 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 38.30 Birr/m2
Over head cost : 10% 3.83 "
Profit Cost: 15% 5.74 "
Total Unit Cost : 47.87 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-8-
-2-
-1-
A= Material unit cost 118.55 Birr/m3 B=Manpower Unit Cost 38.4 Birr/m3 C=Equipment Unit C 0 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A + B + C = 156.95 Birr/m3
Overhead Cost : 10% 15.70 "
Profit Cost: 15% 23.54 "
Total Unit Cost : 196.19 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
A= Material unit cost 338.219 Birr/pcs. B=Manpower Unit Cost 24.27 Birr/pcs. C=Equipment Unit C 52.00 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output Hourly output:
Direct Cost of work item = A + B + C = 414.49 Birr/pcs.
Overhead Cost : 10% 41.45 "
Profit Cost: 15% 62.17 "
Total Unit Cost : 518.11 Birr/pcs.
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-6-
A= Material unit cost 663.32 Birr/pcs. B=Manpower Unit Cost 24.27 Birr/pcs. C=Equipment Unit C 52.00 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output Hourly output:
Direct Cost of work item = A + B + C = 739.59 Birr/pcs.
Overhead Cost : 10% 73.96 "
Profit Cost: 15% 110.94 "
Total Unit Cost : 924.49 Birr/pcs.
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
A= Material unit cost 126.38 Birr/m2 B=Manpower Unit Cost 8.79 Birr/m2 C= Equipment Unit 22.73 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: _________________
Direct Cost of work item = A+B+C = 149.11 Birr/m2
Overhead Cost : 10% 14.91 "
Profit Cost: 15% 22.37 "
Total Unit Cost : 186.38 Birr/m2
Remark ______________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-7-
A= Material unit cost 399.2 Birr/pcs. B=Manpower Unit Cost 18.21 Birr/pcs. C=Equipment Unit C 26.00 Birr/pcs.
Total of (1:02) Total of (1:03)
Hourly Output Hourly output:
Direct Cost of work item = A + B + C = 443.41 Birr/pcs.
Overhead Cost : 10% 44.34 "
Profit Cost: 15% 66.51 "
Total Unit Cost : 554.26 Birr/pcs.
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-