Pick up the correct statement from the following:

A
The theory of formation of concrete is based on the phenomena of formation of voids
.
B.The bulking of sand is taken into account while volumetric proportioning of the aggregates
C.The dry sand and the sand completely flooded with water, have practically the same volume
D
The expansion and contraction joints are provided if concrete structures exceed 12 m in length
.
E. All the above

Answer: Option E

Initial setting time of cement for asbestos cement products should be not less than
A
30 minutes
.
B.50 minutes
C.75 minutes
D
90 minutes
.

Answer: Option D

Pick up the correct statement regarding low heat cement from the following:
A
It possesses less compressive strength
.
B.Its initial setting time is about one hour
C.Its final setting time is about 10 hours
D
Its mainly used for mass concrete work
.
E. All the above.

Answer: Option E

Name the type of cement from the following for canal linings :
A
sulphate resisting cement
.
B.rapid hardening cement
C.quick setting cement
D
pozzuolana cement.
.

Answer: Option A

If water required for 1 bag of cement is 30 litres, the water cement ratio is :
A
0.40
.
B.0.50
C.0.60
D
None of these.
.
Answer: Option C
The weight of 1 m3 of brick earth, is about
A
1200 kg
.
B.1500 kg
C.1800 kg
D
2000 kg.
.
Answer: Option C

Mastic asphalt is normally used for


A
sound insulation
.
B.water proofing
C.fire proofing
D
none to these.
.

Answer: Option B

Strength of cement concrete primarily depends upon


A
quality of water
.
B.quantity of aggregate
C.quantity of cement
D
water-cement ratio.
.

Answer: Option D

Soundness of cement is tested by


A
Vicat's apparatus
.
B.Le-chatelier apparatus
C.compressive strength testing apparatus
D
none of the these.
.

Answer: Option B

Slump test for concrete is carried out, to determine


A
strength
.
B.durability
C.workability
D
water content.
.
Answer: Option C

In case of Raymond pile


A
lengths vary from 6 m to 12 m
.
B.diameter of top of piles varies from 40 cm to 60 cm
C.diameter of pile at bottom varies from 20 cm to 28 cm
D
thickness of outer shell depends upon pile diameter
.
E. all the above.

Answer: Option E

The foundations are placed below ground level, to increase


A
strength
.
B.workability
C.stability of structure
D
all the above.
.

Answer: Option C

The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the
soft area is smaller than
A
the column spacing
.
B.one-third the column spacing
C.half the column spacing
D
three-fourth the column spacing
.
E. none of these.

Answer: Option B

The concrete slump recommended for beams and slabs ; is


A
25 to 50 mm
.
B.25 to 75 mm
C.30 to 125 mm
D
50 to 100 mm
.
E. none of these.

Answer: Option C

The entrained concrete is used in lining walls and roofs for making
A
heat insulated
.
B.sound insulated
C.neither (a) nor (b)
D
both (a) and (b).
.

Answer: Option D

For providing a raft foundation, the following activities are involved

1. ramming the foundation bed


2. excavation of the soil upto required depth
3. laying the reinforcement over the foundation bed
4. curing the cement concrete placed over reinforcement
5. pouring the cement concrete over the reinforcement.

The correct sequence is


A
1, 2, 3, 4, 5
.
B.5, 4, 3, 2, 1
C.2, 1, 3, 5, 4
D
3, 2, 5, 1, 4.
.

Answer: Option C

During percussion drilling


A ground water observations are hindered due to entry of the slurry in the soil below the bottom
. of the hole
B.caving or mixing of strata are caused in soft soils or cohesionless soils
C.the soil to a considerable depth below the bottom of the hole gets disturbed
D
all the above.
.

Answer: Option D

Raft foundation are generally preferred to when the area required for individual footing, is more
than
A
25% to total area
.
B.30% of total area
C.40% to total area
D
50% of total area.
.

Answer: Option D

Pick up the incorrect statement from the following:


A
The retaining wall should be structurally capable to resist the applied earth pressure
.
B.The section of the retaining wall should be so proportioned that it may not overturn by the
lateral pressure
C.The retaining wall should be safe against sliding
D The foundation of the retaining wall should not be stressed beyond safe bearing capacity ; due
. to its weight and the force resulting from the earth pressure
to drain off water from the earth retained, weep holes are provided near the top of the retaining
E.
wall.

Answer: Option E

The process of keeping concrete moist for a certain period after its finishing, is known as
A
finishing of concrete
.
B.curing of concrete
C.placing of concrete
D
compaction of concrete
.
E. none of these.

Answer: Option B

Raft foundations are used for :


A
providing increased area of foundation over poor bearing capacity of soil
.
B.spanning over small soft or loose pockets
C.counter acting the hydrostatic effect
D
all the above.
.

Answer: Option D

The foundation which consists of a thick reinforced cement slab covering whole area to support
heavy concentrated structural loads, is known as
A
combined footing
.
B.strap footing
C.raft footing
D
none of these
.

Answer: Option C

For a wall carrying heavy load on low bearing capacity soil,


A
lean concrete bed is provided
.
B.thick concrete bed is provided
C.reinforced concrete bed is provided
D
(a) and (c) of the above
.
E. (b) and (c) of the above.
Answer: Option D

The bearing capacity of a water logged soil, may be improved by


A
grouting
.
B.chemical action
C.drainage
D
compaction.
.

Answer: Option C

Two columns 50 cm x 50 cm and 60 cm x 60 cm carry 80 tonnes and 120 tonnes of loads


respectively. The centre to centre distance between columns is 5.00 metres. The permissible
bearing capacity of the soil is 20 t/m2. If the footing is not to project more than 25 cm beyond the
outside of the smaller column, pick up the correct design parameters of the footing from the
following:
A
distance of C.G. of the loads from the smaller column = 3.00 m
.
B.the length of the foundation slab = 7.00 m
C.area of footing slab = 11.00 m2
D
width of the footing = 1.57 m.
.
E. all the above.

Answer: Option E

The formWork including the props can be removed from beams, only after
A
3 day
.
B.7 days
C.14 days
D
21 days.
.

Answer: Option C

The concrete slump recommended for foundations, is


A
25 to 50 mm
.
B.30 to 125 mm
C.50 to 100 mm
D
75 to 125 mm
.
E. none of these.

Answer: Option C
The construction joints in buildings are provided after
A
10 m
.
B.15 m
C.20 m
D
40 m
.
E. 60 m.

Answer: Option D

Pick up the correct statements from the following :


A
cracks appear on the plastered surface in the form of hair cracks
.
B.in brick work, the efflorescence is removed by applying a solution of zinc sulphate and water
C.excessive thermal variations in the backing or plaster causes the plaster to fall
D
all the above.
.

Answer: Option D

Pick up the correct statement from the following:


A
Plain cement concrete is equally strong in compression as well as in tension
.
B.Slump test is performed to check concrete strength
C.Curing of concrete is done for proper compaction of cement
D Fineness modulus is the index number expressing the relative sizes of both coarse and fine
. aggregates
E. Concrete is a mixture of binding material, coarse aggregate and water.

Answer: Option D

Pick up the correct statement from the following :


A
Isolated footing is provided under column to transfer the load safely to soil bed
.
B.column footings may have steps or projections in the concrete base
C.heavily loaded column base must be provided steel reinforcement in both directions
D
the concrete offset should be at least 15 cm on all sides
.
E. all the above.

Answer: Option E

If h is the difference in level between end points separated by l, then the slope correction is

. The second term may be neglected if the value of h in a 20 m distance is less than
A
. m
B.1 m
C.2 m
D
3m
.

Answer: Option D

The accuracy of measurement in chain surveying, does not depend upon


A
length of the offset
.
B.scale of the plotting
C.importance of the features
D
general layout of the chain lines.
.

Answer: Option D

Offsets are measured with an accuracy of 1 in 40. If the point on the paper from both sources of
error (due to angular and measurement errors) is not to exceed 0.05 cm on a scale of 1 cm = 20
m, the maximum length of offset should be limited to
A
14.14
.
B.28.28 m
C.200 m
D
none of these.
.

Answer: Option B

Ranging in chain survey means


A
looking at an isolated point not on the line
.
B.establishing an intermediate point on the line
C.determining the distance between end points
D
determining the offset distance
.
E. none of these

Answer: Option B

The operation of resection involves the following steps

1. rough orientation of the plane table


2. the three lines form a triangle of error
3. drawing lines back through the three control points
4. select a point in the triangle of error such that each ray is equally rotated either clockwise
or anti clockwise
5. the points obtained by three rays is the correct location.
The correct sequence is

A
1, 3, 2, 4, 5
.
B.1, 2, 3, 4, 5
C.1, 4, 3, 2, 5
D
1, 3, 2, 4, 5
.

Answer: Option A

If the length of a transition curve to be introduced between a straight and a circular curve of
radius 500 m is 90 m, the maximum perpendicular offset for the transition curve, is
A
0.70 m
.
B.1.70 m
C.2.70 m
D
3.70 m
.
E. 4.70 m

Answer: Option C

For quality control of Portland cement, the test essentially done is


A
setting time
.
B.soundness
C.tensile strength
D
consistency
.
E. all the above.

Answer: Option E

If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the
percentage of water is,
A
20% B.25%
.
C.30% D.35%
E. 40%

Answer: Option B

Hydration of cement is due to chemical action of water with


A
Tricalcium silicate and dicalcium silicate
.
B.Dicalcium silicate and tricalcium aluminate
C.Tricalcium aluminate and tricalcium alumino ferrite
D
All the above.
.
Answer: Option D

Curing
A
reduces the shrinkage of concrete
.
B.preserves the properties of concrete
C.prevents the loss of water by evaporation
D
all of the above.
.

Answer: Option D

Curing a concrete for long period ensures better


A
volume stability
.
B.strength
C.water resistance
D
water tightness and durability
.
E. all the above.

Answer: Option E

Pick up the correct statement from the following:


A
Insufficient quantity of water makes the concrete mix harsh
.
B.Insufficient quantity of water makes the concrete unworkable
C.Excess quantity of water makes the concrete segregated
D
Excess quantity of water causes bleeding in concrete
.
E. All the above

Answer: Option E

Workability of concrete is measured by


A
Vicat apparatus test
.
B.Slump test
C.Minimum void method
D
Talbot Richard test.
.

Answer: Option B

Shrinkage in concrete can be reduced by using


A
low water cement ratio
.
B.less cement in the concrete
C.proper concrete mix
D
presaturated aggregates
.
E. all the above.

Answer: Option E

A construction joint is provided where


A
bending moment is small
.
B.shear force is small
C.the member is supported by other member
D
all the above.
.

Answer: Option D

Pick up the correct statement from the following:


A According to the petrological characteristics, concrete aggregates are classified as heavy
. weight, normal weight and light weight
According to the shape of the particles, concrete aggregates are classified as rounded irregular,
B.
angular and flaky
According to the surface texture of the particles, the concrete aggregates are classified as
C.
glassy, smooth, granular, rough, crystalline, honey combed and porous
D
All the above.
.

Answer: Option D

Pick up the incorrect statement from the following:


A
The degree of grinding of cement, is called fineness
.
B.The process of changing cement paste into hard mass, is known as setting of cement
The phenomenon by virtue of which cement does not allow transmission of sound, is known
C.
as soundness of cement
D The heat generated during chemical reaction of cement with water, is known as heat of
. hydration
E. None of these.

Answer: Option C

Permissible compressive strength of M 150 concrete grade is


A
100 kg/cm2
.
B.150 kg/cm2
C.200 kg/cm2
D
250 kg/cm2
.
E. 300 kg/cm2

Answer: Option C
Slump test of concrete is a measure ofits
A
consistency
.
B.compressive strength
C.tensile strength
D
impact value.
.

Answer: Option A

Water cement ratio is


A
volume of water to that of cement
.
B.weight of water to that of cement
C.weight of concrete to that of water
D
volume of concrete to that of water
.
E. both (a) and (b) of the above.

Answer: Option E

Separation of water or water sand cement from a freshly concrete, is known


A
bleeding
.
B.creeping
C.segregation
D
flooding
.
E. none of these.

Answer: Option A

According to Water-Cement Ratio Law, the strength of workable plastic concrete


A
depends upon the amount of water used in the mix
.
B.does not depend upon the quality of cement mixed with aggregates
C.does not depend upon the quanity of cement mixed with aggregates
D
all the above
.

Answer: Option D

High temperature
A
increases the strength of concrete
.
B.decreases the strength of concrete
C.has no effect on the strength of concrete
D
none of these.
.

Answer: Option B
Allowable shear strength of concrete, depends upon
A
shear strength
.
B.tensile strength
C.compressive strength
D
none of these.
.

Answer: Option A

Workability of concrete mix with low water cement ratio is determined by


A
tensile strength test
.
B.slump test
C.compaction factor test
D
flexural strength test
.
E. none of these

Answer: Option C

While designing an air entrained concrete


A
water cement ratio is reduced
.
B.proportion of aggregates is reduced
C.an allowance for the entrained air is made
D
strength of the concrete, is reduced
.
E. all the above

Answer: Option E

Concrete gains strength due to


A
chemical reaction of cement with sand and coarse aggregates
.
B.evaporation of water from concrete
C.hydration of cement
D
All the above.
.

Answer: Option C

Expansion joints are provided if the length of concrete structures exceeds


A
10 m
.
B.15 m
C.15 m
D
35 m
.
E. 45 m
Answer: Option E

Workability improved by adding


A
fly ash
.
B.hydrated lime
C.calcium chloride
D
bentonite
.
E. all the above.

Answer: Option E

If the slump of a concrete mix is 60 mm, its workability is


A
very low
.
B.low
C.medium
D
high
.
E. none of these.

Answer: Option C

Pick up the correct statement from the following:


A
Construction joints in columns are provided a few cm below the junction of beam
.
B.Construction joints in columns are provided at the bottom haunching
C.Construction joints in beams and slabs are provided within middel third
D
Constructionjoints are generally provided in positions subjected to least shear force
.
E. All the above.

Answer: Option E

The shortest distance between two places measured along the surface of the earth, is
A
length of the equator between their longitudes
.
B.length of the parallel between their longitudes
C.length of the arc of the great circle passing through them
D
none of these.
.

Answer: Option C

In the cantilever truss as shown in below figure, the horizontal component of the reaction at A, is
A
30 tonnes
.
B.60 tonnes
C.90 tonnes
D
120 tonnes
.
E. 150 tonnes.

Answer: Option A

For a simply supported beam with a central load, the bending moment is
A
least at the centre
.
B.least at the supports
C.maximum at the supports
D
maximum at the centre.
.

Answer: Option D

A simply supported beam carrying a uniformly distributed load over its whole span, is propped at
the centre of the span so that the beam is held to the level of the end supports. The reaction of the
prop will be
A
half the distributed load
.
B.3/8th the distributed load
C.5/8th the distributed load
D
distributed load.
.
E. none of these.

Answer: Option C

The range within which a load can be applied on a rectangular column, to avoid any tensile
stress, is
A
one-half of the base
.
B.one-fifth of the base
C.one-fourth of the base
D
one-fifth of the base
.
E. one sixth of the base on either side of centroid.
Answer: Option B

The shear stress at any section of a shaft is maximum


A
at the centre of the section
.
B.at a distance r/2 from the centre
C.at the top of the surface
D
at a distance 3/4 r from the centre
.
E. none of these.

Answer: Option C

The region of the cross-section of a column in which compressive load may be applied without
producing any tensile stress, is known as the core of the cross-section. In circular columns the
radius of the core, is
A
one-half of the radius
.
B.one-third of the radius
C.one-quarter of the radius
D
one-fifth of the radius
.
E. one-sixth of the radius.

Answer: Option C

The maximum bending moment due to a moving load on a simply supported beam, occurs
A
at the mid span
.
B.at the supports
C.under the load
D
anywhere on the beam
.
E. none of these.

Answer: Option C

A simply supported beam of span L carries a uniformly distributed load W. The maximum
bending moment M is
A
.
B.

C.
D
.
E.
Answer: Option C

A cantilever beam rectangular in cross-section is subjected to an isolated load at its free end. If
the width of the beam is doubled, the deflection of the free end will be changed in the ratio of
A
8 B.1/8
.
C.1/2 D.2
E. 3

Answer: Option C

When equal and opposite forces applied to a body, tend to elongate it, the stress so produced, is
called
A
shear stress
.
B.compressive stress
C.tensile stress
D
transverse stress
.

Answer: Option C

Stress in a beam due to simple bending, is


A
directly proportional
.
B.inversely proportional
C.curvilinearly related
D
none of these.
.

Answer: Option A

The bending moment is maximum on a section where shearing force


A
is maximum
.
B.is minimum
C.is equal
D
changes sign.
.

Answer: Option D

A district road with a bituminous pavement has a horizontal curve of 1000 m for a design speed
of 75 km ph. The super-elevation is
A
1 in 40
.
B.1 in 50
C.1 in 60
D
1 in 70
.
E. none of these.

Answer: Option A

The total length of a valley formed by two gradients - 3% and + 2% curve between the two
tangent points to provide a rate of change of centrifugal acceleration 0.6 m/sec 2, for a design
speed 100 km ph, is
A
16.0 m
.
B.42.3 m
C.84.6 m
D
none of these
.

Answer: Option A

The advantage of providing superelevation on roads, is


A
higher speed of vehicles
.
B.increased volume of traffic
C.reduced maintenance cost of the roads
D
draining off rain water quickly
.
E. all the above.

Answer: Option E

For a vehicle moving with a speed of 80 km per hour, the brake reaction time, in ordinary cases,
is
A
1 sec
.
B.1.5 sec
C.2.0 sec
D
2.5 sec
.
E. 3.0 sec

Answer: Option D

Couple of MMUP exam questions (21/5/2014) (exam had 25 in all)

1) What of the following is not considered an aspect of Project management?


a. Innovation
b. Speed
c. Repeatability
d. Flexibility
e. Accountability

2) An aquifer is found to have a velocity of 1m/hr at an hydraulic gradient of 0.004. If a sample


shows the aquifer has a porosity of 15% what is the hourly flow rate of the aquifer
a. 400
b. 0.0006
c. 0.0267
d. 1
e. 360

3) Kilowatt hour is a measure of


a. Electrical power
b. Electrical energy
c. Electrical voltage
d. Electrical amperage

4) Something about what an engineer is, obvious answer

5) What does QSAS stand for


a. Gives 4 answers but correct is Qatar Sustainability Assessment System

6) What is the definition of sustainability – cant remember other possible answers but the correct
did mention using recycling, renewable energy etc so was obvious answer.

7) Some quotes about concrete and need to decide which is correct


a. First was something about concrete crushing strength solely reliant on water / cement
ratio
b. Second was something like ‘vibration has no effect on strength in a high water content
concrete mix
c. Third was something like ‘workability is compromised if an uneven aggregate mix is
used’

8) There was a road curve questions that involved being given speed and length curve, needed to
find superelevation – I didn’t know this one so can’t remember it.

9) If a road has a speed limit of 60mph and a traffic rate of 16 vehicles per lane per minute, how
many cars per lane pass in an hour
a. 300
b. 960
c. 1200
d. 160

10) What is the AASHT0 recommended perception and stopping time


a. 10 seconds
b. 3.5 seconds
c. 2.5 seconds
d. 0.5 seconds

11) Advantages of plywood


a. Tensile strength same in both directions
b. Tensile strength strong in longitudinal direction
c. Tensile strength strong in transverse direction
d. Something else

12) Are the following sentences correct


a. In equilibrium for plastic analysis the sum of all forces = 0 and sum of all moments = 0
b. Can’t remember exactly the second one but something about at breaking point all joints
act as mechanical something?

13) If a concrete column is loaded under axial bending stress the moment will?
a. Increase
b. Decrease
c. Remain the same
d. Increase then decrease

There was a question on using sulphate resistant concrete in soils, another on slump test, a third on
admixtures and what they can do to concrete strength, moisture content etc.. Can’t remember them
exactly but they were not too hard to answer if can remember sulphate resistant concrete is good for
aggressive soils, slump measures workability and admixtures can aid in strength at different MCs

Also question on SPT testing for soils just need to know <4 is very loose, 4-10 – loose, 10-30 compact,
30-50 dense and >50 very dense,

Then the best question I had was

14) Highway Design?


a. Speed
b. Traffic volume
c. Classification of road
d. Line of Sight
(no idea if question was what is most important.., what do you start with.., what is not
critical.., asked guy supervising about it and he said just to ignore question, he noted
the question number down and I think I got a free correct answer.)

I think a couple of others involved raft foundations and concrete cracking due to low MC, then another
roads one on definition of something I can’t remember, (but answer was actually kind of given in
question). Sorry that’s all I remember.
1- What is the maximum value of PHF ?
 1
 0.35
 0
 0.25
2- What is next step after take a project ?
3- Something about “fast track project”
4- Something about “resource levelling”
5- What is the factor not to be taken in consideration in mix design?
 Degree of control of concrete
 Strength of concrete
 Time of first set of cement
 Workability
6- What is the formula of nominal moment in concrete ?
 Mn = Fs.As(d –c/2 )
 Mn = Fs.As(d – a)
 Mn = 0.85f’c.ab(d – a/2)
 Mn = 0.85f’c.ab(d – a/2) + Fs.As(d – a/2)
7- Something about flow in pipes, 2 pipes A and B joined together into pipe C
Flow A given
Flow B given
Area C given
Calculate velocity of water in C.
8- Calculate the length of arc, radius 250m, first tangent 25˚30’, second tangent 30˚25’
9- car going on a speed of 60 mi/H on a curve highway. After passing midpoint the driver saw an
accident in front of him. The distance that will be passed from the moment the driver saw the
accident until he hit the brakes equal to …
10- In AASHTO what is the perception and reaction time for calculating the sight distance?
11- What is AASHTO ?
American Association of Standard Highway and Transportation Organis. (maybe :p)
12- What to take in consideration to safe design for long pile in a drilled rock soil
 Rock bearing capacity
 Strength of concrete
 Buckling of pile
 …..
13- What is the factor effecting the hardness of water ?
14- How to calculate T-beam … (flanged section)
15- Who make testing of product in the factory
 Testing engineer
 Research engineer
 Product engineer
 ……
16-
1- What is the Max Dry density (gm/cm3) and optimized water content
for the following chart?
2- Calculate the fill/excavation (CY)
3- What is the advantage of using concordant cable in pre-stressed
concrete?
4- What are RC columns execution sequences?
5- Calculate the displacement for truss.
6- What is the slope at section ..(.. EI=constant
7- Normal dry-density of RC concrete mix.
8- What is ABET?
9- Why in two way slab, lifting of corner slab happens from ..?
10- What should be issued first when project starts?
11- Activity is followed by two activates what do you call this
activity?
12- 10#@10/m to change to 12# how much the new space?
13- What is the last of stage of sewage treatment plant?
14- The road cross section, using to calculate …
15- The expression is used in roads engineering followed capacity.
16- When design RC section, whether the concrete at tension side
will be neglected or considered?
17- Is any relation between rock density and its content (more or
less)?
18- At project time frame what is type of cost estimation being
used?
19- Air-Entrained Concrete is used to ( Freeze-Thaw Resistance)
20- The station is 00,.000 with elevation of 178.00 what is the filling
required
21- What is the nearest to 100 Yard (1:100, 1: 1000, 1:1500)
22- How many compaction tests are required in 1000m2?
1. What does QCS stand for?
2. What is hydration in concrete?
3. Calculate joint deflection when membrane temperature increases.
4. What does RQD 100% mean?
5. Calculate super elevation in roads.
6. Calculate stopping distance when moving @ speed of 60mi./hr (distance in
feet)
7. What is the function of admixtures in concrete?
8. Project scope definition.
9. What is the last stage in WTP process?
10. What do status reports represent?
11. What is the use of dummy activity in diagrams?
12. Calculate the horizontal displacement for a truss.
13. What is the effect of air within poured concrete?
14. Definition of grade (highways).
15. What is the weight of concrete?
16. What is the yield strength of steel?
17. What is the strength of concrete?
18. What is the maximum allowable stress redistribution in RCC beams (%)?
19. How many compaction tests are required in 1000m2?
20. Tensile strength in wood (direction wrt grains).
21. Ethical- should report any wrong doing.
22. Calculate deflection @ a joint.
23. What is the slope of the cost time curve?
24. Calculate future investment.
25. Where is maximum bending stress located/ how is it distributed when
placing a load on the beam’s C-S (linear/ Parabolic/uniform/ @ top &
bottom)
1- What is the first thing you do after you take a project:
Arrange for meeting
Assign staff
Prepare WBS
2- What is WBS used for:
Only for complex project
Used for planning
Top to down list of activities
Down to top items for project
3- Concrete cubes usually crushed at
2 days
8 days
28 days
30 days
4- Steel yield strength usually used at site in MPA:
400
200
100
300
5- What governs in intersection design after capacity:
Speed
Safety
Cost
Volume
6- Level of surface for Road means:
Quality of road
Quantitative of vehicles
None of above
7- Optimum moisture content and max. dry density is the chart is :
Number in chart %, and KN/M3
Different number in chart % and KN /M3
Number in chart % and gm/M3
Different number in chart and gm/M3
This question requires you to read the optimum moisture content and the max dry
density from given chart and the to know the units
8- Timber used in frames for building has moisture content of:
1- 1 to 4 %
2- 8 to 12 %
3- 14 to 25 %
4- Above 25 %
9- Ethics means :
Good manner and behavior

Good practice in engineering which depends in the environment


Other statements I can’t remember
10- Inter-discipline for ENGINEERING best fit the following:
All engineers should specialized on all fields
All engineers should study all engineer’s aspects
Engineers should cooperate with each other
11- Calculate the deflection at point A

9.75P/EA

21P/EA

42P/EA

12- Method …………. Beam

Bernoulli- Foiler

Filler and some other names which I don’t recall

13- Activity can be described as :


Arrow
Line
Node
All
14- What is critical path
Shortest path
Longest path
15- What is Poisson ratio
?
?
16- Bleeding can be controlled by :
Adding cement
More vibrating concrete
Adding aggregate
Adding fresh concrete
17- Increasing Concrete strength is affected by:

Increasing Water cement ratio in high workability concrete

Vibrating concrete in high water cement ratio

Bad aggregate sieve and gradation.

18- Level for surface road means:


Quality of road
Quantity of traffic
Others which I can’t remember.
19- What is shear span:
Moment is zero
Shear is zero
Moment is maximum

1. Perfect sampling for Rock Soil


Use: - Double Sleeve
Single Sleeve
Main Sleeve
2. Consideration of Long Pile in Rock
- Rock
- Buckling
- Strength of concrete
3. Over Flow rate 35m3/w/day
Tank 2.5 x 4 x 16 m
- Flow Rate
2240 m3/day
800m3/day
350m3/day
0.22m3/day
4. Two Way Slab to consider
- Shear at edges
- Sleep in middle
- - Compression in Middle

10 20
5.
B
Calculation Movement at B
6. C EA given

A B
Calculate the Horizontal force of B
7. calculate the interest rate. how many year to return your money ?
8. At Traffic Junction and Intersection other than the volume of traffic you look
Safety
Cost
Speed
9. In ''T'' the section beam Design as
Simple Support
Rectangular
10. Grade in Streets
In Angle
Percentage ………….?
11. What is the stress in membrane
- Mass Volume
- Force + Mass weight

12. What is the last additional in Cement Factory ?


- Silica
- Aluminum
- Calcium Sulphate
- None of above
13. Meaning of QSAS
- Qatar Sustainability Assessment System
14. Compression Test required in 1000m2?
- 1
- 2
- 3
- 10
15. Compaction of Non Coefficient Soil every
- 100min
- 300 min
- 500 min
- 1000min
16. Activities in Program designed by
- Lines
- notes
- Points
- All of the above
17. In Traffic Volume Measurement
- from 1 to 5
- Special
- no. of cars
- all of above
18. FTh ..What is FTh ?
- 0.25
- 0.35
- 1
19. Quality calculate
- Before
- After
- During
- all of above
20. Bricks
a. Motor is an effect to strength of Brick wall.
b. Lime stone is an effect of Strength of Bricks.
c. Motor is considered the main effect of strength of Brick wall.
d. All of the above
21. Sheet force + Fiber

REVIEW ( 5-Jun- 13 )
22.
1. What is the SPT for dense sand?
Options: 0-20 / 20-40 / > 100.
JUM: 20-40.

2. How to calculate a continuous T beam ?


Supported at various points
Simply supported
Flanged section
Rectangular section.
JUM : flanged section.

3. What is Degree of curve? JUM : 100 feet chord angle .

4. For how cross sections are used ? JUM : for cut and fill quantities.

5. What is the perception and reaction time for calculating the sight distance?
1 second
2.5 s
3.5 s
None of the above .
JUM : 1 second.

6. If a work, if the property decides to make a change in scope, what is the


procedure to do ?
Change order
Modification
....
JUM : Change order .

7. For why steel is preferred as reinforcement in concrete?


Because it is inexpensive and resistant
Because it is easily accessible
Because it adheres well to concrete
Because it has the same coefficient of expansion of the concrete.
JUM : because it adheres well to concrete.

8. What is concrete density ? JUM : 2.4 .

9. Right or false? What factors influence the compressive strength of concrete?


Resistance is inversely proportional to the water-cement ratio
The resistance is proportional to the cement content
Cracks on the surface due to excessive water content
All others are true.
JUM : all others are true.

10. On relation to the use of air-entraining agents in concrete, which of the


following statements are true:
Improve the workability
Improving long-term durability
Makes a less dense mixture
...
JUM : all the above are true.

11.Rellenar the gap : The immediate ______________ are Necessary to Develop


the Following tasks in a breaking down of a project .
Critical activities
predecessor activities
successor activities
Burst activities
None of the above is correct.
JUM : Predecessor activities.

12. What of the following statements are false for a Work package:
Allocating resources must
It should designate a Work manager.
It should set deadlines "definitive "
None of the above is false .
JUM : You should set a timetable definitive .

13.On Work breakdown structure relative to project which of the following


statements are false ? .
Breaks up the project in a " top-down " .
It breaks down the draft as "down -top "
Used to handle large projects.
JUM : used to handle large projects.

14. What is a logical sequence of activities?


1,2,3,4
3,2,4,1
2,4,3,1 .
JUM : 1,2,3,4 .

15. What is the logical sequence of a concrete ?


JUM: formwork (framework) > pouring ( pouring ) > curing ( curing ) > stripping .

16. Problem influence lines. Vocabulary: shear stress .

17. Problem a lattice.

18. Problem: "If in a plane I measure 7 ¼ " "(inches ) and is 1/62.500 scale , what is
the distance between the two points in miles ? " JUM : 7, 25 miles.

19. Lacing system. Doubt: Is an articulated structure?.

20. In a beam which points of stress due to the time and bearing is equal to 0 ?
In the neutral light center .
In the top center fiber light.
At lower fiber support.
In the neutral support .
JUM : the neutral center and the neutral light support .

21. Problem of a cross section of concrete. What is the moment of resistance?


23.
1) Find displacement of free Joint in framed structure with horizontal force for a provided fig (solve
problem) - for given E, A & I Values
2) Nondestructive test of concrete
3) Compaction equipment in clay and sandy soil
4) Radius calculation in super elevation using V,e & f (Solve problem)
5) Tests of concrete & soil (2 nos of questions )
6) Horizontal curve design from deflection angle
7) Sewerage treatment plant outflow calculation (solve problem)
8) Problem of Flows using formula AV=A1 V1 +A2 V2 (solve problem)
9) Project network and critical path calculation (solve problem)
10) SPT test related questions
11) ABET certification coverage
12) Which engineering branch deals with laying of natural gas lane in Oil& construction
13) SPT number of dense sand
14) CPM Network diagram merging activity
15) Total internal angles of hexagon
16) Type of force in hanging rod of Fan
17) Reasons of using Doubly reinforced beams
18) Unit weight of concrete
19) Factor effecting slump of concrete
20) Shear force and bending moments (problem)
21) Which type of settlement is dangerous for framed structures
22) Poisson’s ratio
23) Liquid limit,PL,PI (problem)
24) Flakiness tests in aggregate

You might also like