Project Implementation Manual
Project Implementation Manual
HUNGARY-SERBIA PROGRAMME
Version: 1.0
INTRODUCTION ................................................................................................................ 3
1 INSTITUTIONAL SETUP OF THE PROGRAMME ............................................................. 8
2 RESPONSIBILITIES AND TASKS OF THE LEAD PARTNER ................................................ 9
2.1 The lead partner principle and cooperation among partners within the partnership ....... 9
2.1.1 Partnership Agreement ......................................................................................................... 10
3 CONFLICT OF INTEREST ............................................................................................. 11
4 CONCLUDING THE SUBSIDY CONTRACT FOR EU CONTRIBUTION ............................... 11
5 EU ADVANCE PAYMENTS .......................................................................................... 12
6 MONITORING SYSTEM FOR PROJECT IMPLEMENTATION - INTERREG + (I+)................ 12
6.1 Access to the monitoring system....................................................................................... 13
7 MODIFICATION OF THE SUBSIDY CONTRACT, OTHER PROJECT CHANGES AND
ADMINISTRATIVE CHANGE .............................................................................................. 14
7.1 Modification of the Subsidy Contract (Addendum to SC) ................................................. 15
7.2 Other project changes (OPC) ............................................................................................. 18
7.3 Administrative changes ..................................................................................................... 18
8 MODIFICATION PROCESS ALGORITHM ...................................................................... 19
9 MONITORING VISITS ................................................................................................ 21
10 REPORTING AND REIMBURSEMENT PROCESS OF THE EU FUNDS ............................... 22
11 REPORTING DEADLINES ............................................................................................ 22
12 PROJECT REPORT...................................................................................................... 22
12.1 Reporting about horizontal and „Do No Significant Harm” principles ........................ 23
12.2 Preparation and content of the Project Report, procedures ....................................... 24
12.3 Completion ................................................................................................................... 27
12.4 Revalidation .................................................................................................................. 27
12.5 Rejection....................................................................................................................... 27
12.6 Preparation and content of the Application for Reimbursement................................ 28
12.7 Procedure of reimbursement of EU funding ................................................................ 28
12.8 Final Project Report ...................................................................................................... 28
13 ELIGIBILITY ............................................................................................................... 29
14 PROCUREMENT RULES ............................................................................................. 29
15 SUSPICION OF IRREGULARITY AND IRREGULARITY PROCESS ..................................... 29
16 PROJECT CLOSURE .................................................................................................... 31
16.1 Retention of project documents, audit trail and adequate archive ............................ 31
1
17 USE OF RESULTS AFTER PROJECT CLOSURE ............................................................... 32
18 PROJECT FOLLOW-UP REPORT .................................................................................. 32
19 GDPR ....................................................................................................................... 33
20 LIST OF ANNEXES ..................................................................................................... 33
2
INTRODUCTION
The Project Implementation Manual of the Interreg VI-A IPA Hungary-Serbia Programme
(the Programme) was developed on programme level and based on the followings:
• Regulation (EU) 2021/1058 of the European Parliament and of the Council of 24 June
2021 on the European Regional Development Fund and on the Cohesion Fund (ERDF
Regulation);
• Regulation (EU, Euratom) 2018/1046 of the European Parliament and of the Council
of 18 July 2018 on the financial rules applicable to the general budget of the Union,
amending Regulations (EU) 2013/1296, (EU) 2013/1301, (EU) 2013/1303, (EU)
2013/1304, (EU) 2013/1309, (EU) 2013/1313, (EU) 2014/223, (EU) 2014/283, and
Decision 2014/541 and repealing Regulation (EU, Euratom) 2012/966 (Financial
Regulation);
• Regulation (EU) 2021/1060 (CPR) of the European Parliament and of the Council of
24 June 2021 laying down common provisions on the European Regional
Development Fund Plus, the Cohesion Fund, the Just Transition Fund and the
European Maritime, Fisheries and Aquaculture Fund and financial rules for those and
for the Asylum, Migration and Integration Fund, the Internal Security Fund and the
Instrument for Financial Support for Border Management and Visa Policy;
• Regulation (EU) 2021/1059 of the European Parliament and of the Council of 24 June
2021 on specific provisions for the European territorial cooperation goal (Interreg)
supported by the European Regional Development Fund and external financing
instruments;
• The Application package (including the Guidelines for Applicants and Eligibility of
Expenditures) of the 1st call for proposals (1st CfP) of the Programme under which the
Project has been selected and awarded the subsidy (approved by MC Decision
2/2023 on 22 March 2023);
3
The Project Implementation Manual is intended to guide lead partners (LP) and project
partners in the implementation of the projects, more specifically, on questions related to
administrative and financial management, monitoring, reporting and control procedures,
and other programme related requirements.
Should there be any amendments of the manual due to legislative changes or other
requirements which influence implementation of already approved projects, they will be
available on the official website of the Interreg VI-A IPA Hungary-Serbia Programme:
www.hungary-serbia.eu.
For specific problems related to your project please contact the JS, or JSA for advice. You can
find the contact details of individual JS and JSA programme managers on the above
mentioned website.
Abbreviations
AA audit authority
AF Application Form
AfR Application for Reimbursement
BL budget line
CA certifying authority
IP Interreg programme – the programme document
DOVE Declaration on Verification of Expenditures
ERDF European Regional Development Fund
EC European Commission
EU European Union
CB Control Body
FPR Final Project Report
IPA Instrument for Pre‐accession Assistance
JS joint secretariat
JSA joint secretariat antenna
LP lead partner
MA managing authority
MC monitoring committee
I+ Interreg + monitoring system
NA national authority
OLAF European Anti‐Fraud Office (from French: Office européen de lutte antifraude)
PA Partnership Agreement
PP project partner
PR Project Report
PPR Project Partner Report
PF Project Form
SC Subsidy Contract
4
Glossary of terms
audit
The term “audit” is used for the second level audit performed by the audit authority (Group
of Auditors) or by external auditors on behalf of the audit authority in compliance with Art.
77 of CPR (EU) Regulation 2021/1060. Second level audit covers the verification, on a sample
basis, of already verified and approved project expenditure.
budget heading
Main lines from the project budget: Staff costs, Office and administration, Travel and
accommodation, External expertise and services, Equipment, Infrastructure and works.
cross-border cooperation
The collaboration between adjacent areas across borders. The main aim is to reduce the
negative effects of borders as administrative, legal and physical barriers, tackle common
problems, and exploit untapped potential. Through joint management of programmes and
projects, mutual trust and understanding are strengthened, and the cooperation process is
enhanced.
eligible area
The Hungarian and Serbian counties and regions located in the border area, as mentioned in
the Interreg VI-A IPA Hungary-Serbia Programme approved by the European Commission.
flat rate
A simplified cost option. Specific categories of eligible costs which are clearly identified in
advance are calculated by applying a percentage fixed ex-ante to one or several other
categories of eligible costs. Flat rates involve approximations of costs and are defined based
on fair, equitable and verifiable calculation methods.
lead partner
Project participant taking the overall responsibility for the development and the
implementation of a project. Each lead partner shall conclude the Partnership Agreement
(with its project partners) and the Subsidy Contract (with the MA), ensures a sound
crossborder project management as well as the project implementation, and transfers the
due EU contributions to the project partners.
legal representative
A person authorised to sign binding documents (e.g., PA, SC) on behalf of an organisation.
5
national legislation
The legislation of the state on whose territory the partner is located.
own contribution
Amount with which the relevant partners have to contribute to the total eligible amount of
their own project budget. It depends on the national legislation whether a partner has to
provide own contribution or not.
project outcomes
Expected project results that are achieved by completion of group of activities and measured
by indicators.
project partner
Any applicant whose application has been approved for financing.
real costs
It is the form of reimbursement where the partner must document that expenditure has
been incurred and paid out.
EU contribution
The EU part of the eligible expenditure of a project that is financed by the European Union.
6
indicators
Indicators measure whether the project achieved the planned outcomes. They are used to
track progress, reflect change or assess project performance. There are two types of
indicators: Output (to measure whether the planned activities took place and monitor the
quality of conducted activities) and Result (to provide information on the results and impact
of the activities in the project).
irregularity
Any breach of applicable law, resulting from an act or omission by an economic operator,
which has, or would have, the effect of prejudicing the budget of the Union by charging
unjustified expenditure to that budget; according to Art. 2 (31) of Regulation (EU)
2021/1060.
monitoring system
INTERREG+ monitoring system is an online system covering the full project life cycle within
one monitoring tool containing all records of a project. Lead applicants must create an
account and use the system to submit project applications. If the project is approved,
INTERREG+ will be used for reporting on the progress of project implementation (both
content-wise and financially). National control will confirm the eligibility of expenditure and
the joint secretariat will monitor the projects using the monitoring system.
national co-financing
The non-EU contribution to the projects’ budget provided either by the State budget of each
partner country or provided as own contribution by the project partners.
7
1 Institutional setup of the Programme
The European Commission is the donor of the IPA and ERDF funds, establishing the IPA and
ERDF regulations.
The managing authority (MA) of the Programme is the Ministry of Foreign Affairs and Trade
in Hungary, bearing overall responsibility for the management and implementation of the
Programme towards the European Commission.
The body carrying out the accounting function, also known as certifying authority (CA) of the
Programme is the Hungarian State Treasury, responsible for submitting applications for
payment and annual accounts to the European Commission.
The audit authority (AA) of the Programme is the Directorate General for Audit of European
Funds (DGAEF) in Hungary, as a functionally independent body from the MA, the CA and the
Control Bodies, responsible for verifying the effective functioning of the management and
control system.
The joint secretariat (JS) is the main contact of lead partners both in Hungary and in Serbia in
relation with the implementation of their projects. It is set up within Széchenyi Programme
Office Non-profit LLC (SZPO) in Budapest with an office in Szeged, the JS assists the lead
partners during project development, application, contracting and project implementation.
The JS also assists the MA, CA, AA, the MC and the National Authorities in carrying out their
respective duties.
For each project contracted under the Programme, a responsible Programme manager (PM)
is nominated within the JS, to provide assistance during the project implementation.
The joint secretariat antenna (JSA) contributes to the implementation of tasks delegated to
the JS. The JSA is set up in Subotica, Serbia in order to ensure a geographically balanced
implementation of the Programme through serving Applicants’ needs in the Serbian border
area as well. This also includes that colleagues working at the JSA can act as fully responsible
Programme Managers.
Control Bodies: Set up in Regional Control Units of SZPO with Territorial Offices in Szeged
and Békéscsaba, Hungary and within the Department for Contracting and Financing of EU
Funded Programmes (CFCU) of the Ministry of European Integration of the Republic of
Serbia the respective Control Bodies are responsible for verifying expenditure at national
level in accordance with EU and national rules.
2.1 The lead partner principle and cooperation among partners within the partnership
The lead partner (hereinafter referred to as LP) is solely responsible towards the managing
authority (MA) for the implementation of the SC for EU contribution (hereinafter referred to
as Subsidy Contract or SC) including the timely and correct reporting towards the JS.
The appointed LP coordinates the project implementation process, and the work of the
partnership, and fulfils administrative and professional tasks. The cooperation between
partners (within the partnership) is established in the Partnership Agreement (hereinafter
referred to as PA) in order to implement project activities successfully.
The LP makes sure that all partners within the partnership understand and are aware of the
activities that have to be accomplished. Also, the LP’s task is to find and develop the most
efficient way and source of communication.
The aim of this main programme-level principle is to contribute to the proper and effective
functioning of cross border partnerships, to emphasize the sustainable cross-border
cooperation leading to sustainable actions, results and impacts.
The Partnership Agreement is a document laying down provisions that guarantee sound
financial management of funds allocated to the project; establishing cooperation principles,
which regulate the rights and responsibilities of project partners for a successful
implementation of project activities. As for the EU funding, the SC establishes a legal basis
between the managing authority and lead partner and the PA establishes the legal basis
between the partners including the lead partner. The PA is annexed to the SC.
This contractual arrangement provides an overview of each partner’s role in the project,
activities to be fulfilled, timeframe of the activities, and relationship between the partners as
well as the procedure used in case of disputes. The agreement covers all the special
situations that might occur during project implementation phase as well as necessary steps
to be taken. Therefore, partners should agree on - among others - the ownership of the
project results; the methods to achieve and maintain project results and risk management
procedures.
The PA serves as a mutually binding contract and ensures that each partner accepts and
carries out its assigned tasks.
It is important to point out that the PA can be modified by the partners as long as it is in line
with the SC.
10
3 Conflict of interest
Project partners must undertake all necessary precautions to avoid conflict of interest and
must inform the JS/MA authority without delay about any situation constituting or likely to
lead to any such conflict. A conflict of interest exists where the impartial and objective
exercise of the functions of any person involved in the project is compromised for reasons
involving family, emotional life, political or national affinity, economic interest or any other
shared interest with another person.
Following the MC decision, the Subsidy Contract will be concluded between LP and MA. The
MA/JS will send a letter on award of subsidy to the LP containing all relevant information,
conditions and deadlines essential for contracting.
After the decision on award of subsidy and before the contracting a technical meeting is
taking place between the lead partner and JS. This meeting is about the clearing of project
budget, indicators and activities in order to update the project without prejudice to the main
objective of the original application.
If deemed necessary, the JS can decide to carry out site visits at the premises of the lead
partner (and the partners, if needed) or in other location(s) of implementation. The main
purpose of the site visits is to check whether the activities have already started and whether
they are in line with the content of the approved project form (PF).
A site visit can be carried out by the JS on the date agreed with the lead partner. During the
visit minutes of the meeting is taken containing the observations of the JS staff.
The SC guarantees, on the one hand, the rights and obligations of the LP, and on the other,
the rights and duties of the MA for the appropriate use of EU contribution within the
framework of the Programme.
The SC containing the PF serves as a basis for the monitoring of activities, and it is a core
document in the event of settlement of disputes.
The SC enters into force on the date when the last of the contracting parties signed it. The
implementation of the project starts on the date indicated in the SC, which can be before or
after the signature of the SC. In case of Hungarian lead partners, E-signature is applicable.
11
5 EU Advance payments
In line with the SC, projects will receive the amount of EU advance payment specified in the
SC - EU advance payment of 15% of the maximum EU contribution of the project. The
amount of EU advance of partners determined at the time of concluding SC are not subject
to change during the project implementation. Re-allocation between project partners or
additional EU contribution for the project does not affect the EU advance amount. The
transfer of the EU advance payment is done automatically, within 60 days from the date of
signature of the Subsidy Contract (subject to availability of EU funds on the Programmme’s
single bank account). The LP is responsible for transferring the respective amounts of EU
advance specified in the SC to the partners within the timeframe agreed in the PA. The
received pre-financing shall be deducted from the payment of EU contribution of approved
PRs during the implementation period, in line with the provisions of the SC.
During the process of signing the SC, each lead partner will receive online access to the Front
Office of the Programme’s monitoring system. This surface will enable the lead partners to
submit PRs and applications for reimbursement and modification requests on behalf of the
partnership. Upon LP’s approval of their role requests, project partners also gain access to
the Front Office of the Programme’s monitoring system, where they will be able to see the
content of their project part and submit PPRs.
The monitoring system is the main communication and monitoring tool along project
implementation: all information must always be updated by the lead partner, as the JS/MA
shall make reference to those data to proceed with the requests for payment.
Monitoring system for project implementation - Interreg + (I+) is in line with Regulation (EU)
No 2016/679 - General Data Protection Regulation, GDPR - which introduces rules on data
protection.
12
6.1 Access to the monitoring system
All PPs must become I+ user through registration: recording and signatory user roles will be
provided on level of project partner and project level, as only assigned users can create,
modify and submit PPRs and PRs.
The lead partner requests the I+ user roles from the JS. After the user role was granted, the
lead partner recording user provides access upon request to all project partners. The
usernames and passwords to access project’s data, PPRs and PRs must be considered as
confidential data. The lead partner and project partner(s) must create their own PPRs. Also,
the lead partner has an obligation to prepare and submit the PR on behalf of the
partnership. Only users assigned to the lead partner can view PPRs from all project partners,
as those users are responsible to prepare and sign the PR. Other project partners have
access only to their reports.
For more information to access the monitoring system, details on adding, removing and
changing different types of users please see the User manual for Front Office users of the
INTERREG+ system.
13
7 Modification of the Subsidy Contract, Other Project Changes and
administrative change
Even if well planned and prepared, a project might need modifications during the
implementation due to various reasons. The deviations from any aspect of project
implementation defined in the SC and its Annexes have to be reported to the JS. To seek an
approval for changes, the LP fills in the modification request in cooperation with project
partner(s) and submits it to the JS.
As a general rule:
• LP has to notify the JS maximum 15 calendar days from the time after the change
occurred, or with the submission of the PR at the latest.
• Only one modification (either addendum or OPC) can be requested during a reporting
period (four months).
• Prolongation request has to be initiated at least 45 calendar days before the project
end date.
The basic rule is that the modifications affecting the basic purpose of the project as approved by
the MC are not allowed.
1. Modification of the SC
2. Other project changes (OPC)
3. Administrative changes
4. Withdrawal - “Declaration of Withdrawal” of the partner leaving the project
5. Termination of the SC
14
3. Reallocation to a budget line which was decreased according to the decision of the
MC
4. Budget reallocation under 100 EUR
5. Budget reallocation within those budget headings, which are calculated based on flat
rate.
Modifications between budget items within one budget line do not need to be requested
within a modification process. The INTERREG+ monitoring system tolerates these differences
while reporting.
Special type of modification is the termination of SC by MA, see the Annex I. to the SC Article
11. (General Terms and Conditions).
As a general rule, all types of modifications shall be requested by the LP through the
INTERREG+ monitoring system. For technical help regarding how to submit a modification
request within the system, please see the Front Office user manual for project modification
on the programme’s website.
The only exception is merging the reporting periods, because that shall not be requested,
the LP has only the obligation to inform the JS in the name of the partnership. Since merging
the reporting periods has an effect on the reimbursement of EU funds, the merge in only
possible if the whole partnership agrees on it.
If the LP requests substential project changes, then it requires a request for the modification
of the Subsidy Contarct. Such request must be approved by the MC or the MA. After the
approval of the request, the MA and the LP are signing an addendum to the SC.
As a general rule, the project lead partner cannot be changed, only project partners. This
type of request for project modification requires the approval of the MA and MC, depending
on the reason for change. If the MC approves the requested change, the addendum of the
SC is signed by the MA. However, in case of merger/fusion with legal continuity/successor in
partner or lead partner organisation, without a change of tax number, which can be proved
by legal documents of succession, the addendum to the SC is not necessary, unless the MA
decides differently. In such instances, it is enough that the lead partner informs the JS by
15
submitting the necessary documents. Nevertheless, in case that the partner’s national tax
number changes, the change must be approved by the MA, i.e. it will be a SC modification.
Project partner replacement can be done if a PP(s) already present in the partnership -
meaning activity and financing involvement of a certain partner is higher. The change is
preferably located in the same partner state so that the overall EU contribution part of the
project budget stays the same. Eligibility requirements must be ensured. In case the
withdrawn project partner has already received EU contribution payments related to
preparation costs and/or expenditure incurred and verified , it retains its share of paid EU
amount, unless it did not implement any activity during the project implementation. The
withdrawn project partner must respect the obligations of documents retention for the time
duration as reported in the SC/PA and solve all pending situations (e.g. repayment of undue
EU funds). The replacing project partner(s) shall take over the left budget of the withdrawn
project partner; it must demonstrate to have sufficient skills and expertise to efficiently
implement the remaining tasks left by the withdrawn PP.
• A withdrawn partner is replaced by a new partner, which takes over the remaining
activities;
The withdrawn PP can be replaced by a new institution which takes over the remaining
activities, upon condition that eligibility requirements are fulfilled. PP replacement can be
done through the inclusion of a new PP located in the same partner state by keeping
unchanged the overall EU contribution part of the project budget shares. The new identified
PP must demonstrate to have sufficient skills and expertise to efficiently implement the
remaining tasks. The new total EU contribution part of the PP budget is the difference
between what initially planned for the withdrawn PP and what already spent and paid. The
16
withdrawn PP must respect the obligations of documents retention for the time duration as
mentioned in the SC/PA and solve all pending situations (e.g.repayment of undue EU funds).
The legal change is possible on condition that the new entity takes over all duties and
obligations of its predecessor (e.g. retention of document, respect of internal audit trail,
eventual follow-up of irregularities etc.) and eligibility rules are respected. Legal change can
effect the subsidy structure of the respective partner. All documents affecting the modified
legal status or legal change must be provided to MA/JS.
Since this type of change can have fundamental effects on the project content, the JS may
use the help of quality assessors with the decision on the modification request. In case the
request for modification is deemed necessary and well justified, the JS forwards it to the
MC/MA for decision. If the MC/MA approves the requested change, the Addendum of the SC
is signed by the MA and the LP.
As a general rule, the request for modification requires the approval of the MA, but in case
the project duration exceeds the maximum duration set in the Guidelines for Applicants of
the respective Call for Proposals, the approval of the MC is necessary. If the MC approves
the requested change, the Addendum of the SC is signed by the MA and the LP.
Any request for modification of the SC has to be justified and submitted by the LP to the JS.
The JS checks the request for modification and in cases described above submits it for
approval to the MA or to the MC depending on the type of the requested modification.
Upon approval of the MA/MC, the finalized Addendum to the SC has to be signed by both
contracting parties.
17
7.2 Other project changes (OPC)
For project changes not listed above – which do not require the amendment of the SC – the
modification requires the approval of the JS, and the modification is considered as an other
project change (OPC). The LP has to notify the JS maximum 15 calendar days from the time
after the change occurred, or with the submission of the PR at the latest.
All changes in the project have to be in line with the rules of the Guidelines for Applicants of
the relevant Call for Proposals, as well as the Eligibility of Expenditures, (e.g. if a limit for a
certain type of cost was set in the Guidelines for Applicants, the proposed change must
respect the limit as well).
Furthermore, requested changes have to be in line with the decision of the MC, i.e. if the MC
decision contained any conditions for contracting, those have to be respected throughout
the implementation of the project, the modification(s) of the project cannot be
contradictory to the conditions.
Smaller adimistrative changes such as, changing postal address or the address of the
headquarters, contact person, contact data (phone number, e-mail address) of the contact
person or the legally authorised representative;
18
8 Modification process algorithm
The LP submits a request for modification to the JS through the monitoring system.
19
Request for modification from LP
MA/JMC: JS:
Approved/ Rejected Rejected Approved/
Rejected? Rejected?
Approved
JS informs LP.
End of process. Approved
JS sends signed
Addendum to LP JS sends Approval
of request to LP
LP signs the
Addendum and LP informs Ps
sends it back to
the JS
Controller is
informed about
LP informs Ps
the modification
The responsible
Partner informs Controller
the Controller registers the
about the changes
modification
Controller
registers the
changes
20
9 Monitoring visits
In order to have a more direct contact between the programme management bodies and
the partnership of individual projects and to get a closer, more real view of the project
implementation, the work being carried out, the progress and the achievements, the JS visits
contracted projects at least once during the implementation period and in case it is
considered necessary, additional visits might be needed based on the project financial and
technical performance.
Project partners should be prepared for these visits and ready to provide all required
information and documents. The focus of the review and meeting will be on the progress of
activities, their timely implementation and the related reported and verified costs, the
progress towards project objectives and indicator targets, management and communication
of the project, potential risks, problems, delays and their possible solutions, and a realistic
forecast for the remaining implementation. It is to be based on a constructive dialogue
between the programme management and the project partnership to get direct feedback on
both sides about the status and perspectives of the project.
The JS (including members of JSA) or the MA may carry out monitoring visits in order to
check the status of the project implementation. In general, the JS notifies the LP prior to the
monitoring visit about the proposed date, although unannounced visits are also possible,
especially if there is a suspicion of irregularity. The visit may be linked to a project event. In
addition, JS monitoring visit provides an opportunity for partners to consult the JS. The
monitoring visit is not considered as an audit and is not a pre-requisite for the approval of
the PR and the Application for Reimbursement. However, the JS/MA can use the information
gathered during the visit as a basis to propose specific actions, including suspending EU
contribution payments or even withdrawal from the SC (in case the project implementation
significantly deviates from the objectives indicated in the SC or there is a suspected
irregularity).
In case of investment projects a site visit can be organized prior to conclusion of the SC, in
order to check the present situation.
All observations made and the results of the monitoring visit will be included in the minutes
to be acknowledged and signed by all the participants.
21
10 Reporting and reimbursement process of the EU funds
The payment of EU funds (except for the advance payments described before) is connected
to the submission and approval of PR. The aim of the PR is to describe the progress in the
implementation of the project and the way partners acted in order to obtain these results.
The PR furthermore underpins the content of the Application for Reimbursement, i.e. links
between the incurred costs and the tasks and activities stipulated in the PF. Each PR
submitted to the JS has to be prepared by the LP and shall be accompanied by an AfR, which
indicates the total amount of EU funding to be reimbursed. An essential condition for the
transfer of EU funding is the timely submission of the PR together with the necessary
supporting documents/annexes containing correct information.
EU funding will be transferred directly to the LP’s bank account (sub-account) opened
exclusively for the purpose of the project. The LP is responsible for transferring the
respective EU amounts to the partners within the timeframe agreed in the PA.
PRs need to be submitted on a regular basis by the deadlines specified in the SC. The
reporting period, in general, covers four months of the project implementation, starting
from the starting date of the Project.
11 Reporting deadlines
By signing the PA and SC the project partners respect the deadlines of reporting which is 15
days for project partners (30 days in case of the final report) and 90 days for lead partners
after the end of the reporting period.
12 Project Report
At the end of each 4-month reporting period, the lead partner prepares and submits a PR to
the JS via the Front Office of the monitoring system. For technical help regarding how to
submit a PR within the system, please see the Front Office user manual for PRs on the
programme’s website.The purpose of the PR is to inform the JS and the programme
management bodies about the activities, which were carried out and the expenditures
incurred in the given reporting period. In order to compile a comprehensive report, the lead
partner gathers necessary data and documents from all partneres of the project.
Each partner prepares their own PPR concerning the activities they implemented and
justifying their own expenditures. The partners shall be aware of the fact that this might be a
time and resource consuming process and the timely preparation of the documents is
essential for the successful reimbursement process.
22
The PR (which includes both, narrative and financial report) is accompanied by the
Application for Reimbursement, which is generated by the monitoring system based on the
Declaration on Verification of Expenditures (DOVE) issued by the responsible Control Bodies
to each partner for the given period, as well as other compulsory annexes and relevant
supporting documents.
The template of the PR is attached as Annex I and the template of the AfR as Annex II of the
present Project Implementation Manual. Both documents are automatically generated by
the monitoring system (and saved under ’Documents’ datasheet) upon the completion and
online submission of the PR. (The annexes are attached for your information only, they are
approximations of the forms generated by the system, so, please, do not use them for
reporting).
The deadline for submission of the PR and AfR to the JS is 90 days from the end date of the
respective 4-month reporting period. The project start date, the reporting periods and the
actual deadlines for submission are indicated in the PF and also available in the monitoring
system.
The PR is prepared by the LP, but each PP must contribute to the compilation of the PR by
preparing and submitting their PPRs. PPs have to provide adequate information to the LP
concerning the activity and financial progress of their project part via the PPR in relation to a
certain reporting period. It is important that the LP describes the progress of the project
implementation in sufficient details and quality. In the PR, the LP is expected to regularly
present the progress in achieving the project outcomes, implementing the activities and
reaching the deliverables, including the progress towards reaching the indicators’ target
values. Following submission of the PR, the report is verified by the JS..
All projects financed by the Programme must respect the horizontal principles of the
Programme including „do-not-significant harm” (DNSH) principle which states that the
activities implemented within a project may not cause any significant harm to the
environment.
However, some projects may contribute to one or more Programme’s horizontal principles
(equality between men and women, equal opportunities and non-discrimination and
sustainable development including environmental sustainability). Such projects were
awarded points during the assesment of project proposals which they need to justify in the
project implementation. In case the project planned to promote and strengthen any of
three horizontal principles, the contribution should be explained and proved in the PRs and,
if relevant, in PPRs.
In PPRs and PRs the partners should explain their contribution with specific actions to the
above mentioned principles and always prove with quantitative data, supporting documents
and other sources of verification. Those specific actions relevant to both principles will be
23
closely monitored by the Programme bodies. For more information, please visit Guidelines
for Applicants Chapter 7. p.41-48)
The PR shows the progress of the implementation of project activities in a given period of
time. The PR provides an overview of the project implementation and also shows deviations
in comparison to the activity plan presented in the PF. The PR consists of two main parts:
narrative and financial part.
The narrative part requires descriptions about the steps taken in a given reporting period.
Under the Achievements chapter, updates are provided by answering the following
questions:
24
• progress of reaching all indicator targets
• progress on works/infrastructure related activities etc.
Please note that the Narrative part must be clear, coherent, relevant and time-related
compared to PF. In case of deviation (especially in deliverables and outputs),
clarification/justification shall be provided.
The MA/JS might reject submitted deliverables or outputs that are of low quality or do not
comply with the project form, requesting the project to solve detected issues.
The financial part contains information and provides general overview of the expenditures
related to the project activities performed in the reporting period. The report must contain
the lists of expenditures for all partners, verified by the respective Control Body in the form
of DOVEs.
The LP must ensure that the expenditures presented for reimbursement by all partners are
not double financed; are in compliance with the principle of sound financial management;
and were included in the budget of the project approved by the MC.
The financial part of the PR summarizes the costs incurred and paid on partner level based
on several different aspects. The PR contains the financial summary by budget lines and by
sources, the overall financial progress in the total budget and in the EU contribution
separately, and revenues gained (if applicable in case of state aid) in the reporting period.
This part also contains information about the settlement of the EU advance and also about
the transfer of the EU funding by the lead partner to the partners (accompanied by the bank
statement proving the transfer).
Project Partner Reports closed without verification, Project Reports with merged reporting
periods
25
project, therefore it will affect all project partners. Thus two reporting periods can be
merged only upon agreement of the whole partnership.
PPR without any reported expenditure can also be submitted to Control Body with proper
explanation about reasons and causes of underperforming. The Control Body will close the
verification without issuing DOVE.
Partners of the project with weak performance will be invited by MA/JS to targeted
meetings, to provide further clarifications on the project implementation state of play and to
define a road map to catch up or to adopt specific countermeasures.
As a general rule supporting documents for the PR have to be submitted only in electronic
form via the monitoring system.
The PR is filled in, which also includes the upload of all necessary supporting documents, and
submitted electronically through the front office of the monitoring system. The AfR is
generated by the monitoring system. The language of the reporting is English: the PR, the
AfR and the DOVEs are prepared in English. Accompanying documents which were made in
Hungarian and Serbian languages shouldn’t be translated.
Verification process by JS
Following the receipt of the documents, the responsible Programme / Financial Manager at
the JS / JSA performs the PR’s content verification.
During the verification process, the JS may request additional information or documents if
necessary for the proper understanding and approval of the PR. The verification process is
suspended until all required documentation and data are provided by the LP.
The verification process is divided into two main stages: verification of the PR and
verification of the application for reimbursement.
In order to facilitate the appropiate fill in of PR, please find attached the Checklist of JS for
PR and AfR as Annex III of this document.
26
12.3 Completion
In case the submitted PR is technically incomplete; the content of the report is found
unsatisfactory or any of the required supporting documents are missing, the JS programme
manager sends a completion letter via monitoring system (submission of additional/missing
documents and information).
The lead partner has maximum 10 working days upon receipt of the request to submit the
required additional/missing information and documents. The documents are submitted
electronically by filling the required fields in the certain sheet(s) of the monitoring system or
uploading it to the corresponding folder of the Interreg + monitoring system.
12.4 Revalidation
12.5 Rejection
If the lead partner does not respond to the request for completion of documents, the PM
sends a reminder. If the lead partner fails to reply to the second notice and does not
complete the documents, the PR may be rejected. As a general rule, those expenditures,
which relate to a rejected AfR can be re-submitted only once and only for the subsequent
reporting period. Only in justified cases, later re-submission of those expenditures may be
accepted.
27
12.6 Preparation and content of the Application for Reimbursement
The AfR summarizes the expenditures of the partners in the reporting period, based on the
Declarations on Verification of Expenditures (DOVE) issued by the Control Body.
In the verification process of the AfR special attention is paid to the following aspects:
• The EU subsidy requested in the AfR is within the frame of the approved amount of
EU subsidy;
• The EU amount of reimbursement is correct and in line with the EU amounts
approved in DOVEs;
• EU advance payment is taken into consideration in the amount of transferable EU
contribution, as stipulated in article 2. point 3. of the SC.
Once the verification of the PR and AfR has been completed, the JS initiates the
reimbursement of the EU funding. Following the approval of the MA, the CA transfers the
amount of EU contribution stated in the approved AfR to the separate bank account of the
lead partner. Upon receipt of the EU funding, the lead partner is obliged to transfer the
respective amounts on time and in full to each partner. Timeframe of the reimbursement
stated in the PA.
The reporting procedure and the form of the final PR are the same as the procedure and
form of any PR but a special attention should be paid to the check box in the monitoring
system.
The latest possible date for the payment of expenditures incurred within the project is 30
calendar days after the last date of eligibility period. However, the payment is not allowed
after the final date of eligibility which is 31 December 2029.
The project is considered fully implemented if carrying out the planned activities and results
is successful, moreover by achieving at least 80 per cent of the quantifiable outputs in due
time.
28
SRB: Predlog komisije za tehnički pregled za izdavanje upotrebne dozvole;) any other
permits prescribed by relevant Regulations;
• Other project specific documents requested by the JS;
• A scanned copy of bank statement proving the last transfer of EU funds.
In addition, lead partners should deliver to the responsible PM samples of information and
publicity material produced during the project implementation along with the final PR. Such
material includes, but is not limited to: posters, any other printed material – books, booklets,
or brochures, as well as promotional branded merchandize used during the project. The
Programme will use such material on occasions which promote the Programme, Interreg
and EU.
The final reimbursement of the EU funding is made after the conclusion of the project and
according to the final AfR as approved by the JS. Please note that in case of unsettled EU
advance settlement the remaining amount will be recovered.
Following the approval of the FPR the JS initiates the financial closing of the project in the
monitoring system, in order to calculate the exact amount of EU funding to be reimbursed to
the LP.
Financial closure cannot be initiated in case other processes related to the project are still
on-going (such as irregularity and recovery procedures). After the final payment of EU
contribution to the lead partner and transfer the reimbursement to partners, the project is
considered as closed.
13 Eligibility
Detailed rules of eligibility of a certain cost are described in the ‘Eligibility of expenditures’
published on the Programme’s website (always check the latest available version).
14 Procurement rules
Procurement rules to be applied at programme level are defined by MA, published on the
Program’s website, they are available as in the ‘Eligibility of expenditures’. National rules and
legislation are also to be respected.
An irregularity may occur at any moment in the project cycle, from programming through to
audit, ex post monitoring or evaluation. Checks at any stage of project implementation may
indicate that the conditions to be met by a partner after project completion are not being
respected.
29
Irregularity suspicions can be detected by the Control Body, JS, MA, CA, NA, AA, EC,
European Court of Auditors, European Anti-Fraud Office (OLAF), whistle-blowers, lead
partners, project partners, other bodies authorised to carry out financial verifications on
projects, or other bodies and individuals, including anonymous ones. The investigation of
irregularity suspicions and decision making about irregularities belongs to those country’s
NA, of which the affected partner is located (or in case of EGTC, the EGTC is registered).
Where recoveries shall be performed in running projects, all unduly paid out EU funds must
be deducted from the next reimbursement due or, where applicable, from reimbursement
which is still under examination by the Programme bodies or remaining EU payments can be
suspended. In order to ensure a proper audit trail of such deductions, these financial
corrections will be managed and stored through the monitoring system (INTERREG+).
Depending on how the amounts unduly paid out have been detected, different requirements
must be met:
1) in cases where they have been identified by the controller of the project partner
(e.g. during on‐the‐spot checks), the relevant controller must provide the
necessary information to the JS/MA/NA so that the financial correction can be
made;
2) in cases where they have been identified by other level controllers (JS, MA, CA,
audit authority, European Commission), the MA/JS will promptly inform the lead
partner, the concerned partner and the national authority. Possibility of involving
the responsible CB at national level, will be undertaken whenever necessary.
For already closed projects, or in cases when deduction from the next reimbursement
cannot be made fully, a recovery procedure towards the lead partner must be launched.
For cases in which the project has already received the last EU fund instalment, the MA shall
demand from the lead partner repayment of EU subsidy in whole or in part. In case the EU
amounts unduly paid out refer to a project partner, it will be up to the concerned project
partner to repay the lead partner any EU amounts unduly paid in accordance with the
agreement existing between them (PA).
In any cases of financial corrections the LP shall ensure that, if applicable, the concerned PP
repays the LP any EU amounts unduly paid, as provided for in the PA. If the LP does not
30
succeed in securing repayment from other PP(s), the LP shall inform the MA via the JS in
written form within the deadline for repayment.
If the MA does not succeed in securing repayment from the LP, the partner state on whose
territory the partner concerned is located (or in case of EGTC, the EGTC is registered). shall
reimburse the MA any EU amounts unduly paid to that PP. As a consequence of that, the
affected partner state shall be entitled to claim the unduly EU funds from the PP concerned.
The MA shall be responsible for reimbursing the EU amounts concerned to the general
budget of the Union, in accordance with the apportionment of liabilities among the
participating partner states as laid down in the Interreg Programme.
c) Double funding
One of the important elements to be taken into account when participating in EU funded
projects is the need for implementing measures to avoid double funding from different
co‐financing sources for the same expenditure item. In practice, this means that the
expenditure that has already been supported by other EU or national funds is not eligible. In
case of co‐financing from other funds, the cost can be deemed eligible only for the part of
the cost not covered by subsidy. Whereas analytical accounting systems help in this respect,
more straightforward measures must also be foreseen. More information in the SC art.6 and
in national rules (if relevant).
16 Project closure
The audit trail is a comprehensive set of documents, which provides a complete history of a
project and evidence that proper procedures have been applied and outcomes achieved. It is
a compulsorily requirement both for the LP and PPs and legally foreseen both in the SC and
in the PA. Linked to the audit trail it is the need of ensuring the creation and regular update
of a project archive where to store all relevant data, documents, pictures etc. related to the
project implementation and of setting in place a separate accounting system or a separate
accounting code. Please note that relevant documents necessary for PR must be uploaded in
the monitoring system as well. The audit trail allows the recording of all documentary
evidence of the steps undertaken by the partners during the project implementation.
Documents part of the audit trail can be originals, certified true copies of the originals, or
electronic versions stored on commonly accepted data carriers (including electronic only) in
accordance with the respective LP and PPs national rules. Electronic archives must comply
with the relevant necessary security standards in accordance with the national law and that
can be considered as reliable for verifications and audit purposes. These documents shall be
made available for any audit, control or verification after project closure.
All the supporting documents related to the project must remain available at the premises of
each LP/PP at the appropriate level for a 5-year period from 31 December of the year in
which the last payment by the managing authority to the LP is made according to Article 82
31
(1) of CPR (EU) Regulation 2021/1060. In case of state aid relevance, different rules can
apply.
Right after the last day of implementation, the project’s retention period starts. For the
entire retention period, all bodies in charge of performing controls and audits are entitled to
access the LP and PPs premises to check all relevant project documentation and invoices or
other accounting documents with equivalent probative value value.
The project partners should retain ownership of results (investements, equipment, other
deliverables) during both the implementation period and follow-up period of the project
according to the article 11 and 14 of the PA.
If there is a need to transfer rights of use of project outputs described and approved in the
PF to a third party to maintain the results, the lead partner should notify the JS.The project
partner has to obtain the prior written consent of the MA. The request for the consent to
transfer rights of use of outputs of the project should be submitted with well defined
justification, supporting documents and draft of written agreement with the third party. In
case MA approves the request, the written agreement with the third party can be signed.
According to the SC, the project results have to be maintained for a period of minimum 5
years after the date of the final payment to the lead partner. This means that the project
result shall not undergo a substantial modification. In addition, partners have to fulfil some
obligations towards the Programme, namely keeping all the project documentation in a safe
place for audit purposes and preparing and submitting project follow-up reports even when
all the activities were implemented, expenditures reimbursed and paid and the project was
closed. Additional financial controls and audits can be expected during the entire
Programme period. Until then, the partners should be able to provide without delay all
documentation related to their respective project parts.
The Follow-up Report covers minimum 12-month periods (except for the Final follow-up
report), starting from the date of the final payment to the lead partner. It is submitted upon
JS request in monitoring system, before the set deadline. In case that LP does not submit the
follow-up report within 15 days following the expiry of the deadline, LP will recieve a
reminder letter.
32
19 GDPR
The EU General Data Protection Regulation’s (GDPR) purpose is to harmonize data privacy
laws across Europe, to protect and empower all EU citizens’ data privacy, and to reshape the
way organizations across the region approach data privacy. GDPR applies to all handling of
personal data, such as how to collect, handle, store and delete the data. The Regulation
2016/679 (General Data Protection Regulation – GDPR) introduces strict rules on data
protection. Interreg VI-A IPA Hungary-Serbia Programme are obliged to collect some
personal data necessary for project monitoring with full respect of GDPR.
20 List of Annexes
Annex I.: Project Report and Application for Reimburesement (PR&AfR) template
Annex II.: Project Report and Application for Reimburesement (PR&AfR) checklist
Annex III.: Modification checklist template
Annex IV.: Monitoring visit template
NOTE: The PR&AfR form and PR&AfR and modification checklists (Annex I, II, III) are visual
representations of on-line forms that will be used within INTERREG+ system during the
different stages of implementation. The actual printed forms (if their printing becomes
necessary), may differ from the listed annexes.
33