Quality Answer
Quality Answer
Quality Answer
b is the correct answer. Each of these methods can be used to reduce risk by either reducing the
frequency of a harmful event or the magnitude of the harm in an event.
2. Which of the activities below should be performed first as part of the SIL selection process?
b is the correct answer. The amount of risk that can be tolerated should be agreed upon before risk
identification, budget or equipment issues.
a. only I, II and IV
b. only II and III
c. only I and II
d. only I, II and III
d is the correct answer. All of the items are true except it IV. A SIL2 system must have a PFDavg
between 0.001 and 0.01 to provide a risk reduction factor of 100 to 1000.
4. What is the difference between qualitative and quantitative SIL selection processes?
a. Qualitative methods do not use any numbers while quantitative ones do.
b. Qualitative methods use categories of risk while quantitative ones use specific numerical criteria.
c. Qualitative methods are generally better than quantitative ones.
d. Both b and c.
b is the correct answer. Qualitative methods can have numerical components and may or may not be
better that quantitative methods depending on the type of information available for a given situation.
As defined in the presentation, qualitative methods make categorical groupings while quantitative risk
techniques use specific numerical criteria.
5. The hazard matrix has dimensions (rows or columns) for which of the following risk components?
a. II and III
b. I and III
c. all four items
d. I and II only
b is the correct answer. Both the magnitude and the frequency of the harmful event define the
dimensions of the hazard matrix method of SIL selection.
a. Consequence magnitude
b. Probability of avoiding the hazard if in its effect zone
c. Occupancy probability
d. Demand rate or frequency of the hazard.
e. all of the above
e is the correct answer. All of the items listed are commonly used categories in a risk graph analysis.
7. What would you expect a higher probability of occupancy to produce in a risk graph analysis?
b is the correct answer. The higher probability of occupancy is generally likely to result in a higher SIL
requirement. It is important to note that each risk graph category should be treated independent of all
of the others so that each component of the risk is counted once and only once in the analysis.
a is the correct answer. A risk graph provides a recommended SIL for the situation in question. The
other items listed are often considered in developing the risk graph analysis but are not its result.
9. Which safety standards address SIL selection methods?
I. IEC 61508
II. IEC 61511
III. ISO 9000
IV. ISA84.01
a. I and IV only
b. I, II, and IV only
c. all four items
d. I and II only
b is the correct answer. Both of the IEC standards and the ISA standard specifically cover SIL
selection methods. ISO 9000 addresses quality work process and production system issues.
a is the correct answer. A SIL specifies required risk reduction to an order of magnitude level. A SIL
does not specify the level of risk, it states risk reduction.