Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 1
ITP - Inspection & Test Plan
THE CONSTRUCTION MANAGER: THE CONTRACTOR:
Contract No.: Transmittal no.: ITP Ref. No.: Date Issued: ITP Details Inspection & Test Plan for NGR Test or Action Specification and/or Verification Item No. Activity Description Inspection Acceptance Criteria Frequency Verification Document Drawing No. Personnel Method B A C A Visual and Mechanical Inspection Compare equipment nameplate date with Manufacturer 1.0 Inspection the same as approved before energization CM/ SBG/ QA/QC H H S Appoved shop drawings drawings and specifications. recomendation Manufacturer 2.0 Inspect physical and mechanical condition. Inspection no defects before energization CM/ SBG/ QA/QC H H S Appoved shop drawings recomendation Inspect anchorage, alignment, grounding, and Manufacturer 3.0 Inspection completeness before energization CM/ SBG/ QA/QC H H S Appoved shop drawings required area clearances. recomendation Manufacturer 4.0 Verify the unit is clean Inspection completeness before energization CM/ SBG/ QA/QC H H S Appoved shop drawings recomendation Verify that current transformer ratios correspond Manufacturer 6.0 Inspection completeness before energization CM/ SBG/ QA/QC H H S Checklist to drawings. recomendation Verify the Resistor Rating as per the approved Manufacturer 7.0 Inspection completeness before energization CM/ SBG/ QA/QC H H S Checklist drawings. recomendation Verify that all required grounding and shorting Manufacturer 8.0 Inspection completeness before energization CM/ SBG/ QA/QC H H S Checklist connection provided. recomendation Verify all shorting blocks are in correct position, Manufacturer 9.0 Inspection completeness before energization CM/ SBG/ QA/QC H H S Checklist either grounding or open as required. recomendation Verify tightness of accessible bolted electrical connections by calibrated torque-wrench Manufacturer 10.0 test manufacturer recomendation before energization CM/ SBG/ QA/QC H H S Checklist method in accordance with manufacturer’s recomendation published data or Table 100.12. Verify the Equipment’s are satisfied with the Manufacturer 11.0 Inspection manufacturer recomendation before energization CM/ SBG/ QA/QC H H S Appoved shop drawings specifications and approved drawings. recomendation B Electrical Test Perform insulation-resistance tests on Current Manufacturer 1.0 test manufacturer recommendation before energization CM/ SBG/ QA/QC H H W test results Transformers & Resistors recomendation Perform electrical tests on Current transformers Manufacturer 2.0 test manufacturer recommendation before energization CM/ SBG/ QA/QC H H W test results & Resistors. recomendation Manufacturer 3.0 Perform HI-Pot test test manufacturer recommendation before energization CM/ SBG/ QA/QC H H W test results recomendation C Test Values – Visual and Mechanical Compare bolted connection resistance values to values of similar connections. Investigate values which deviate from those of similar Manufacturer 1.0 test manufacturer recomendation before energization CM/ SBG/ QA/QC H R R test results bolted connections by more than 50 percent of recomendation the lowest value. (7.1.1.7.1) Bolt-torque levels shall be in accordance with manufacturer’s published data. In the absence Manufacturer 2.0 of test manufacturer recomendation before energization CM/ SBG/ QA/QC H R R test results recomendation manufacturer’s published data, use Table 100.12. (7.1.1.7.2 D Test Values - Electrical Compare bolted connection resistance values to values of similar connections. Investigate values which deviate from those of similar Manufacturer 1.0 test manufacturer recomendation before energization CM/ SBG/ QA/QC H R R test results bolted connections by more than 50 percent of recomendation the lowest value. Manufacturer 2.0 Electrical tests on Resistors test manufacturer recomendation before energization CM/ SBG/ QA/QC H R R test results recomendation Results of electrical tests on instrument Manufacturer 3.0 transformers shall be in accordance with test manufacturer recomendation before energization CM/ SBG/ QA/QC H R R test results recomendation Section 7.10. Manufacturer 4.0 Heaters shall be operational. test manufacturer recomendation before energization CM/ SBG/ QA/QC H R R test results recomendation Legend: H - Hold Point (signature required to proceed) S - Surveillance (random attendance, no signature) B- Subcontractor W - Witness (attendance expected, signature on check sheet) R - Record Review A - Contractor C - Constraction Management