7 Day Forecast

Well HSV‐1XST1 Max beds on rig 144


Date Sat 28‐Dec‐24 Current POB 135 Max POB next 6 days 138

Saturday 28 Dec Sunday 29 Dec Monday 30 Dec Tuesday 31 Dec Wednesday 01 Jan Thursday 02 Jan Friday 03 Jan
0:00 Shut in well for main PBU 0:00 Shut in well for main PBU 0:00 BHS Flow 0:00 MPLT flow period 0:00 Kill well and unset packer, POOH and L/D tubing 0:00 RIH w/ 5.5" DP X 3.5" DP to 3408m 0:00 POOH
1:00 1:00 1:00 1:00 1:00 1:00 1:00
2:00 2:00 2:00 2:00 2:00 2:00 2:00
3:00 3:00 3:00 3:00 Max flow 3:00 3:00 Circulate bottoms up gas free 3:00
4:00 4:00 4:00 4:00 4:00 4:00 4:00
5:00 5:00 5:00 5:00 5:00 5:00 Pump cement plug #1 5:00
6:00 6:00 6:00 6:00 Kill well and unset packer, POOH and L/D tubing 6:00 6:00 Pull out and circulate out 6:00 Rig up Baker E‐line
7:00 7:00 7:00 MPLT flow period 7:00 7:00 7:00 7:00 Run and set bridge plug
8:00 8:00 8:00 8:00 8:00 8:00 8:00
9:00 9:00 9:00 9:00 9:00 9:00 Pump cement plug #2 9:00
10:00 10:00 10:00 10:00 10:00 10:00 Pull out and circulate out 10:00 Rig down wireline
11:00 11:00 11:00 11:00 11:00 11:00 11:00 Pick up 8.5" Window Mill / Whipstock
12:00 12:00 12:00 12:00 12:00 12:00 12:00
13:00 13:00 13:00 13:00 13:00 13:00 WOC 13:00
14:00 14:00 14:00 14:00 14:00 14:00 14:00 TIH
15:00 15:00 15:00 15:00 15:00 15:00 15:00
16:00 16:00 16:00 16:00 16:00 16:00 16:00
17:00 17:00 17:00 17:00 17:00 17:00 17:00
18:00 18:00 18:00 18:00 18:00 Lay out Jar 18:00 18:00
19:00 19:00 19:00 19:00 19:00 M/U 3.5" DP CMT stinger 19:00 Tag cement and pressure test 19:00
20:00 20:00 20:00 20:00 20:00 20:00 POOH 20:00 Orient Whipstock / Set WS/Release BHA
21:00 21:00 BHS Flow 21:00 21:00 21:00 RIH w/ 5.5" DP X 3.5" DP to 3408m 21:00 21:00
22:00 22:00 22:00 22:00 22:00 22:00 22:00 Mill Window drill and sidetrack hole
23:00 23:00 23:00 23:00 23:00 23:00 23:00
Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig
Coil Tubing Equipment / N2 Equip JDC Equipment PVD Well Test Equipment/ Burner Booms
6" Fishing Tools Rubbish Skip & Hazardous Waste Skip SLB DST Equipment
PBL Sub Basket Round Trip JDC Pipe & Cargo Slickline Equipment
3‐1/2" Tubing & 4‐3/4" DC 3‐1/2" Tubing (After POOH)
Round Trip Cargo TCP Equipment & explosives

?? Subject to change due to Operation ?


Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig
JDC Groceries SLB Sidetrack BHA tools
SLB Cement & Chemicals?? Baker Whipstock Equipment
PVD Expro Well Test Empty Baskets for R/D Baker MPC Cutter
6.5" Jars and 6‐3/4" PBL Sub
Mud Cooler & Equipment

(To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig)
On Off On Off On Off On Off On Off On Off On Off
9 JDC Crew Change 9 1 Murphy Logistics Paul/Chet 1
1 Murphy HSE 1 6 JDC 6
Murphy Completion Engineer 1 3 SLB MWD/DD
2 Baker Hughes Whipstock
1 MI Mud Engineer 1
2 Baker Wireline Second Flight
PVD NOV Solids Control 4 PVD Expro Well Test 7
Second Flight SLB Well Test/DST 4
4 PVD Mud Cooler Halliburton TCP 4

New Year's Groceries (90kg)


0 0 0 0 0 0 19 16 0 0 10 22 0 0
POB 135 POB 135 POB 135 POB 138 POB 138 POB 126 POB 126
VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS
SM12 Departing Rig SM12 Arriving at Rig SM29 Departing Rig SM29 Arriving at Rig SM12 Departing Rig??
8 ‐ 14 Day Forecast
Well HSV‐1XST1 Max beds on rig 144
Date Sat 4‐Jan‐25 Max POB next 6 days 134

Saturday 04 Jan Sunday 05 Jan Monday 06 Jan Tuesday 07 Jan Wednesday 08 Jan Thursday 09 Jan Friday 10 Jan
0:00 Mill Window drill and sidetrack hole 0:00 P/U 8‐1/2" Drilling BHA. TIH 0:00 Drill to coring point 0:00 Drill to coring point 0:00 POOH 0:00 TIH 0:00 TOH slowing down for last 200m
1:00 1:00 1:00 1:00 1:00 1:00 1:00
2:00 2:00 2:00 2:00 2:00 2:00 Core #1 54m 2:00
3:00 3:00 3:00 3:00 3:00 3:00 3:00
4:00 Circulate clean 4:00 4:00 4:00 4:00 4:00 4:00
5:00 5:00 Drill to coring point 5:00 5:00 5:00 5:00 5:00
6:00 Perform LOT 6:00 6:00 6:00 6:00 6:00 6:00
7:00 POOH L/D Window Mill 7:00 7:00 7:00 7:00 7:00 7:00
8:00 8:00 8:00 8:00 8:00 8:00 8:00
9:00 9:00 9:00 9:00 9:00 9:00 9:00
10:00 10:00 10:00 10:00 10:00 10:00 10:00 Lay down core barrels
11:00 11:00 11:00 11:00 11:00 11:00 11:00
12:00 12:00 12:00 12:00 Circulate hole clean 12:00 12:00 12:00
13:00 13:00 13:00 13:00 13:00 13:00 13:00
14:00 14:00 14:00 14:00 14:00 Pick up coring assembly 14:00 14:00 Pick up coring barrels
15:00 15:00 15:00 15:00 POOH 15:00 15:00 15:00
16:00 16:00 16:00 16:00 16:00 16:00 TOH slowing down for last 200m 16:00
17:00 P/U 8‐1/2" Drilling BHA. TIH 17:00 17:00 17:00 17:00 17:00 17:00
18:00 18:00 18:00 18:00 18:00 TIH 18:00 18:00 TIH
19:00 19:00 19:00 19:00 19:00 19:00 19:00
20:00 20:00 20:00 20:00 20:00 20:00 20:00
21:00 21:00 21:00 21:00 21:00 21:00 21:00
22:00 22:00 22:00 22:00 22:00 22:00 22:00
23:00 23:00 23:00 23:00 23:00 23:00 23:00
Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig Equipment From Rig

Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig Equipment AT Rig
Halliburton Coring Equipment
Contingency 7" Liner

(To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig) (To Rig) CREWCHANGE (From Rig)
On Off On Off On Off On Off On Off On Off On Off
5 Halliburton Coring Crew?? 15 JDC 13 12 JDC 12
1 PVD Mudlogger 1 1 PVD Data Engineer 1
1 SLB MWD/DD
Baker Wireline 3
1 VPI OOC
6 PVD NOV Solids Control
PVD Expro Well Test 4

14 8 0 0 0 0 16 14 0 0 12 12 0 0
POB 132 POB 132 POB 132 POB 134 POB 134 POB 134 POB 134
VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS
SM12 Arriving at rig