07210231
07210231
07210231
Abstract—This paper presents a tri-level reliability-constrained Annualized investment cost of unit and of line
robust power system expansion planning (SEP) framework mod- ($).
eling the uncertainty of electricity demand, wind power genera- Availability status of unit and of line (1/0
tion, and availability of units and lines. In the proposed tri-level stating availability/unavailability status).
SEP model, electricity demand and wind power generation being
continuous uncertain variables are modeled by bounded intervals Lower and upper bounds for the decomposition
and availability of units and lines being discrete uncertain vari- algorithm.
ables are modeled by probability distributions. Simulation results Sufficiently large positive constant.
on the Garver 6-bus, the IEEE 24-bus, and the IEEE 73-bus test Operation cost of unit ($).
systems confirm the effectiveness of the proposed tri-level frame-
work to cope with multi-fold planning uncertainties. Nominal estimate for electricity demand at bus
Index Terms—Reliability, robust optimization, stochastic pro- in operating condition (MW).
gramming, system expansion planning. Lower and upper estimates for electricity demand
at bus in operating condition (MW).
Penalty cost ($).
NOMENCLATURE Capacity of unit (MW).
1) Functions: Capacity of line (MW).
EENS Expected energy not supplied. Repair time of unit and of line (h).
2) Indices: Nominal estimate for wind power generation at
bus in operating condition (MW).
Index of operating conditions. Lower and upper estimates for wind power
Index of units. generation at bus in operating condition
Index of Monte Carlo simulation samples. (MW).
Susceptance of line (mho).
Index of iterations.
Maximum allowable limit for variables.
Index of lines.
Convergence tolerance.
Index of buses.
Degree of robustness.
Sending bus of lines .
Receiving bus of lines . 4) Sets:
Set of operating conditions.
3) Parameters:
Set of units and of lines.
Duration time of operating condition .
Set of units connected to bus .
at iteration (MWh).
Set of operation and of reliability cuts.
Target value of (MWh).
Set of buses.
Energy not supplied for sample (MWh).
Feasible region for investment decisions.
Failure rate of unit and of line (Occ./Yr.).
Feasible region for operation decisions.
Energy not supplied for sample (MWh).
Polyhedral uncertainty set.
Manuscript received January 31, 2015; revised June 03, 2015; accepted July 5) Variables:
26, 2015. Date of publication August 19, 2015; date of current version April 15,
2016. Paper no. TPWRS-00139-2015. Power generation of unit in operating condition
S. Dehghan is with the Department of Electrical, Biomedical, and Mecha- (MW).
tronics Engineering, Qazvin Branch, Islamic Azad University, Qazvin, Iran Power flow of line in operating condition
(e-mail: shahab.dehghan@ieee.org).
N. Amjady is with the Department of Electrical and Computer Engineering, (MW).
Semnan University, Semnan, Iran (e-mail: amjady@semnan.ac.ir). Uncertain electricity demand at bus in operating
A. J. Conejo is with the Integrated System Engineering and the Electrical and condition (MW).
Computer Engineering Departments, The Ohio State University, Columbus, OH
43210 USA (e-mail: conejonavarro.1@osu.edu).
Unserved electricity demand at bus in operating
Digital Object Identifier 10.1109/TPWRS.2015.2464274 condition (MW).
0885-8950 © 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
2384 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 31, NO. 3, MAY 2016
Uncertain wind power generation at bus in others, most of previous research works deal with generation
operating condition (MW). and transmission expansion planning separately [1], [2]. How-
Status of unit and of line (e.g., ever, some SEP approaches have been presented in the liter-
constructed; otherwise). ature employing reliability cost-worth criterion [3], mixed-in-
Phase angle of bus in operating condition teger linear programming (MILP) [4]–[6], and mixed-integer
(radian). nonlinear programming (MINLP) [7].
Phase angle of reference bus in operating Any power system is subject to different low-frequency un-
condition (radian). certainty sources (e.g., annual peak load) and high-frequency
6) Vectors and Matrices: uncertainty sources (e.g., availability of units and lines) [8].
Moreover, in the past decade, increasing integration of intermit-
Matrices of coefficients.
tent renewable energy sources has resulted in increasing chal-
Vectors of requirements. lenges and uncertainties in planning studies. Accordingly, it is
Vectors of investment and operation costs. necessary to develop non-deterministic SEP frameworks coping
Vector of coefficients for the operation with the uncertain nature of power systems and finding a flexible
variables in the objective function of the expansion plan immunized against different realizations of un-
load-curtailment problem (i.e., certainty sources. Stochastic programming (SP) [9], modeling
). uncertain variables by means of scenarios [4]–[7], [10] and ro-
Vector of availability status of equipment bust optimization (RO) [11], modeling uncertain variables by
(e.g., ); when means of bounded intervals [12]–[16], have been used in the
the uncertainty of equipment availability is literature to handle a wide range of uncertainty sources. RO
considered, this vector is shown by . is particularly attractive in case of low-frequency uncertainty
Simulated vector of availability status of sources [13], [15], as it only requires the relative variation in-
equipment at iteration . tervals of uncertain variables rather than generating scenarios.
Vector of electricity demand; when the Besides, RO is more conservative than SP as the solution of
uncertainty of electricity demand is considered, RO is optimal for the worst-case realization of uncertain vari-
this vector is shown by . ables while the solution of SP is optimal on average for a set
of deterministic scenarios capturing the uncertainty spectrum.
Vectors of lower and upper estimates of .
Over-conservatism of the optimal solution may be a disadvan-
Vector of fixed obtained by solving the tage of RO-based optimization models. However, this issue is
operation sub-problem at iteration . more significant in the case of pioneering RO-based optimiza-
Vector of wind power generation; when the tion models, such as the robust counterpart of linear program-
uncertainty of wind power generation is ming problem introduced by Soyster [11], which are not capable
considered, this vector is shown by . of controlling the conservatism of the optimal solution. This
Vectors of lower and upper estimates of . issue is alleviated in the case of recent RO-based optimization
Vector of fixed obtained by solving the models, which have the ability of controlling the conservatism
operation sub-problem at iteration . of the optimal solution. For instance, the conservatism of the
Vector of investment variables (i.e., optimal solution in the proposed model can be controlled by a
). particular parameter named degree of robustness.
Vector of fixed obtained by solving the In [4] and [5], SP is used to cope with uncertainties pertaining
investment master problem at iteration . to electricity demands and availability of equipment within
Vector of operation variables (i.e., the SEP problem. In [6], SP is employed to handle the uncer-
tainties of SEP pertaining to correlated electricity demands
; ). and wind power generations. Also, the SEP problem under
Vector of operation variables added to the uncertain electricity demand is solved in [7] by incorporating
master problem to create operation primal cut a risk factor, based on the mean-variance theory, into SP. In
at iteration . [16], RO is employed to handle the uncertainties pertaining to
Vector of expected sensitivity of EENS with availability of equipment (i.e., units and lines) within the SEP
respect to at iteration . problem. Although the SEP problem has been solved previously
under different uncertainty sources, to the best of the authors'
I. INTRODUCTION knowledge, there is no non-deterministic SEP model for power
systems including wind units and considering both discrete and
A. Background and Motivation continuous uncertain variables simultaneously. Accordingly,
1) Joint consideration of continuous and discrete uncertainty between modeling accuracy and computation tractability [6].
sources. Previous research works in the area have used Without loss of generality, it is assumed that the location and
either bounded intervals [13]–[15] or probability distribu- capacity of wind farms are specified.
tions [4]–[7], [10] to characterize continuous and discrete
uncertain variables. Accordingly, there is no research B. Uncertainty Characterization
work characterizing the continuous uncertainties per- The intrinsic uncertainties pertaining to electricity demands
taining to correlated electricity demands and wind power and wind power generations as well as availability of equipment
generations by bounded intervals, through a polyhedral are considered in the proposed SEP model. Specifically, wind
uncertainty set, and the discrete uncertainties pertaining to power generation is not stochastic within a yearly window. In
availability of equipment by probability distributions. In other words, the profile of wind power generation (acquired by
addition, the -means clustering technique is used in this dividing the wind power generation by the capacity of wind
paper to construct a polyhedral uncertainty set pertaining farms) remains unaltered from year to year. Needless to say,
to the correlated electricity demands and wind power many scenarios are needed to characterize wind generation
generations. It is worth mentioning that the -means clus- throughout one year, but there are no changes from year to year.
tering technique has been previously used in [6] and [10] Analogous to wind power generation, the profile of electricity
to generate deterministic operation conditions considering demand (acquired by dividing the electricity demand by the
fixed values for the correlated electricity demands and peak demand of each year) is assumed to remain unaltered
wind power generations. On the contrary, such technique during one whole year and many scenarios are needed to
is used in this paper to generate non-deterministic opera- characterize it throughout one year [10]. However, the yearly
tion conditions considering bounded intervals rather than forecasted growth rate of demand is subject to uncertainty.
fixed values for the correlated electricity demands and We characterize the uncertainty pertaining to the profile of
wind power generations. electricity demand and wind power generation in terms of
2) Hybridizing SP and RO modeling to find a robust expan- uncertainty sets [18] rather than scenarios. Accordingly, we
sion plan satisfying a probabilistic reliability constraint, can find a flexible and robust expansion plan withstanding the
i.e., expected energy not supplied (EENS), under the worst-case realization of these uncertainty sources.
worst-case realization of correlated electricity demands Since electricity demand and wind power generation are sta-
and wind power generations. To the best of the authors' tistically correlated [19], the -means clustering technique [10]
knowledge, there is no work reported in the literature is used to construct a polyhedral uncertainty set. In this study,
jointly characterizing continuous and discrete uncertain the yearly historical data sets of wind/demand profiles are parti-
variables by hybridizing the notions of RO and SP. tioned by the -means clustering technique into a finite number
3) Introducing a new tri-level decomposition algorithm to of clusters [19]. The centroid of each cluster is chosen as the
solve the proposed reliability-constrained robust SEP nominal estimate of the electricity demand and wind power gen-
problem. The proposed decomposition algorithm employs eration in each operation condition (i.e., and ). Also,
primal and dual cutting planes submitted to the first level -quantile and -quantile of empirical cumulative prob-
expansion master problem by the second level operation ability distributions pertaining to electricity demand and wind
and third level reliability sub-problems, respectively. Note power generation of each cluster (e.g., for ) are chosen
that the traditional Benders decomposition only employs as lower and upper estimates of electricity demand and wind
dual cutting planes [17]. On the contrary, the proposed power generation in each operation condition (i.e.,
tri-level decomposition algorithm simultaneously benefits and ). In addition, the duration time of each oper-
from dual and primal cutting planes. ation condition (i.e., ) is calculated by dividing the total
number of historical data samples belonging to each cluster over
C. Paper Organization the total number of historical data samples. On the other hand,
The rest of the paper is organized as follows. In Section II the the discrete uncertainty pertaining to availability of equipment
main features of the proposed SEP model are described. In are characterized by their forced outage rate (FOR) [3]. In line
Section III the mathematical formulations of deterministic and with previous research works in the area [3]–[8], short-term op-
non-deterministic models are introduced. In Section IV, sim- erational uncertainties, such as the uncertainties pertaining to
ulation results comparing deterministic and non-deterministic short-term load forecast, are not considered in this paper. Note
SEP models are provided and discussed. Finally, the main that the time framework of the operational uncertainty sources
conclusions are given in Section V. (e.g., one to several hours) is completely different from the time
framework of the planning uncertainties considered in the paper
II. PROBLEM DESCRIPTION (e.g., one to several years).
(1a)
(1b)
(1c)
(1d)
Fig. 1. Tri-level decomposition algorithm to solve the RSEP problem.
(1e)
(1f)
(1g) The objective function (2a) represents (1a). Also, (2b) corre-
(1h) sponds to (1h) and (1i), (2c) corresponds to (1b) and (1g), (2d)
corresponds to (1c)–(1f), and (2e) corresponds to (1j). Note that
(1i)
the equality constraint can be stated in terms of two op-
(1j) posite inequalities and . In (2d), , where is
a vector of ones. As the DSEP model only considers one real-
The objective function (1a) minimizes the total investment ization of the uncertainty sources, its expansion plan may not be
costs of candidate units and lines, total operation costs of units, sufficiently robust to withstand different realizations of the un-
and total penalty costs due to unserved electricity demands. certain variables. To remedy this limitation and find a robust and
Constraint (1b) states the power balance for each bus in every flexible expansion plan, the reliability-constrained robust SEP
operating condition. Constraints (1c)–(1e) represent the power (RSEP) model handling the uncertain nature of electricity de-
flow for every line and its limits, respectively, where is a suf- mands, wind power generations, and availability of equipment
ficiently large positive constant (i.e., [14]). Con- is introduced as follows:
straint (1f) limits the generation of units. Also, constraint (1g)
bounds the maximum value of unserved electricity demand for (3)
each bus. Constraint (1h) bounds phase angles. Constraint (1i)
sets the phase angle of reference bus on zero. Finally, constraint
(1j) represents the integrality conditions for investment vari- where ,
ables. In the deterministic model given by (1a)–(1j), and , and
indicate investment related variables and , , , , and .
indicate operation related variables. Min-max-min problem (3) minimizes the summation of
investment and operation costs subject to investment and
B. Non-Deterministic Model operation constraints (i.e., and ) under the worst-case
realization of uncertain electricity demands and wind power
The above-mentioned DSEP model can be rewritten in the generations (i.e., and ). Although min-max-min plan-
compact form given in the following: ning models have been solved by two-level decomposition
algorithms in [13]–[15], these algorithms cannot be used here
(2a) due to incorporating the probabilistic reliability constraint
(2b) of in (3). Accordingly, a
tri-level decomposition algorithm, outlined in Fig. 1, employing
(2c)
primal operation and dual reliability cuts is proposed in this
(2d) paper. Next, the investment master problem as well as the
(2e) operation and reliability sub-problems are presented.
DEHGHAN et al.: RELIABILITY-CONSTRAINED ROBUST POWER SYSTEM EXPANSION PLANNING 2387
1) Investment Master Problem: This problem finds the op- in (11) can be replaced by their equivalent expressions given
timum expansion plan considering the primal operation cuts, in (14) and (15), respectively. Thus, T2 in (11) can be rewritten
i.e., (5)–(7), and dual reliability cuts, i.e., (8): as follows:
(4)
Ξ (16)
(5)
As (16) only includes multiplication of binary and continuous
(6) variables, its nonlinear terms can be recast into linear ones using
(7) a set of new binary and continuous variables in addition to the
disjunctive constraints as given in the following:
(8)
(9) (17)
where Ξ . After solving the MILP where
investment master problem, the investment variables are fixed
in the operation and reliability sub-problems (i.e., ). Also, the
in Fig. 1 is updated in terms of the optimal solution of the
master problem obtained at iteration (i.e., ).
2) Operation Sub-Problem: The operation sub-problem only
considers the uncertainty pertaining to electricity demands and
(18)
wind power generations. Given the optimal investment vari-
ables obtained by solving the master problem (i.e., ),
Also, , , , and are auxiliary continuous mod-
the operation sub-problem is
eling variables. The linear terms in (17) function analogously to
(10) the nonlinear terms in (16) where . Consequently, the
linearized version of the bilinear operation sub-problem can be
rewritten as follows:
where
. Considering the dual of the inner minimization
problem of (10), this max-min problem can be rewritten as a (19)
Ξ
maximization model given in the following:
(20)
(11)
where Ξ
, and T2 is as given in (17). Also, the robustness
(12) of the operation sub-problem can be controlled by adding the
(13) following constraint (21) to the MILP model of (19) and (20):
(22)
(23) IV. CASE STUDIES
(24) In this section, the proposed RSEP methodology is used to
(25) expand the generation and transmission system of a modified
(26) Garver 6-bus test system [20], the IEEE 24-bus, and the IEEE
73-bus reliability test systems (RTS) [21] where . All
where, represents a vector of auxiliary variables case studies have been run using CPLEX within GAMS on a
and represents the vector of dual variables for the 64-bit windows-based server with 60 GB of RAM and 24 Intel
constraint of sample . By solving the LP Xenon processors clocking at 3.33 GHz.
problem for sample , the objective function of (22)
A. Garver 6-Bus Test System
gives .
Step 4) Calculate the value of and as given in The modified Garver 6-bus test system includes 10 units and
(27) and (28). If the coefficient of variation [12] for 8 lines as shown in Tables I and II, respectively. Moreover,
the MCS is less than , stop the algorithm and re- 72 candidate units and 45 transmission lines are considered.
port and ; otherwise, go to Step 2, gen- The characteristics of candidate units and lines are shown in
erate another sample , and continue the algorithm: Tables III and IV, respectively. In this study, the forecast of peak
electricity demand for each bus is assumed to be 2.5 times of the
current value given in [20]. Also, two wind farms with 40-MW
(27)
and 20-MW capacities are located at buses 1 and 5, respec-
tively. Wind units are not investment candidates, as mentioned
in Section II-A. The polyhedral uncertainty set of electricity de-
(28)
mand and wind power generation is constructed using the his-
torical data pertaining to the power system of Texas during year
After solving the reliability sub-problem, the probabilistic 2005 based on the method described in Section II-B with
reliability constraint (i.e., ) should be . The employed electricity demand profiles of buses 1,
checked. If , the decomposition algorithm 2, 3, 4, and 5 belong to North, East, Coast, West, and South re-
stops; otherwise, and are submitted to the invest- gions of electricity reliability council of Texas (ERCOT) [22],
ment master problem to incorporate a new dual reliability cut, respectively. Moreover, it is assumed that the wind farms lo-
as given in (8) and shown in Fig. 1. By terminating the proposed cated at buses 1 and 5 are equipped with 2-MW wind units
tri-level decomposition algorithm, the obtained optimal expan- (Vestas V80/2000 with a hub height of 80 m) and their wind
sion plan, i.e., , and its associated investment and operation power generation profiles belong to Northwestern and South-
costs are reported. eastern flat lands of Texas [23], respectively.
DEHGHAN et al.: RELIABILITY-CONSTRAINED ROBUST POWER SYSTEM EXPANSION PLANNING 2389
TABLE IV
CANDIDATE LINES FOR GARVER TEST SYSTEM
TABLE VI
OPTIMAL SOLUTION VERSUS FOR GARVER TEST SYSTEM
1) Optimal Solution versus Degree of Robustness: Given 2) Optimal Solution versus : Given and
10 operation conditions for the 5 electricity demand buses 10 operation conditions for correlated electricity demands and
and the 2 wind power generation buses, can adopt different wind power generations, the optimal expansion plans obtained
integer values between 0 and (i.e., the from RSEP-1 are provided in Table VI where of the
total number of uncertain variables belonging to ). The previous case (i.e., 0.01) is varied leading to 0.015 and
optimal expansion plans obtained from DSEP and RSEP are 0.005 of AED. According to Table VI, the expansion cost is
illustrated in Table V where is equal to 0, 35, and 70 in increased from $175.289 M to $187.352 M by decreasing the
RSEP-1, RSEP-2, and RSEP-3, respectively, and is value of from 0.015 of AED to 0.005. In other words,
0.01 of the annual energy demand (AED). In Table V, a more reliable expansion plan is obtained by adding more new
and denote number of operation and reliability cuts in units and lines at the expense of more expansion cost. Similar re-
the proposed tri-level decomposition algorithm required to sults are obtained from RSEP-2 and RSEP-3 for this case, where
find the optimal expansion plan, respectively. The expansion is set on 50% and 100% of its maximum value, respectively.
cost monotonically increases from DSEP to RSEP-3. The 3) Optimal Solution versus Operation Conditions: In this
lowest expansion cost is imposed by DSEP as it ignores all case, the initial 10 operation conditions are increased to 20 and
uncertainties. The expansion cost obtained by RSEP-1 is more 30. Considering 5 electricity demand and 2 wind power genera-
than DSEP because RSEP-1 includes the uncertainty pertaining tion buses, the maximum value of becomes
to the availability of equipment and requires satisfying the and , respectively. The optimal expansion
probabilistic reliability constraint. However, RSEP-1 excludes plans obtained from RSEP-2 for 20 and 30 operation conditions
the uncertainty pertaining to electricity demand and wind are illustrated in Table VII where adopts 50% of its max-
power generation as it considers . Accordingly, its imum allowable value. In this table, denotes number of op-
expansion cost is less than RSEP-2 and RSEP-3, which include eration conditions and the probabilistic reliability constraint is
the uncertainties pertaining to electricity demands and wind relaxed for simplicity leading to . The expansion plan
power generations in addition to satisfying the probabilistic of RSEP-2 for is relatively different with respect to
reliability constraint. Moreover, the expansion cost imposed by as more operation conditions model more realistically
RSEP-3 is larger than that of RSEP-2 because is equal to 70 the uncertainty pertaining to correlated electricity demands and
and 35 in RSEP-3 and RSEP-2, respectively. In other words, wind power generations.
RSEP-3 is the most expensive expansion plan as it satisfies the
probabilistic reliability constraint under the most conservative B. IEEE 24-Bus Test System
realization of uncertain electricity demands and wind power In the previous case studies, wind units are not considered
generations. as investment candidates. However, the proposed deterministic
2390 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 31, NO. 3, MAY 2016
TABLE VIII
CANDIDATE UNITS FOR IEEE 24-BUS RTS
TABLE IX
CANDIDATE LINES FOR IEEE 24-BUS RTS
the proposed reliability-constrained robust planning tool is [13] B. Chen, J. Wang, L. Wang, Y. He, and Z. Wang, “Robust optimiza-
capable of finding an optimal solution, immunized against tion for transmission expansion planning: Minimax cost vs. minimax
regret,” IEEE Trans. Power Syst., vol. 29, no. 6, pp. 3069–3077, Nov.
worst-case realization of uncertain electricity demands 2014.
and wind power generations, satisfying a probabilistic [14] R. A. Jabr, “Robust transmission network expansion planning with un-
reliability constraint. Additionally, the proposed approach certain renewable generation,” IEEE Trans. Power Syst., vol. 28, no.
4, pp. 4558–4567, Nov. 2013.
can control the robustness and reliability of the optimal [15] S. Dehghan, N. Amjady, and A. Kazemi, “Two-stage robust genera-
solution by means of two parameters named the degree tion expansion planning: A mixed integer linear programming model,”
of robustness and the target value of EENS. Accordingly, IEEE Trans. Power Syst., vol. 29, no. 2, pp. 584–597, Mar. 2014.
[16] R. L. Y. Chen, A. Cohn, N. Fan, and A. Pinar, “Contingency-risk in-
it is more flexible than solution methods based solely on formed power system design,” IEEE Trans. Power Syst., vol. 29, no. 5,
either RO or SP. pp. 2087–2096, Sep. 2014.
2) Joint consideration of continuous and discrete uncertain [17] A. J. Conejo, E. Castillo, R. Minguez, and R. Garcia-Bertrand, Decom-
variables using either RO or SP may result in intractability position Techniques in Mathematical Programming. New York, NY,
USA: Springer-Verlag, 2006.
of the optimization problem. Accordingly, RO has been [18] Y. Guan and J. Wang, “Uncertainty sets for robust unit commitment,”
previously used in the planning to only characterize either IEEE Trans. Power Syst., vol. 29, no. 3, pp. 1439–1440, May 2014.
continuous [13]–[15] or discrete [16] uncertain variables. [19] L. Baringo and A. J. Conejo, “Correlated wind-power production and
electric load scenarios for investment decisions,” App. Energy, vol.
On the contrary, SP has been previously used for joint 101, pp. 475–482, Jan. 2013.
consideration of continuous and discrete uncertain vari- [20] L. L. Garver, “Transmission network estimation using linear pro-
ables, but in small-scale test systems and not medium- and gramming,” IEEE Trans. Power App. Syst., vol. PAS-89, no. 7, pp.
1688–1697, Sep. 1970.
large-scale test systems [5]. Therefore, jointly considering [21] “The reliability test system task force, IEEE reliability test system,”
continuous and discrete uncertain variables of the planning IEEE Trans. Power Syst., no. 3, pp. 1010–1020, Aug. 1999.
model through either RO or SP is computationally cumber- [22] ERCOT [Online]. Available: http://www.ercot.com
[23] Alliance for Sustainable Energy System Advisor Model version, De-
some. On the other hand, the proposed hybrid approach can partment of Energy (DOE), National Renewable Energy Laboratory
more effectively characterize both continuous and discrete (NREL), Jan. 14, 2014.
planning uncertainties than either RO or SP.
Shahab Dehghan (M'14) received the M.S. and
Ph.D. degrees (with honors) in electrical engineering
REFERENCES from Iran University of Science and Technology,
[1] X. Wang and J. R. McDonald, Modern Power System Planning. New Tehran, Iran, in 2009 and 2014, respectively.
York, NY, USA: McGraw-Hill, 1994. He is currently an assistant professor at Qazvin Is-
[2] R. Hemmati, R. A. Hooshmand, and A. Khodabakhshian, “Compre- lamic Azad University, Qazvin, Iran.
hensive review of generation and transmission expansion planning,”
IET Gener. Transm. Distrib., vol. 7, no. 9, pp. 955–964, Sep. 2013.
[3] W. Li and R. Billinton, “A minimum cost assessment method for com-
posite generation and transmission system expansion planning,” IEEE
Trans. Power Syst., vol. 8, no. 2, pp. 628–635, May 1993.
[4] J. H. Roh, M. Shahidehpour, and L. Wu, “Market-based generation and
transmission planning with uncertainties,” IEEE Trans. Power Syst.,
vol. 24, no. 3, pp. 1587–1598, Aug. 2009.
[5] P. Jirutitijaroen and C. Singh, “Reliability constrained multi-area ad- Nima Amjady (SM'09) received the B.S., M.S., and
equacy planning using stochastic programming with sample-average Ph.D. degrees in electrical engineering from Sharif
approximations,” IEEE Trans. Power Syst., vol. 23, no. 2, pp. 504–513, University of Technology, Tehran, Iran, in 1992,
May 2008. 1994, and 1997, respectively.
[6] R. Dominguez, A. J. Conejo, and M. Carrion, “Toward fully renewable At present, he is a full professor with Semnan Uni-
electric energy systems,” IEEE Trans. Power Syst., vol. 30, no. 1, pp. versity, Semnan, Iran.
316–326, Jan. 2015.
[7] J. A. Lopez, K. Ponnambalam, and V. H. Quintana, “Generation and
transmission expansion under risk using stochastic programming,”
IEEE Trans. Power Syst., vol. 22, no. 3, pp. 1369–1378, Aug. 2007.
[8] B. G. Gorenstin, N. M. Campodonico, J. P. Costa, and M. V. F. Pereira,
“Power system expansion planning under uncertainty,” IEEE Trans.
Power Syst., vol. 8, no. 1, pp. 129–136, Feb. 1993.
[9] J. R. Birge and F. Louveaux, Introduction to Stochastic Program-
ming. New York, NY, USA: Springer, 1997. Antonio J. Conejo (F'04) received the M.S. degree
[10] L. Baringo and A. J. Conejo, “Risk-constrained multi-stage wind power from the Massachusetts Institute of Technology,
investment,” IEEE Trans. Power Syst., vol. 28, no. 1, pp. 401–411, Feb. Cambridge, MA, USA, in 1987 and the Ph.D. degree
2013. from the Royal Institute of Technology, Stockholm,
[11] A. Ben-Tal, L. E. Ghaoui, and A. Nemirovski, Robust Optimization. Sweden, in 1990.
Princeton, NJ, USA: Princeton Univ. Press, 2009. He is currently a full professor at The Ohio State
[12] S. Dehghan, A. Kazemi, and N. Amjady, “Multi-objective robust trans- University, Columbus, OH, USA.
mission expansion planning using information-gap decision theory and
augmented -constraint method,” IET Gener. Transm. Distrib., vol. 8,
no. 5, pp. 828–840, May 2014.