Measured Item Fir&Syami
Measured Item Fir&Syami
Measured Item Fir&Syami
DATA :
1) Material cost
= RM21.25 x 2 workers
= RM25.00
Total RM 402.50
i. 15% RM 60.38
Cement & sand brick built in cement and sand (1:3) mortar with
B3-A1-6(1/1) RM 63.20
plaster :
DATA :
1) Material cost
ii. Brick
Clay Bricks 63 bricks x RM 0.47 / pieces RM 29.61
= RM15.00
= RM3.72
Total RM 54.96
i. 15% RM 8.24
DATA :
1) Material cost
= RM30.00
= RM20.00
Total RM 500.00
i. 15% RM 75.00
C-1(1/3) RM 80.50
300 mm thick crusher run road base
DATA :
1) Material cost
= RM30.00
= RM20.00
Total RM 70.00
i. 15% RM 10.50
40mm thick Sandor /87 waterproofing plywood flush door with pvc
B4-A2-7(3/5) lining on external side overall size 750mm x 2100mm hanging on RM 284.63
butt hinges (measured with door frame) (Type D4)
DATA :
1) Material cost
= RM21.25 x 2 workers
RM 247.50
3) 15% Profit and Overhead
Total
i. 15% x 247.50 RM 37.13
DATA :
1) Material cost
= RM21.25 x 2 workers
= RM25.00 RM 320.50
10% tools RM 32.05
RM 352.55
3) 15% Profit and Overhead
Total
i. 15% x 352.55 RM 52.88
RM 405.43
Rate for 100 m2 100