CADANGAN PEMBINAAN 128 UNIT RUMAH TERES 2 TINGKAT UNTUK KAKITANGAN

KERAJAAN PT 23799 HINGGA PT 23927 LOT 23798, FASA 11B (2) DI


SEMENYIH MUKIM HULU LANGAT SELANGOR.

BUILT-UP RATE : MEASURED ITEMS

ITEM DESCRIPTION RATE


REF. (RM/M3)
WORK BELOW LOWEST FINISH

B3-A1-1(2/4) Reinforced In-Situ Concrete grade 25 in Column Stump RM 462.88

DATA :

MATERIAL : Concrete Grade 25 = RM 335.00 / m3

LABOUR : 1 Skilled Labour = RM 100 / day


2 General Unskilled Labour = RM 85.00 / Day

CALCULATION: RM/DAY RM/M3

1) Material cost

i. Concrete Grade 25 RM 335.00

2) Labour for installing

i. Unskilled Labour RM85.00 RM 42.50


x 2 Hour
8 Hours

= RM21.25 x 2 workers

ii. Skilled Labour RM100.00 RM 25.00


x 2 hours
8 Hours

= RM25.00

3) 15% Profit and Overhead

Total RM 402.50
i. 15% RM 60.38

Total Rate/No RM 462.88


CADANGAN PEMBINAAN 128 UNIT RUMAH TERES 2 TINGKAT UNTUK KAKITANGAN
KERAJAAN PT 23799 HINGGA PT 23927 LOT 23798, FASA 11B (2) DI
SEMENYIH MUKIM HULU LANGAT SELANGOR.

BUILT-UP RATE : MEASURED ITEMS

ITEM DESCRIPTION RATE


REF. (RM/M2)
EXTERNAL WALLS

Cement & sand brick built in cement and sand (1:3) mortar with
B3-A1-6(1/1) RM 63.20
plaster :

A Half brickwall, reinforced with brick reinforcement at every


A fourth course including bonding ties.

DATA :

MATERIAL : Mortar = RM 265.00 / m3

LABOUR : Bricklayer = RM 120.00 / day


General Unskilled Labour = RM 85.00 / Day

CALCULATION: RM/DAY RM/M2

1) Material cost

i. Mortar (1:3) RM 6.63


cost of mortar 0.025 m3 x RM265.00 /m3

ii. Brick
Clay Bricks 63 bricks x RM 0.47 / pieces RM 29.61

2) Labour for installing

i. Bricklayer RM120.00 RM 15.00


x RM 1.00 hr/m2
8 Hours

= RM15.00

ii. Skilled Labour Rm 85.00 RM 3.72


x RM 1.00 hr/m2
8 Hours

= RM3.72

3) 15% Profit and Overhead

Total RM 54.96
i. 15% RM 8.24

Total Rate/M2 RM 63.20


CADANGAN PEMBINAAN 128 UNIT RUMAH TERES 2 TINGKAT UNTUK KAKITANGAN
KERAJAAN PT 23799 HINGGA PT 23927 LOT 23798, FASA 11B (2) DI
SEMENYIH MUKIM HULU LANGAT SELANGOR.

BUILT-UP RATE : MEASURED ITEMS

ITEM DESCRIPTION RATE


REF. (RM/no)
SEWERAGE
840mm x 840mm Ductile Iron Heavy Duty manhole cover and
frame to B.S 497 with Model N, including bedding frame in
C-4(2/3) cement and sand (1:3) and sealing cover with grease and RM 575.00
painting with black synthetic,resin based paint complete with
locking and fitting device, comply with specification and
approved by the Sewerage Services Department as per
A Engineer's detail drawing

DATA :

MATERIAL : 840mm x 840mm mabhole cover = RM 450.00/no

LABOUR : skilled labour = RM 120.00 / day


General Unskilled Labour = RM 85.00 / Day

CALCULATION: RM/DAY RM/no

1) Material cost

1 840mm x 840mm mabhole cover RM 450.00

2) Labour for installing

i. skilled labour RM120.00 RM 30.00


x 2 hrs
8 Hours

= RM30.00

ii. Skilled Labour Rm 85.00 RM 20.00


x 2 hrs
8 Hours

= RM20.00

3) 15% Profit and Overhead

Total RM 500.00
i. 15% RM 75.00

Total Rate/no RM 575.00


CADANGAN PEMBINAAN 128 UNIT RUMAH TERES 2 TINGKAT UNTUK KAKITANGAN
KERAJAAN PT 23799 HINGGA PT 23927 LOT 23798, FASA 11B (2) DI
SEMENYIH MUKIM HULU LANGAT SELANGOR.

BUILT-UP RATE : MEASURED ITEMS

ITEM DESCRIPTION RATE


REF. (RM/m2)
ROADWORKS

C-1(1/3) RM 80.50
300 mm thick crusher run road base

DATA :

MATERIAL : Crusher run = RM 20.00 / m2

LABOUR : skilled labour = RM 120.00 / day


General Unskilled Labour = RM 85.00 / Day

CALCULATION: RM/DAY RM/m2

1) Material cost

1 crusher run RM 20.00

2) Labour for installing

i. skilled labour RM120.00 RM 30.00


x 2 hrs
8 Hours

= RM30.00

ii. Skilled Labour Rm 85.00 RM 20.00


x 2 hrs
8 Hours

= RM20.00

3) 15% Profit and Overhead

Total RM 70.00
i. 15% RM 10.50

Total Rate/no RM 80.50


CADANGAN PEMBINAAN 128 UNIT RUMAH TERES 2 TINGKAT UNTUK KAKITANGAN KERAJAAN
PT 23799 HINGGA PT 23927 LOT 23798, FASA 11B (2) DI
SEMENYIH MUKIM HULU LANGAT SELANGOR.

BUILT-UP RATE : MEASURED ITEMS

ITEM DESCRIPTION RATE


REF. (RM/M3)
DOOR

40mm thick Sandor /87 waterproofing plywood flush door with pvc
B4-A2-7(3/5) lining on external side overall size 750mm x 2100mm hanging on RM 284.63
butt hinges (measured with door frame) (Type D4)

B Overall size 750mm x 2100mm high

DATA :

MATERIAL : Sandor /87 waterproofing playwood = RM 200/no

LABOUR : 1 Unskilled Labour = RM 85/ day

CALCULATION: RM/DAY RM/M3

1) Material cost

i. Sandor /87 waterproofing Plywood RM 200.00

2) Labour for installing

i. Unskilled Labour RM85.00 RM 42.50


x 2 Hour
8 Hours

= RM21.25 x 2 workers

ii. Transportation Charges


Approximate 30 Door/Trip
RM150/trip
=
30 door RM5/door RM 5.00

RM 247.50
3) 15% Profit and Overhead
Total
i. 15% x 247.50 RM 37.13

Total Rate/No RM 284.63


CADANGAN PEMBINAAN 128 UNIT RUMAH TERES 2 TINGKAT UNTUK KAKITANGAN
KERAJAAN PT 23799 HINGGA PT 23927 LOT 23798, FASA 11B (2) DI
SEMENYIH MUKIM HULU LANGAT SELANGOR.

BUILT-UP RATE : MEASURED ITEMS

ITEM DESCRIPTION RATE


REF. (RM/M3)
CEILING FINISHES FOR PAINTING

Prepare and apply two finishing coats of "Kansai" or other


B4-A2-10(8/8) RM 4.05
equal and approved emulsion paint

DATA :

MATERIAL : Kansai paint = RM 99.00/ 5 litre


Emulsion paint = RM 55.00/ 5 ltire
LABOUR : 1 Skilled Labour = RM 100 / day
1 Unskilled Labour = RM 85/ day

CALCULATION: RM/DAY RM/M3

1) Material cost

i. 2 Coats Kansai paint RM 198.00

ii. Emulsion paint RM 55.00

2) Labour for installing

i. Unskilled Labour RM85.00 RM 42.50


x 2 Hour
8 Hours

= RM21.25 x 2 workers

ii. Skilled Labour RM100.00 RM 25.00


x 2 hours
8 Hours

= RM25.00 RM 320.50
10% tools RM 32.05
RM 352.55
3) 15% Profit and Overhead
Total
i. 15% x 352.55 RM 52.88
RM 405.43
Rate for 100 m2 100

Total Rate/No RM 4.05