CROSS-report-Concern-over-modelling-of-concrete-frame-structure
CROSS-report-Concern-over-modelling-of-concrete-frame-structure
Overview been constructed, or would not have through all stages of its life, including
A reinforced concrete-framed building sufficiently cured, to provide the stiffness those temporary conditions which
was several storeys in height and required for such an effect to occur. This would exist during construction. The
supported by a critical transfer slab at is clearly significant when considering reporter believes it is a case of ‘rubbish
first floor. It became apparent that the a concrete-framed structure, where in, rubbish out’ as far as the modelling
design had not appropriately considered about 80% of the load was as a result is concerned. Finally, checks should
the construction sequence of the frame. of self-weight. have been undertaken to ensure that
The peer review indicated several software outputs mirror those which can
Report areas of the critical transfer slab which be derived through conventional and
A reporter’s firm had recently been were considerably under-reinforced. This empirical ‘hand calculations’.
involved in undertaking a peer review could have led to structural failure of an As part of the review, enquiries were
of another consulting engineer’s design element and a possible disproportionate made with leading bodies who are
for a reinforced concrete flat-slab collapse. Even in areas where authorities on concrete construction and
frame. The frame was several storeys reinforcement was within strength limits, there seemed to be a lack of technical
in height and supported by a critical there was concern that the designed guidance on this subject. The current
transfer slab at first floor. structure lacked sufficient redundancy design codes (EC2, etc.) did not appear
In undertaking the review, it became and was therefore not robust enough to to cover the temporary modelling
apparent that the original design had withstand catastrophic disproportionate aspect in any significant detail aside
not appropriately considered the collapse. In such events, it is this from general statements to consider all
construction sequence of the frame. ‘redundancy’ which will be relied upon stages of construction.
The designer had undertaken their to ensure the structure remains stable Additionally, the reporter is concerned
reinforcement design for the critical (even if only temporarily) to allow the safe that the published guidance is now
first-floor transfer slab using a ‘global’ evacuation of occupants. around 15 years old and becoming
or ‘whole building’ 3D design model. The reporter understands that the increasingly outdated as more rigorous
The design model assumed that issues were acknowledged by the and detailed finite element-type analysis
the complete building structure was original designer and amendments to is undertaken. The reporter was also
in situ and fully cured. As such, the the design were made. surprised to find that the IStructE’s
analysis gave loads on the transfer slab In the opinion of the reporter, the latest technical guidance on this
much reduced compared to that of a issues stem from the inexperience of the subject, Computational engineering,
conventional ‘hand’ load takedown, designers in tackling such a structure, does not even appear to consider the
or indeed what would be replicated lack of competent internal checking importance of this subject in modelling
by undertaking individual slab design and over-reliance on software. The lack structures of this type.
models. of experience allowed the designers to In conclusion, the reporter considers
The analysis showed loads in proceed with the design not recognising that further technical guidance should
columns supported by the transfer slab the need to design the structure be provided on the subject and perhaps
were only about one third of those that even revisions to the aforementioned
would be obtained from a conventional documents considered. Additionally,
load takedown. It was clear that the Key learning outcomes engineers should remain vigilant in
global model had generated alternative For civil and structural design engineers: undertaking simplified ‘hand check’
load paths within the structure by Ò| During design and checking consider the loads assessments and more should be done
‘hanging’ of columns above the at each stage of construction to reinforce this to more junior (and
transfer structure; the columns being Ò| It is good practice to carry out sense checks and therefore inexperienced) engineers.
hung from frames above, proportionate validate all analysis and design outputs
to the frame stiffness, through a Ò| Ensure assumed construction methodology is Expert Panel comments
catenary or other action. communicated to contractors and is verified as Unfortunately, it is not uncommon for
It is the opinion of the reporter’s constructible by the contractor, with any changes lack of experience to lead to analysis
firm that generation of alleviating load agreed with the designer models missing key construction
paths was not possible at least when Ò| Consider the need for robustness at all stages of stages, or those using the model
considering the self-weight of the construction failing to appreciate the presence of
structure. The structure above the Ò| Independent checking is good practice secondary load paths. In this case,
transfer slab would either not have the upper frames in the model were
22
April 2022 | thestructuralengineer.org
23
thestructuralengineer.org | April 2022