Master Programme 4 revised
Master Programme 4 revised
77
78 139 days 17/9/14 2/2/15
Basement Slabs
79 7/1/15 66SS+24 days
Basement 3 slabs 105 days 25/9/14
80 22/1/15 79SS+55 days
Basement 2 beam & slabs 65 days 19/11/14
81 2/2/15 80SS+16 days
Basement 1 beam & slabs 60 days 5/12/14
82 79SS-8 days
Anti-termite treatment 75 days 17/9/14 30/11/14
83 79SS+5 days
Water Proofing basement 3 slab 85 days 30/9/14 23/12/14
84
85 286 days 4/2/15 16/12/15
SUPER-STRUCTURE
86 28/2/15 81FS+1 day
1st Storey slab 25 days 4/2/15
87 20/3/15 86FS-1 day
2nd Storey slab 21 days 28/2/15
88 4/4/15 87
3rd Storey slab 15 days 21/3/15
89 19/4/15 88FS+1 day
4th Storey slab 14 days 6/4/15
90 3/5/15 89
5th Storey slab 14 days 20/4/15
91 17/5/15 90
6th Storey slab 14 days 4/5/15
92 31/5/15 91
7th Storey slab 14 days 18/5/15
93 14/6/15 92
8th Storey slab 14 days 1/6/15
94 28/6/15 93
9th Storey slab 14 days 15/6/15
95 13/7/15 94FS+1 day
10th Storey slab 14 days 30/6/15
96 28/7/15 95FS+1 day
11th Storey slab 14 days 15/7/15
97 11/8/15 96
12th Storey slab 14 days 29/7/15
98 25/8/15 97
13th Storey slab 14 days 12/8/15
99 10/9/15 98
14th Storey slab 14 days 26/8/15
100 1/10/15 99FS+1 day
15th Storey slab 14 days 14/9/15
101 100
16th Storey slab 14 days 2/10/15 21/10/15
102 101FS+1 day
17th Storey slab 18 days 23/10/15 17/11/15
103 7/12/15 102
Roof Slab 14 days 18/11/15
104 103
Lift Roof slab 7 days 8/12/15 16/12/15
105
106 92 days 23/9/14 23/12/14
M & E Underground Services
107 79SS
Sanitary (Hatch Box) 90 days 25/9/14 23/12/14
108 29/9/14 67SS+7 days
Rain Water Tank/Sump 7 days 23/9/14
109
110 60 days 21/3/15 19/5/15
Basement Services
111 19/5/15 87
ACMV 60 days 21/3/15
112 19/5/15 111SS
Sanitary & Plumbing 60 days 21/3/15
113 19/5/15 112SS
Electrical 60 days 21/3/15
114 19/5/15 113SS
Rain Water System 60 days 21/3/15
115 19/5/15 114SS
Fire Protection, Sprinkler 60 days 21/3/15
116
117 342 days 7/2/15 8/3/16
Architecture Works
118 79FS+30 days
Brick & Block works 280 days 7/2/15 11/12/15
119 118SS+10 days
Waterproofing 280 days 17/2/15 25/12/15
120 118SS+10 days
Internal Plastering 280 days 17/2/15 25/12/15
121 127SS+30 days
False Ceiling 240 days 23/3/15 17/12/15
122 8/3/16 126SS+21 days
Timber Flooring 255 days 5/5/15
123 118SS+5 days
Door sub-frames 255 days 12/2/15 13/11/15
124 1/2/16 122SS+129 days
Door frame & Panels 100 days 15/9/15
125 118SS+21 days
Windows Frames 260 days 28/2/15 14/12/15
126 15/2/16 125SS+45 days
Windows Panels 260 days 14/4/15
127 137SS+7 days
Tiling To Kitchen, Bath 270 days 21/2/15 17/12/15
128 1/1/16 120SS+15 days
Tiling to Living 270 days 4/3/15
129 1/3/15 12/1/16 86
Rain Water Down Pipes 280 days
130 88FS+1 day
M S Railings to Staircases, a/c ledge 230 days 6/4/15 23/12/15
131 120SS+21 days
Internal Painting 250 days 10/3/15 14/12/15
132 25/2/16 127FS-50 days
Shower Screen 100 days 9/10/15
133 11/2/16 127FS-100 days
Kitchen Cabinets & wardrobes 140 days 10/8/15
134 26/2/16 133FS-10 days
Install Signages 21 days 29/1/16
135
136 351 days 14/2/15 30/3/16
M & E Services (Units)
137 19/1/16 118SS+7 days
Electrical conceal piping 300 days 14/2/15
138 9/2/16 137FS-45 days
Electrical Install Face Plate 60 days 18/11/15
139 137SS+14 days
Security conceal piping 250 days 28/2/15 30/11/15
140 19/1/16 118SS+7 days
Plumbing & sanitary piping 300 days 14/2/15
141 9/3/16 127SS+149 days
Install Sanitary Wares 180 days 20/7/15
142 19/1/16 118SS+7 days
Aircon Refrigerant & drainage piping 300 days 14/2/15
143 1/3/16 130SS+149 days
Install FCU & CU units 130 days 2/9/15
144 30/3/16 143SS+21 days
Swimming Pool 130 days 1/10/15
145 15/3/16 104FS+4 days
Installation of Lift 60 days 23/12/15
146
147 290 days 18/5/15 13/5/16
EXTERNAL WORKS
148 25/1/16 103FS+14 days
RC Flat Roof Water Proofing 21 days 28/12/15
149 4/3/16 118SS+100 days
External Plastering 240 days 18/5/15
150 1/4/16 149SS+140 days
External Painting 120 days 19/10/15
151 14/3/16 150FS-35 days
Surface Drain Grating 21 days 15/2/16
152 26/2/16 151SS-50 days
Boundary Wall 60 days 7/12/15
153 29/1/16 150SS+40 days
Tiling to Swimming Pool 35 days 14/12/15
154 29/2/16 153
Tiling to 1st Storey driveway 21 days 1/2/16
155 14/3/16 152FS-10 days
Canopy at 1st Storey 21 days 15/2/16
156 13/5/16 153
Lift Lobby Finishing 75 days 1/2/16
157 15/2/16 152SS+21 days
Landscaping 30 days 5/1/16
158
159 40 days 20/4/15 29/5/15
MOCK-UP UNIT (2nd Storey)
160 29/5/15 90SS
Type 'B' 40 days 20/4/15
161
162 37 days 12/2/16 4/4/16
TESTING & COMMISSIONING
163 2/3/16 133
Electrical, Generator Set 14 days 12/2/16
164 7/3/16 163SS+3 days
Plumbing & Sanitary 14 days 17/2/16
165 2/3/16 163SS
ACMV 14 days 12/2/16
166 2/3/16 163SS
Fire Protection 14 days 12/2/16
167 25/3/16 145
Lift 8 days 16/3/16
168 18/3/16 153FS+21 days
Swimming Pool 14 days 1/3/16
169 21 days 7/3/16 4/4/16 126FS+14 days
Water Field Test for Curtain Wall
170
171 281 days 28/5/15 16/5/16
AUTHORITY'S INSPECTION
172 15/3/16 157
HS Inspection 21 days 16/2/16
173 26/6/15 91FS+10 days
Sub- Station (Handover) 30 days 28/5/15
174 5/2/16 173FS+150 days
Power turn-on 30 days 28/12/15
175 16/2/16 164SS-14 days
Water turn-on 14 days 28/1/16
176 2/3/16 175
Post CCTV Report of Existing Sewer Line 11 days 17/2/16
177 14 days 3/3/16 22/3/16 176
Plumbing & Sanitary Inspection
178 15 days 27/6/15 11/7/15 173
MDF/SCV Inspection
179 14 days 8/2/16 25/2/16 174
Unit Electrical Inspection
180 14 days 23/2/16 11/3/16 175FS+4 days
NEA Clearance
181 28 days 3/3/16 11/4/16 166
RI Inspection M&E
182 28 days 3/3/16 11/4/16 181SS
RI Inspection Architecture
183 21 days 29/3/16 26/4/16 182FS-10 days
BCA Inspection
184 7 days 27/4/16 5/5/16 183
TOP
185 7 days 6/5/16 16/5/16 184
Handover
186
187 71 days 17/12/15 24/3/16
As-Built Drawing Submission
188 30 days 12/2/16 24/3/16 162SS
M&E
189 30 days 12/2/16 24/3/16 188SS
Architecture
190 30 days 17/12/15 27/1/16 104
C&S
Project: MASTER PROGR Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: 22/11/2013
Page 1