Document numbering & Control Procedure-Panametrics-1
Document numbering & Control Procedure-Panametrics-1
Page
Package
PEPL / 000 / II / 000 / CP / 001 0 1 of 14
PROJECT :
LOCATION :
1 Approved / Reviewed
Approval
2 Approved / Reviewed with comments as marked
Review
3 Not Approved / Resubmit
Information
4 Retained for Information / Records
Date: Name:
This approval does not absolve the Contractor from meeting their contractual
obligations of delivering a complete, safe and efficiently operating units/facilities
meeting all requirements of the contract.
DOCUMENT REVISIONS
CONTENT
1. OBJECTIVE
2. SCOPE
3. PROJECT INTRODUCTION
4. ABBREVIATION
5. RESPONSIBILITIES
1. OBJECTIVE
To define & describe the documentation procedures, Shop document numbering (i.e. QAP,
ITP, Job procedure, stage Inspection formats/reports etc.) and responsibilities of concerned
for effective document control, preparation, issue and approvals of drawings, documents etc.
2. SCOPE
This work procedure outlines and describes the document control flow procedure for
documents developed by ‘Panametrics. Document numbering as well as incoming and outgoing
correspondence & transmittals to Client/TPI.
4. ABBREVIATION
5. RESPONSIBILITIES
The Planning Manager shall be responsible for the overall implementation of this work
procedure, liaison/co-ordination with the Document controller & HOD's to ensure the efficient
control and security of all drawings & documents.
5.1 The Quality Manager shall be responsible to review the operability of the system and
Conduct assessment of the system on a regular basis.
5.2 The Construction Manager or Discipline Lead will be responsible to ensure the latest
drawings to be available at shop work location for construction.
5.3 The Planning Engineer will be responsible for the day to day activities of the
document control office including receiving, reproduction, issuing and transmitting of all
drawings and documents.
Planning Engineer will be responsible for filing and managing all original drawings
and approved documents received from Client/TPIA.
The Planning Engineer will be responsible to manage and update the Document Control
Database. All Incoming/ Outgoing letters shall be distributed (as marked by SHOP-
Head/GM) vide exclusive mail box by DC. All documents are generated by PEPL and
approvals shall be distributed (as marked by SHOP-Head/GM).
5.4 All concern Leads shall fulfil the requirement of document control and numbering
system as described below and QM shall ensure the numbering system are in place by
means of Inter department auditing as per the audit plan.
5.5 The field Engineer shall be responsible to ensure that current revisions are available/
Followed at work locations and numbering arrangements shall be followed strictly.
The general sequence of activities for control of documents from/ to PEPL will be as follows:
All documents shall be received by Planning Engineer and date of receipt shall be
mention on every document/ Cover sheet.
Planning Engineer shall maintain the Document IN-OUT register with initial of concern,
except drawings received from TPIA.
Separate register shall be maintained for Drawing/ Isometrics received from TPIL with
transmittal no., received date and E-mail date with Initial (for document received
through e-mail).
Original documents access shall be given after only getting authorization from Quality
Manager.
Any E-mail/ Letter/ Documents shall not be disclosed to TPIA, Vendor & Sub-Agency
without permission of SHOP-Head/GM.
Discipline
Document Type
Planning Engineer shall Re-submit the revised site generated documents to TPIA through
letter marked to Shop Head/GM. Discipline leads ensure that revised data shall be
clouded with revision no. nearby clouds
1
Planning Engineer to ensure to get back all old revision documents from site and
ensure update of IN- OUT register.
All obsolete documents shall be kept in designated area/ file after stamping as “VOID”.
All correspondence to TPIL/CLIENT shall be through Planning Engineer under guidance of Shop
Head/GM.
PDF copy of letters & Documents Sent/Received shall be internally distributed by DC for
information.
Flow Chart-1:-
-
Shop Documents to be prepared by PEPL
Head/GM -
Approved after Internal (Concerned Departments) & forward
Comments incorporated
CLIENT - DC
Documents. for internal review.
Documents Submit
To
CLIENT/TPIA
- DC
CLIENT/TPIA
Reviewed &
Approved copy
The fields shall be separated by Slashes only (/), Diacritical characters such as _ * % () -
.?! § And blanks shall be strictly prohibited.
Unit number shall be three digits as:
000 -COMMON
For e.g.:-
Table-1:-
PEPL Project No. Package Unit Doc. Type Serial No. Revision
(Initial)
CP- Common
Procedure
JP- Job
Procedure
QAP- Quality
Assurance Plan
ITP- Inspection
PEPL 000 II 000 Test Plan 001 & 00 & above
PQR- above
Procedure
Qualification
Record
WPS- Welding
Procedure
Specification
MS- Method
Statement
The arrangement of the Project Quality Control Forms Numbering shall be as follows:
The fields shall be separated by Slashes only (/), Diacritical characters such as _ * % () -
.?! § and blanks shall be strictly prohibited.
Unit number shall be three digits as:
000 –COMMON
For e.g.: -
Table-2:-
‘Panametri Project No. Package Unit Category Serial No. Revision
cs(Initial)
GN – General
WH – Ware House
WC – Welding
Consumable
7.3 REQUEST FOR INSPECTION (RFI) / FIELD INSPECTION NOTE (FIN) NUMBERING
The arrangement of the RFI/Field Inspection Note report numbering shall be as follows:
The fields shall be separated by Slashes only (/), Diacritical characters such as _ * % () -
.?! § and blanks shall be strictly prohibited.
Unit number shall be three digits as:
000 -COMMON
All RFI/Field Inspection Note (FIN) reports shall be arranged and maintained as per work
location indicated F – Field, for site works which covers site Inspection and S – Shop
Inspection. It shall be separate numbering for field and shop. Unit No. shall be used 000-
COMMON for all units for ease of handling (Refer Table-3). For e.g.: -
PEPL/000/S/FIN/00001…..99999, PEPL/000/F/FIN/00001 …..99999
Table-3:-
ONSHORE (INITIAL) UNIT No. INSPECTION SERIALNo
F- FIELD / FIN
PEPL 000 00001-upto- 99999
S- SHOP/ FIN
The arrangement of the Stage wise Inspection report numbering shall be as follows:
The fields shall be separated by Slashes only (/), Diacritical characters such as _ * % () -.?!
§ and blanks shall be strictly prohibited.
The serial number is the progressive number for the same kind of inspection report and
Serial numbers shall be based on FIVE digits from 00001 up to 99999 (Refer Table-5).
Work location shall be indicating as F – Field, for site works which covers site fabrication
and erection works and S – Shop, for shop fabrication and assembly works, it shall be
prefix before stage inspection (Refer Table-5).
For e.g.: - PEPL/ XX/F/PR/0001…… OR PEPL/ XXX/S/RC/0001…….
Table-5:-
DT - Document Transmittal
RFI - Request for Inspection
SQOR - Site Quality Observation Report
MQR - Monthly Quality Report
NCR- Non conformity Form/Report
QWR- Quality Walk down Report
QTBT- Quality Tool Box Talk
WPS – Welding Procedure Specification
PQR - Procedure Qualification Record
S – Shop
SPPPIR - Surface Preparation And Primer Painting Inspection Report
Refer 00001-upto-
F - Field FPIR – Finish Paint Inspection Report
PEPL Table-4 99999
TMECVR – Testing & Measuring Equipment Calibration Verification Report
DP - Deviation Permit
MRAWR - Site Modification, Rework, Additional Work Report
IMIR – Inward Material Inspection Report
DRR - Daily Receipt Report
MIV – Material Issue Voucher
MRV - Material Return Voucher
ESDRR - Excess /Short/ Damage/ Reject Report
MARF - Material Approval Request Format
EBHR - Electrode Backing and Holding Register
EQTR – Electrode Qualification Test Record
CCLS - Consumable Control Log Sheet
CIS - Consumable Issue Slip
WQT - Welder Qualification Test Record
The arrangement of the Inward Material Inspection Report numbering shall be as follows:
The fields shall be separated by Slashes only (/), Diacritical characters such as _ * % () -
.?! § and blanks shall be strictly prohibited.
Unit number shall be three digits as:
000 -COMMON
All Inward Material Inspection reports shall be arranged and maintained
PEPL/942/II/000/IMIR/00001 ………………………..999999,
UNIT No. shall be used 000- COMMON for all units for ease of handling.
It is important and mandatory to keep a clear and update Inspections Tracking System in order
to:
Monitor the implementation of the Approved Documents
Easily file and find the “Thousands Documents and Inspection issued Reports”
Make easier the Final Documentation Handover
System for box files side labelling and cover page to ease of access to the required
document and avoid searching each files. For e.g.:-
DISCIPLINE
SCOPE TITLE :
PANAMETRICS.
DOCUMENT INDEX
PANAMETRICS
DOCUMENT TRANSMITTAL
MARK TO (Name) :
DOCUMENT TRANSMITTAL NO. :
ISSUED TO (Agency) :
ISSUE DATE :
ISSUER RECEIVER
PANAMETRICS
DOCUMENT CHECKLIST
DOCUMENT NO.&
NAME :
DOCUMENT RELEASE
DATE :
PURPOSE :
RECEIVED BY
SL. NO. INITIALS/ ISSUED COMMENTS REVIEW SIGNATURE DC
DATE DATE (DATE & SIGN)
Letter register shall be maintained in soft copy only and monthly circulated to the concern
leads in prescribed format as:
A) Letter – OUT Register to CLIENT/TPIA
Sl. PEPL TPIA PEPL Letter Date Reply
No Letter Ref. Letter Ref. No. Subject
No.