Accident Case Studies On Lifting Equipment
Accident Case Studies On Lifting Equipment
Accident Case Studies On Lifting Equipment
Presented by: Dr Goh Yang Miang Assistant Director, Investigations Branch, OSH Inspectorate, OSHD, MOM
Purpose and Scope of Presentation To share accident case studies so as to: highlight possible hazards and incident sequences; highlight reasonably practicable measures that could have been done to prevent the accidents
These case studies are presented for learning and educational purposes. The case studies must not be used in any legal proceedings.
Load
Person caught in-between lifting machine and other objects Or struck by lifting machine
Struck persons/ Struck persons/ properties properties Severity Minor Moderate Major
Case Studies
Case Study 1 Truck-mounted crane overturned Case Study 2 Crawler crane overturned Case Study 3 Load fall from height Case Study 4 Person caught in-between
10
Fly jib = 16m at 5 to boom Load = 1.2-1.3 ton Initial boom angle = 60 Crane collapsed when boom angle = 50 to 52
11
12
13
Accident Analysis
Situation Lifting of debris using mobile crane Incident Sequence Possible Direct Causes
Crane overturn
Why?
ConseQuences (CSQ)
Boom Angle
Initial angle 60 Just before collapse 53 Allowable load = 1.06 ton Allowable load = 0.55 ton
15
Rear quadrant usually has higher Factor of Safety for stability than side quadrants
16
Accident Analysis
Situation Lifting of debris using mobile crane Incident Sequence Causation
Operator continued operation even though overload alarm sounded
Why?
Crane overturn
Why?
Overloaded
Why? Why?
Why?
Actual Moment condition limiter not deviated from properly calibration calibrated condition, e.g. (?) out-of-level (?)
Why? Momentum too high No system to cut-off too identify and correct unsafe late (?) habit 17
Employer/ Principal
Personsat-work
Occupier
Crane overturn
Why?
Overloaded
Require pre-lifting risk assessment and planning (run through key lifting parameters) Conduct briefing, additional test or onthe-job observations to ensure operator is competent and has safe habits Conduct frequent check on crane condition (incl. safety devices)
Supplier/ Manufacturer
Highlight limitations of safety devices to users Assist users in basic maintenance of 18 crane
19
20
10
Precast staircase = 6900kg Hook Block = 250kg Total Load = 7,150kg Safe working load based on load chart = 7,600kg
21
22
11
Cabin
Steel plates
24
12
Cabin
Fulcrum shifted
Steel plates
25
Accident Analysis
Situation Lifting of staircase using crawler crane Incident Sequence
Crawler moved out of steel plate
Why?
Causation
Crane overturn
Why?
Why?
Operator unaware
Why?
ConseQuences (CSQ)
Work pressure?
Reckless? Negligent?
26
13
Incident Sequence
Employer/ Principal
Occupier
Crane overturn
Require pre-lifting risk assessment and planning Ensure that crane are on stable grounds e.g. simple flag markers to highlight to operator edge of steel plate
Supplier/ Manufacturer
Highlight common causes of overturning to users Engineering Control - Develop new devices to control risk of overturning (ground condition detector? Edge detector?)
ConseQuences (CSQ)
Personsat-work
Follow SWPs and highlight hazards to employers Participate in identifying risk 27 controls
28
14
29
Gap widened
15
31
Accident Analysis
Situation Lifting of scrap DB using lorry crane and chain sling Incident Sequence
Breakdown Event (BE)
No maintenance regime
Why?
Causation
Why?
Why?
Lack of supervision
Lack of competency
Why?
Lack of training
ConseQuences (CSQ)
32
16
Accident Analysis
Situation Lifting of scrap DB using lorry crane and chain sling Incident Sequence
Breakdown Event (BE)
Causation
Why?
ConseQuences (CSQ)
Why?
33
Employer/ Principal
Provide training to workers that are expected to be involved in lifting work (rigger, signaller etc) Ensure that the training is effective and worker practise what they are taught on-going supervision and briefing Ensure that all lifting gears are
Recommend basic checks to determine if lifting gear is serviceable Practise according to SWP or training
ConseQuences (CSQ)
Please note that the risk control measures mentioned here are provided for 34 the benefit of enhancing workplace safety and health. Stakeholders should to review their own workplace and determine what measures need to be taken.
17
35
18
Emergency button cover not present Investigation revealed that button still working Operator should have clear view of deceased
37
Accident Analysis
Situation Operating gantry crane in precast yard Causation Incident Sequence
Why?
Why?
ConseQuences (CSQ)
Why?
19
Employer/ Principal
Occupier
Conduct risk assessment Erect barrier to ensure no one gets near to motor Yellow line to demarcate stacking zone Inspection by supervisors Briefing and training on possible hazards
Highlight inherent hazards of crane components recommend clearance from motor housing
ConseQuences (CSQ)
Please note that the risk control measures mentioned here are provided for 39 the benefit of enhancing workplace safety and health. Stakeholders should to review their own workplace and determine what measures need to be taken.
20
Conclusion
an Su ufa pp c t u lie re rs rs / Pe rs on s at w or k
41 42
pl oy ed em Se lfPr in
pi er
oy er
Em pl
cc u
ci p
al s
Duty to take, so far as is reasonably practicable, such measures as are necessary to ensure workplace safety and health
Workplace Safety and Health Act
All stakeholders should use risk management as the basic tool to help improve safety and health at workplaces.
Thank You!
21