1.1 Palm Oil Mill
1.1 Palm Oil Mill
1.1 Palm Oil Mill
0 Introduction
1.1 Palm Oil Mill
Step 5: Gasification
Advantages Significant reduction of weight and volume of sludge. The use of less oxygen results in less emissions. Syngas produced have many uses Disadvantages Expensive initial set up. Complex multi-stage process Syngas must be cleaned/purified Energy input to start reactions.
Step 6: Landfill
Advantages volume can increase with little addition of people/equipment filled land can be reused for other community purposes Disadvantages completed landfill areas can settle and requires maintenance requires proper planning, design, and operation
Gravity Thickening
Anaerobic Digestion
Chemical Coagulation
Gasification
Landfilling
6.0 Calculation
Equation used: A = Q/ HL (HL is hydraulic loading) Areq = Weight of solids/ ML (ML is mass loading) D=
4
Equation used:
BOD3 loading rate = Flow rate x BOD concentration SAl = 21.34 + 2.77 (Pin Pout) + 3.07 Aladded3+ (Snurer, 1999) Slugde age =
Equation used:
Concentration of Solid =
Water Reduction = Flow rate x (1-percentage of water residue) Filter Cake Production =Total flow rate Liquid Flow rate
29 cm 21.4 cm 10.4 mm
Equation used:
1. Height h of the nozzle plane above the smallest cross-section of the throat (dthroat = dt). h/dt = 1.15 2. Diameter (dr) of the fire box. dr/dt = 3.0 3. Diameter (drl) of nozzle top ring drl/dt = 2.3 4. Nozzle diameter (dn) Total nozzle area (An) =
2 5 4
Equation used:
Volume = L x W x D Hydraulic Retention Time =
ECONOMY ANALYSIS
Plant Specifications:
Production rate : 231,921 tons/year Efficiency : 80% Operation : 365 days/year or 7,300 hours/year (20 hours/day) Maintenance duration : 1,460 hours/year Land Price (Size) : RM 254,166 (3 acres, approx. 12,140.569 m2)
Unit (MYR)
15,000
Unit (MYR)
15,000
(MYR)
15,000 70,000
Mechanical
mixing chamber Belt filter
676 m3
20,000
20,000
20,000
0.75 m
55,750 15,000
55,750
press
Gasifier Purchased Equipment Cost (PCE) 15,000
55,750
15,000 175,750
f4
f5 f6 f7 f8 Total
Electrical
Buildings, process Utilities Storages Site Development PCE
0.10
0.15 0.50 0.15 0.05 3.25
Total Physical plant cost (PPC) PPC= PCE (1+f1+f2++f8) =MYR 175,750 (3.25) =MYR 571,187.50
Total
Fixed Capital
1.45
Fixed Capital = PPC (1+ f9+ f10+ f11) = MYR 571,187.50 (1.45) = MYR 828,221.90 @ MYR 828,222
Fixed cost
Cost Maintenance Operating Labour Laboratory costs Price (MYR) 82,822.20 584,000 116,800
Laboratory costs
Capital charges Insurance Local taxes
146,000
82,822.20 8,282.22 16,564.44
Variable cost
Main Raw Material Chemical coagulation Price (MYR/t) 573.2 5.55765 Quantity (t/year) Total (MYR/year) 3,185.65
Production Cost Direct Production Cost = Fixed Cost + Variable Cost = MYR 7,921,683 Production Cost (MYR/ton) = MYR 36.12/tons @ MYR 36.00/tons