PCCI Energy Committee - TWG On Power
PCCI Energy Committee - TWG On Power
PCCI Energy Committee - TWG On Power
Energy Security
International Energy Agency (IEA) Definition 1. Adequate 2. Affordable 3. Reliable European Commission Definition
Uninterrupted physical availability of energy products on the market, at a price which is affordable for all consumers (private and industrial)
Considering the above definition, one can say that the Philippine energy is NOT SECURED because we have been experiencing the cycle of power capacity deficiencies and high prices
2
Luzon Grid
New Power Plant Capacity added courtesy of PPAs signed in 1990s
Generation deficiency started in 2010. WESM prices reflects this first stage of power crisis. There will be generation deficiency even with BacMan rehabilitation (2012) and GNPower new 600 MW Power plant in (2013) Worst situation in 2014 Malaya and Limay Oil Thermal
LOLE Plant cannot be retired (Days/Yr) (uneconomic dispatch) 5.07 12.08 5.27 Assuming Malaya Oil Thermal Plant 82.27 will not be operated
Visayas Grid
50 MW Intermediate Plant (2017) 100 MW Intermediate Plant (2018)
Mindanao Grid
Visayas Grid had power crisis in 2009 after which Distribution Utilities signed power supply contracts with Gencos to build new power plant. Mindanao Grid is currently in crisis. Modular Diesel plants were recently procured by ECs for emergency power and power supply contracts signed to build new capacity (2015 2017). Luzon Grid will soon experience power crisis DUs signed contract only with existing plants DUs hesitated to sign power supply contract for new capacity because of threat of Open Access and Retail Competition [Concern on contracted capacity that will be stranded]
6
Power Generation is liberalized and competitive (deregulated) sector of the power industry
DOE Power Development Plan only provides outlook.
Private Generation Companies will decide what capacity, what type of plant, when and where to build power plants NPC no longer allowed to build new power plants or sign new PPA with IPPs
EPIRA in 11 Years: Plan did not convert to Plant on time Power Rates also went up instead of reduction
Lack of policy, regulation and implementation mechanism that will ensure new power plant capacity will be available on time to meet growing demand in the liberalized and competitive electricity market .
7
Luzon Grid
San Miguel 27% First Gen 20% Aboitiz 18%
PSALM 14%
Visayas Grid
Global 28% Salcon 15% PSALM 28%
Mindanao Grid
Others 2%
NPC 2% Aboitiz 6%
NPC 52%
Source: DOE
Source: MERALCO 9
25
20
15
10
0 Brunei Cambodia Indonesia Lao PDR Malaysia Myanmar Philippines Singapore Thailand Vietnam
Report of MERALCO Consultant on Subsidies: Other countries are using subsidy for strategic competitive advantage in the short term
11
20
US Cents/kWh
15
14.28
10
9.92
7.14 6.21
Lender Financing
Investor Capital
Uncontracted Demand
Long-term PS Contract
Baseload: 3-5 Years Peaking: 1-2 Years 166 Permits & Licenses
Long-Term Contract for New Capacity Short-Term Contract for Existing Capacity Competitive Electricity Market will only work if Supply deficiency is avoided
13
20 ECs in Mindanao bidded 330 MW of baseload. Signed long-term power supply contract at Php4.09/kWh requiring Genco to supply from new power generation capacity (405 MW in 2017) 12 ECs in Central Luzon bidded (October 18, 2013) 300 MW of uncontracted demand starting 2018. Genco is also required supply from new capacity. Lowest bid less than Php4.00/kWh
Lessons: Economy-of-scale, Competitive Selection Process, and Long-term contracting for new capacity!
14
Industry associations and Economic Zones to organize power supply aggregation similar to Electric Cooperatives
Minimum of 100 MW (preferably at least 300 MW) Long-term contract (at least 10 years). The longer the term, the lower the price.
Unbundled transmission and distribution wheeling fees are already in place. Hence, will require only metering, billing & settlement protocol to implement
15
Needs Liquified Natural Gas Terminals in Batangas and Bataan and Transmission pipelines to Metro Manila through the economic zones
16
DOE to mandate and oversee a regular international power generation supply bidding for DUs and large customers. ERC to use market-based rules as default in approving power supply contracts of DUs (for captive customers) with reserved price such as the prices Best New Entrant (BNE). Cost-based rules to be used only if price from competitive selection process did not achieve competitive results (i.e., higher than BNE).
2.
3.
Declare Power Projects and Fuel Exploration as National Major Strategy Programs (Shovel Ready). Streamline & shorten Permitting and Licensing
18
5.
Fastrack the establishment of ancillary reserve market and provide mechanism for transparent procurement and rules on determining optimal level required and dispatching. Fastrack Natural Gas program (e.g., accelerated PPP) and establish regulation (technical and price) to make LNG for power and industries available ASAP.
.
19
6.
7.
DOE to tighten the power program in Mindanao that would assure adequate, reliable and reasonably priced power supply and total electrification for small and large utilities and consumers. ERC to simplify and make more transparent and understandable the Rate Setting Methodology for transmission and distribution utilities.
8.
20
Ensuring Energy Security, Reliable Power Supply and Affordable Power Rates
National Engineering Center University of the Philippines Diliman, Quezon City 1101
Tel/Fax (02) 981-8500 Loc. 3014 / Fax (02) 926-1516 Email: rddelmundo@gmail.com Cellphone: (0929) 564-2772
21