Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Technical Proposal

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 24

Technical Proposal

For NEC
Jakarta - 2014

CONTENTS

1. Project Organization

2. Project Strategy

3. Implementation Schedule

4. Project Quality

5. Project Reference

6. Project Experiences
2

1. Project Organization
Project
Project
TI
TI -- PM
PM

TI
TI
Preparation

Implementation

Acquisition

Oder/Delivery

Planning

Site Access

Survey

CME

Report / Drawing

Install MW

Design Review

Comm./Integ.

Preparation

Implementation

5~9
Survey Team

5~9
Installation Team

ATP Docs
Legend :

Out of Scope
In Scope
3

1. Project Organization
Key Person ( PM, Coordinator and
Leader)

Project Manager

(Yong Bok Lee)


Project Coordinator
(Putu Eka Dharma Yhuda)
Team Leader
1. Arief Ridwan
2. Hendro Prasetyo
3. Heriyadi
4. Budiono Premaswara
5. Hidayah Aprilawati (DC)
6. Mustaqim Hardali (DC)
7. Cah Yatno (Drafter)

Curiculum Vitae

Ado be Acro ba t
Do cume nt

Ado be Acro ba t
Do cume nt

Adobe Acroba t
Do cument

Ado be Acro bat


Do cume nt

Ad o be Ac ro ba t
Do cu me nt

Ado be Acro ba t
Do cume n t

Adobe Acroba t
Do cument

1. Project Organization
Team Member with K3 Working At High
Certificates

PT Qutec Global Working At High Certificates Holder

NO

Name of Team Member

Arief Ridwan

Putu Eka Dharma Yudha

Budi Susanto

Heriyadi

Aris Darsono

Erick Estrada

Abdul Khadir Jaelani

Ahmad Hakiki

Dzaki Fahim

10

Mahyudin

11

Yaya Nursamsi

12

Aditya Prawira

13

Arief Rahman

WAH CERTIFICATES

Arief ridwan.jpg

Putu Eka Dharma Yudha.jpg

Budi Susanto.jpg

Heriyadi.jpg

Aris Darsono.jpg

Erik Estrada.jpg

Abdul Khadir Jaelani.jpg

Ahmad Hakiki.jpg

Dzaki Fahim.JPG

Mahyudin.jpg

Yaya Nursamsi.jpg

Aditya Prawira.jpg

Arief Rahman.jpg

Ichwan Maulana.jpg

Yoga Priyanto.jpg

1. Project Organization
Dimensioning (M1
~M7)

Manpower Ram up Plan

Team Organization
Project Manager (Plan)
Project Manager (Curent)
Asistent Project Manager (To be
added)
Coordinator Project (Plan)
Coordinator Project(Current)
Coordinator Project (To be added)
Survey and TI Team (Plan)
Survey and TI Team (Current)
Survey and TI Team (To be added)
Acceptance test team (Plan)
Acceptance test team (Current)
Acceptance test team (To be
added)
Target Site (Commisioning )
Target Site (Acceptance)
Target Site (Total Accumulated)

M1

M2

M3

M4

M5

M6

M7

1
1
0
6
8
(-2)
20
8
12

13

6
8
(-2)
20
8
12

13

6
8
(-2)
15
8
7
15
13

15
8
7
25
8
17
25
13

17
8
9
30
8
22
28
13

17
8
9
30
8
22
28
13

6
8
(-2)

12
13

(-13)

(-13)

12

15

15

(-1)

(800)
(800)

(1000)
(1800)

300
180
180

500
440
620

600
500
1120

600
500
1620

180
1800

1. Project Organization
Dimensioning (M1
~M7)

Manpower plan

35

Sub Project
Manager
(Plan)

30
25
20

TI Team
(Plan)

15

Accecptanc
e test team
(Plan)

10
5
0
M1

M2

M3

M4

M5

M6

M7
7

2. Project Strategy
Ramp Up Plan
M7
M6
M5
M4
M3
M2

M1
Del
ive
rab
les
Acceptance
Progress
Productivity

800
40%
20*2/Day

1000
180
440
500
500
180
60%
10%
24%
28%
28%
10%
25*2/Day 180/Month 440/Month 500/Month 500/Month 180/Month
8

2. Project Strategy
Strategy for Site
Survey
ASSIST TOOL :

SCHEDULING :

Site manager Tool


(Smartphone)
to reduce time and cost

Scheduling for nearby sites


per team per day

SITE ACCESS :
Advance Application for
Access Permit

ON SITE TRAINING :
Sample site OJT with NEC or
Operator to define SOW
clearly

Site Survey :

Up to 2 ~ 3 times
productivity increase
to initial phase within
a WK

QUALITY :
Pre-Training, On Site Self
Check List, Documentation
Inspection

RAMP UP MAN
POWER :
Worst Case 2 Sites/Team*Day,
Ready 1 Week in Advance

2. Project Strategy
Strategy for MW Implementation

SCHEDULING :

PERFORMANCE :

Scheduling for nearby sites


and cluster base

SITE ACCESS :
Advance Application for
Access Permit

H & S ASSURANCE :
Hiring qualified Eg. or train
current employee prior to
project

Support from HQ to

MW
Implementatio
n
Twice of productivity
increase within 3 WKs

QUALITY :
Rapid Exp. For ENC project.
Exact understanding of ENC
requirement.

RAMP UP MAN
POWER :
Build up enough Team
Structure to achieve Target
Date.
Based on HQ Investment

10

3. Implementation Schedule
Key Milestones and Date
M0

M1

Prepare
Survey
-7D

Start
Survey

Prepare End
TI
Survey

0 +1D

M5

+16W

Start
Install

Start
Integration

+9W

+10W

1800Sites
Team /Tool Setup
Team /Tool Setup Training
Resource ramp up
Training
accordingly

Team setup
Training / SOW define

+13W

+8W

+6W

20 team
Increasing Performance

M4

M3

M2

M7

M6
End
Install

End
Integration

+20W

+22W

+24W

1800Sites
1800Sites
Integration/PAC/RFS
ongoing

+26W

1800Sites

11

3. Implementation Schedule
Key Assumption

Potential
Resource
Technical
Delivery
Instalation

Key Assumption
- Human
- Tools
- Skill
- Material delivery when
instalation
- Delay Optimization

12

3. Implementation Schedule
Risk and Mitigation

13

4. Project Quality Control


Quality Concept
Quality Control

Project
Management

Engineering
Service

Resource
Management

TI Quality

SOW Define
Risk Manage

NPO Quality

Comm.
with
customer

Document
Quality

Quality
assuranc
e

Custome
r

Quality
Manage

Customer Satisfaction
Resourc
e
Quality

Project Acceptance
Completely Delivery
Reasonable Price

Comm.
Quality

PT. QUTEC GLOBAL


Basic quality Concept

Service
Quality

14

5. Project Reference
Project Handling List

NSN-Smartfren LTE Project


Project Name

Smartfren LTE Project

Project Scope Survey


Project
more than 300 Sites
Volume
Project Year
2014~present

At Jabodetabek and Sumatera

Huawei-XL Jupiter Project


Project Name

XL Jupiter Project

Project Scope Dismantling eks AXIS equipment


Project
more than 300 Sites
Volume
Project Year

At Sumatera area

2014~ Present

15

6. Project Experiences
Major History
Customers/ Partners
2006.07 Start Indonesia Project with Telkom
2007.03 Start Telkom, Bakrie, Indosat Project

Customers

Partners

2007.11 Start Installation Project(Indosat)


2008.03 Start 3G Project (Indosat, NTS)
2008.09 Start Telkomsel Project
2009.01 Supporting Overseas Project
2009.10 Start IBC Design and Installation
2010.04 Smartfren Optimization/ Installation
2011.01 Smartfren Sumat-Kali-Sulawesi
Optim
2012.02 Smartfren Central Java Optim/Install
2012.10 Singapore LTE RF Project
2013.01 Smartfren Sumatra Optimization
2013.04 Smartfren MW RFI Scanning
2013.05 Axis Frequency Relocation Project
2013.10 Axis Filter Installation Jawa-Bali
2014.02 XL Dismantle Sumatra Project
2014.10 Smartfren LTE Project

16

6. Experiences
Project Experience
Operator

Telkom

Mobile-8
Operator

We are providing N/W Planning, Optimization,


Installation, Acceptance test and consulting service.

Project Name

Project

Area

CDMA BTS Installation (541


site)

Installation

Divre
3,4,5,6,7

MSC Migration all of the


Indonesia (9)

Installation

Divre
1,2,3,4,5,6,7

CDMA MW/ BTS Installation


(84 site)

Installation

Sulawesi

CDMA MW/ BTS Installation


(204 site)

Installation

Java

CDMA BTS Migration

Installation

Java

MSC Migration
Project Name

Installation
Project

Java/ Bali
Area

Installation
Frequency
Migration

Java
Sulawesi

GSM Turnkey MW Survey/


Installation

MW Survey,
Installation

Sulawesi

GSM Turnkey GSM Survey/


Installation

MW Survey,
Installation

Sulawesi

EVDO2G
site
Installation
(110
GSM
2007
Frequency
site)
Migration
Indosat

17

6. Experiences
Project Experience (RNP/O)
Operator

Project Name
Phase 5 Additional Site (32
site)

Bakrie
Telecom

Telkom

Oversea

Korea

Phase 6 MW Survey/
Installation (106)
Site Audit
Telkom Java Repeater Adding
BTS Relocation
Airtel 3G BTS,M/W
Installation (66 site)
Mobitel In-Building
Installation (26 site)
SKT, KT, LGT: In-Building &
Outdoor
Voice/Video/Data Quality
Test

Project

Area

BTS, MW Installation

Bandung, WJ

MW Survey /
Installation

Bandung, WJ

Existing Site Audit

Bandung, WJ

Telkom Repeater

West Java

BTS Relocation

Kalimantan

Installation

Sri Lanka

Installation

Sri Lanka

BenchMarking Test
(by Government
Yearly test)

Korea

18

6. Experiences
Project Experience (RNP/O)
Operator

Project Name
GSM 2G Optimization

Indosat GSM

Telkomsel

Project

Area

Optimization

Sulawesi
Sulawesi

GSM 3G MOS Test

MOS Test

GSM 2G 2007 SSV


Optimization

SSV Optimization

Sulawesi

GSM 2G 2007 Cluster


Maintenance

Cluster Maintenance

Sulawesi

GSM 2G 2007 Frequency


Migration

Frequency Migration

Sulawesi

GSM Turnkey MW Survey

MW Survey

Sulawesi

GSM Turnkey GSM Survey

GSM Survey

Sulawesi

3G SSV Optimization

SSV Optimization

Sulawesi
Kalimantan

Phase 5 SSV Optimization

SSV Optimization

Kalimantan

Sumatera
19

6. Experiences
Project Experience (RNP/O)
Operator

NTS

SMARTFREN

Oversea

Project Name

Project

Area

2G Planning & Optimization

Planning

Java

3G Planning & Optimization

Optimization

Java

CDMA 1x + EVDO Rev. A


Phase 2.1

Installation/
Optimization

CDMA 1x + EVDO Rev. A


Phase
2.2 Network
Aktel Radio
Optimization

Installation/
Optimization
Optimization/
Analysis

GP Optimization & Swap


Project

Optimization/
Analysis

Bangladesh

M1 3G/LTE Optimization

Optimization

Singapore

Huawei Optimization

Optimization

Hong Kong

Airtel WCDMA Optimization

Optimization

Dialog Optimization

Optimization

Mobitel In-Building Planning

Planning/
Optimization

Mobitel WCDMA Optimization

Planning/

Central Java
Sumatra
Sulawesi
Kalimantan
Bangladesh

Sri Lanka
(by Qubicom
Lanka, Sri
Lanka
20
Corperation)

6. Experiences
Project Experience (Survey,TI, FO)
Operator
TRS
(PPC)
Angkasa Pura
Metrasat

NTS
HCPT

Project Name

Project

Area

TRS Tower, Network,


Camera
Installation

Bali, EJ

Angkasa Pura II VSAT


Installation

Internal Network

Airports

Telkomsel link connect to


Telkom II

VSAT Installation

Sumatra

Fiber Optic Network

FO Network Inner
City
Ring 1-5

Jakarta

Fiber Optic Network

FO Network HCPT-2
Core

Jakarta
Purwakarta

Sulawesi Java
Over 3,000Km

Sulawesi, EJ,
CJ,
WJ,
Jabodetabek

West Java
Over 250Km

West Java
21

PPC 1 Bali & EJ

Fiber Optic Network


Telkomsel

6. Experience
Project Experience (TI, FO)
Operator

Project Name

Project

Area
JABO

NTS

3G Frequency Relocation
Project

Frequency
Relocation

West Java
Central Java

Frequency Scanning
Filter Installation

Jakarta
Balom
Jakarta
West Java
Central Java
East Java

MW RFI Scanning
SMARTFRE
N

RFI Scanning

Balom

Medan

22

6. Experiences
Project Experience (Supply)
Operator

Project Name

Project

Area
JABO

NTS

3G Filter Supply

Filter Supply
Migration
Installation

West Java
Central Java
Balom

3G Filter Installation

3G Filter Installation

All Java

Power Supply System

Rectifier
Battery

All Java

Power Supply System

Supply & Installation

Sulawesi

Site Material Supply

Feeder & Grounding


& Etc.

Java

Power Supply System


(Rectifier)

Supply & Installation

Jabo, CJ, EJ

23

Head Office: Palma One Bld 13th Floor Suite 1390 Jl.HR Rasuna
Said Kav.X2/4, Kuningan - Jakarta Selatan 12950, Indonesia
Tel : 62-21-522 8354 (Hunting)
withdaniel@qubicom.co.kr
(Daniel Park)
24

You might also like