Performance Monitoring (PM) & Compliance Monitoring (CM) : Malaysia (DOE)
Performance Monitoring (PM) & Compliance Monitoring (CM) : Malaysia (DOE)
Performance Monitoring (PM) & Compliance Monitoring (CM) : Malaysia (DOE)
LD-P2M2 TOOLS PERFORMANCE MONITORING (PM) RECOMMENDED LIMITS MONITORING LOCATIONS FREQUENCIES
PARAMETERS/ STATUS
Sediment Basin / Trap Turbidity *50 NTU • In the plant operation (Point 1) Every day or after rain event (in-situ).
Total Suspended *50 mg/l • 50 meter out from the plant Take photo.
Solid (TSS) Sediment level (Point 2)
• 200 meter (point 3) out from
point 2
• 1 km meter (point 4) out from
Perimeter Drain Performance - point 3
• Residential area
Earth Drain with Check Dam -
Quarterly
Sediment level
Wash Trough -
Temporary or permanent Structure and Performance -
waterway crossing
(culvert/bridge
Note:* National Water Quality Standards for Malaysia (NWQS), Department of Environment,
Malaysia (DOE).
Activity Regulated Parameters Applicable Standards Monitoring Locations Frequencies
*** Water Quality Total Suspended Solids (TSS) 50 mg/L Twenty (20) points
pH 6.0~9.0
Turbidity 50
* New Malaysia Ambient Air Quality Standard, Department of Environment Malaysia (DOE).
** The Planning Guidelines for Environmental Noise Limits and Control, Schedule 1, Department of
Environment Malaysia (DOE).
Impact Monitoring (IM)
Impact Monitoring Parameters Monitoring Locations Frequencies
pH
Ammoniacal Nitrogen (NH3-N)
Nitrogen (N)
Phosphate (P)
Potassium (K)
* New Malaysia Ambient Air Quality Standard, Department of Environment, Malaysia (DOE).
** The Planning Guidelines for Environmental Noise Limits and Control, Schedule 1, Department of
Environment, Malaysia (DOE).
*** National Water Quality Standards for Malaysia (NWQS), Department of Environment, Malaysia
(DOE).
The Main Stages of Cost- Benefit Analysis
Define the decision what technology used
Economic Cost
Existence Value of Habitats such as Terrestrial $32-$122 per household per year