SMED is Continuous Improvement
Look Familiar ?
7
Identify what types of internal and external setup & times are involved in the
following pictures.
Picture A: Wire Cutting Machine Picture B: Metal Stamping Machine
Think Break
Internal External
____________ ____________
____________ ____________
____________ ____________
Defective tooling,fixtures,
setup instruments are
noticed after the machine is •The operator notices that equipment is
missing after internal setup has begun.
turned on.
10
5 “Traditional”Setup Steps Defined
Preparation - Ensures that all the tools are working
properly and are in the right location.
Mounting & Extraction - Involves the removal of the
tooling after the production lot is completed and the
placement of the new tooling before the next
production lot.
Establishing Control Settings - Setting all the process
control settings prior to the production run. Inclusive of
calibrations and measurements needed to make the
machine, tooling operate effectively.
First Run Capability - This includes the necessary
adjustments( re-calibrations, additional measurements)
required after the first trial pieces are produced.
Setup Improvement- The time after processing during
which the tooling, machinery is cleaned, identified, and
tested for functionality prior to storage.
11
Think Break Examples of wastes in a traditional setup !
What kind of “setup wastes” can you identify in this pictures ?
________________________________________________________
________________________________________________________
________________________________________________________
12
One Step Setup
Implementation
Plan
Separate Internal
from External Progressive
Reduction of Setup
Setup Enhancements Processes
Optimizing Setup
Integrate Internal into
Processes
External Setup
Step 6
Verification / Standardization
13
Phase 2 Combining equipment functionality
15
Phase 3: Reducing setup Elimination of Bolts &
processing time. Adjustments.