Project Plan For Abc Project: by Priyanka Choudhary
Project Plan For Abc Project: by Priyanka Choudhary
Project Plan For Abc Project: by Priyanka Choudhary
”
Project Manager : Priyank Choudhary
Project Plan for ABC Project BA :BA Name
Delivered By : Internal team
ABC Project is an a global web application to manage ITD CPP (Customer facing) projects from creation to closure at one place. Being part of the Escape Notes redevelopment Sponsor : Sponsor ABC
program, ABC application will retain existing functionalities from PWB Lotus Notes application, allow enhanced features and realign to CPP terminology and methodology Capability : Solution Centre Mgmt
23%
JIRA:
Baselined: 9-Apr-18 Baselined: € 110K+ 143.1KK Defects: 0 Open, 807 Closed box:
Schedule Cost Quality
Revised: NA Consumed: € 111K+ 108.8K CRs: 35 Closed
Gates O D C
Planned
Definition Demo
Go-Live
Initiation SteerCo-1
Sprint 1
Comple
Demo
te
Tuning Demo
UAT
Delayed
Certification
Soln Release
Hyper Care
Deployment Deployment to QA
Sprint 1 - Tests QA tests
Sprint 1 - Bug fixing Defect fixes
Deployment (bug fixing)
Daily stand -ups 15 minutes of project team
Meetings
Project status Update
Backlog re-prioritization for Sprint-
2
Sprint 2
SPRINT 2
Module Activities Dependencies
6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov
Open Projects Landing page
Open Project details Page.
(extended)
Order List and Details View +
History
Search and sort
Create 'new order" form
Order Metrics page
Open Projects Customer Info (extended)
Action-"View /Edit"
Action-"Save", "Cancel"
Project Team
Action items
Issues
Email template
History
Back office landing page
User and Access Mgt-Add,
Remove, Edit
Configurations Keywords
Admin
History - Approvers + Keywords
History- User and Access
Management
Export to Excel
Defect Fixes
Proposed Project History
Depolyment to QA QA deployment
Sprint 1– Test QA tests
Sprint 2 –Demo Readiness Check Defect fixes
Sprint-2 Demo to business Live Demo
Daily stand -ups
Meetings
Project status Update
Sprint 3
SPRINT 3
Module Activities Dependencies
20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 27-Nov 28-Nov 29-Nov 30-Nov 1-Dec
bFO API integration API integration for manual Opportunity ID Resource Name 1
To fetch Oracle PA details
Oracle PA API integration Form creation
History RN 1
Lessons Learned- List Page, Detail Page, Soft Delete
and History RN2
Open Projects Changes -List Page, Detail Page, Workflow , Soft
Delete and History RN3
Change Requests
Lessons Learned
Issues
Views Action Items
Risks
Project Survey
Oracle PA
All (open/closed/proposed/change
requests/issues/action items/risks/lessons learned)
Issues
Risks
Action Items
Oracle PA
History
Change Requests
Opportunity Details
Lessons Learned
Project Team
To fetch Oracle PA details
Oracle PA API integration
History
Defect Fixing from Sprint-3 Fixing prioritized defects from previous Sprints
Depolyment to QA QA deployment
Sprint 3- system Testing QA retest of fixed defects
Test cases for Sprint-4 Writing test cases for Sprint-4
Sprint 4 –System testing Test all scenarios for Sprint-4
Sprint-4 Demo to business Live Demo
Sprint Planning
Meetings Daily stand -ups
Project status Update
Sprint 5
SPRINT 5
Module Activities
18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec
bFO Mailbox Proposed project creation through bFO
Modification in the Oracle PA form to accommodate Edit
Oracle PA requirement
Orders
History Project Milestones
Risks
Project Survey
Views
BackOffice-All Docs(open/closed/proposed/change
requests/issues/action items/risks/lessons learned)
Frontoffice- Add, Rename , Delete folders/subfolders
Back Office- Add, Rename , Delete folders/subfolders
Sub-folder creation
Box structure Back Office- set up Folder structure for different application centers
Portfolio Basic Report
Opportunity Audit
Workload Model Report
PWB Reports
Accepted Projects Report
Change Order Report
Contingency Report
Help
Admin Back Office Access Levels for Oracle PA, Box, Risks, Back Office
Email Template
Pop-Ups Pop - up on Navigation
Sorting Sorting of Projects (Open, Proposed, All, closed)
Open Projects Advanced Filter
CPP Gate questions
soft Delete and Restore
Project Milestones Project Ticker Logic
Data Migration
Defect Fixing from Sprint-4 and Sprint-5 Fixing prioritized defects from previous Sprint and current sprint
Depolyment to QA QA deployment
Sprint 5- system Testing Test all scenarios for Sprint-5
Test cases for Sprint-5 Writing test cases for Sprint-5
Sprint-5 Demo to business Live Demo
Sprint Planning
Meetings Daily stand -ups
Project status Update
Sprint 6
SPRINT 6
Module Activities
3-Jan 4-Jan 5-Jan 6-Jan 7-Jan 10-Jan 11-Jan 12-Jan
bFO mailbox integration bFO mailbox integration- creation of new proposed project entry
ACL Third Party, Related Projects, Contingency, Risks, Reports
BOX Backoffice Add and Delete Folders/sub folders
BOX Attachments Project Milestones,
Orders,
Changes,
Lessons Learned,
Issues,
Action items,
Risks
CH 18 Notes Section--Link that opens a pop-up which allows user to type in data.
System will automatically save this data. (Rich text format) system should also
provide a history of people who edited and when they edited
CH16 Show hide- Add "Select all" option in show hide functionality
Defect Fixing from Sprint-5 and Sprint-6 Fixing prioritized defects from previous Sprint and current sprint
Depolyment to QA QA deployment
Sprint 7- system Testing Test all scenarios for Sprint-7
Test cases for Sprint-7 Writing test cases for Sprint-7
Sprint-7 Demo to business Live Demo
Meetings Sprint Planning
Daily stand -ups
Project status Update
Tuning phase
SPRINT 6-7
Module Activities
1-Jan 2-Jan 3-Jan 4-Jan 5-Jan 8-Jan 9-Jan 10-Jan 11-Jan 12-Jan
PWB Reports Workload Model Report
Change Order Report
Contingency Report
Pop-Ups Pop - up on Navigation
Open Projects Advanced Filter
Project Survey
Views
Templates
Third Parties- add, delete, edit
Related Projects
P2 and P3 requirements Support Request details
In- App Notifications
Project survey
Supplier Invoice and View
can be
Mass Update of Project Managers removed
Creation of sub-project, Edit and Workflow
Sub project (TBD)
Data Migration
Tender
Complete application filter
Stats for Open project
Sub region