Financing PPP Projects
Financing PPP Projects
Financing PPP Projects
PARTNERSHIPS (PPPs)
Francis Can
MBA, PMP, FCCA, CPA(K), CPA(U),
CIPS(Cert), Prince2, BSc(Ed), PgDIMA
fcan1961@gmail.com
Tel: 256 772 989401
FINANCING PPP PROJECTS
2
22
4. FINANCING PPP PROJECTS
4.1.1 What is project financing?
PPPs in infrastructure are normally financed on project basis (as opposed to
corporate financing).
This refers to financing in which lenders look to the cash flows of an
investment for repayment, without recourse to either equity sponsors or the
public sector to make up any shortfall.
Advantages:
reduces/isolates the financial risk of investors;
more careful project scrutiny, risk analysis leading to change in project
structure, reduction in level of risk and more appropriate allocation of risks
between parties.
Disadvantages
more complex transactions than corporate or public financing;
higher transaction costs (the due diligence process conducted by parties
results in higher development costs, which could be up to 5-10 per cent of
project value);
protracted negotiation between parties;
requirement of close monitoring and regulatory oversight (particularly for the
3
33 potential expostulate guarantees).
4.1.2. Sources of Finance
Lenders of debt capital have senior claim on income and assets of the
project. Generally, debt finance makes up the major share of investment
needs (usually about 70 to 90 per cent) in PPP projects. The common
forms of debt are:
Commercial loan
Bridge finance
Bonds and other debt instruments (for borrowing from the capital market)
Subordinate loans
Commercial loans are funds lent by commercial banks and other financial
institutions and are usually the main source of debt financing.
Bridge financing is a short-term financing arrangement (e.g., for the
construction period or for an initial period) which is generally used until a
long-term financing arrangement can be implemented.
Bonds are long-term interest bearing debt instruments purchased either
through the capital markets or through private placement (which means
direct sale to the purchaser, generally an institutional investor.
Subordinate loans are similar to commercial loans but they are
The other sources of project finance include grants from various sources,
supplier's credit, etc.
Government grants can be made available to make PPP projects
commercially viable, to reduce the financial risks of private investors, and to
achieve socially desirable objectives such as to induce economic growth in
lagging or disadvantaged areas.
Many governments have established formal mechanisms for the award of
grants to PPP projects. Where grants are available, depending on
government policy they may cover 10 to 40 per cent of the total project
investment.
6
66
4.1.3 Financing Choice
PortfolioTheory
Options Theory
Equity vs. Debt
Type of Debt
Sequencing
7
7
1) Financing Choice: Portfolio Theory
Combined cash flow variance (of project and sponsor)
with joint financing increases with:
Relative size of the project.
Project risk.
Positive Cash flow correlation between sponsor and project.
Firm value decreases due to cost of financial distress
which increases with combined variance.
Project finance is preferred when joint financing
(corporate finance) results in increased combined
variance.
Corporate finance is preferred when it results in lower
combined variance due to diversification (co-
insurance).
8
8
2) Financing Choice: Options Theory
9
9
Financing Choice: Options Theory
10
10
Financing Choice: Options Theory
11
11
3) Financing Choice: Equity vs. Debt
12
12
4) Financing Choice: Type of Debt
Bank Loans:
Cheaper to issue.
Tighter covenants and better monitoring.
Easier to restructure during distress.
Lower duration forces managers to disgorge cash early.
Project Bonds:
Lower interest rates (given good credit rating).
Less covenants and more flexibility for future growth.
Agency Loans:
Reduce expropriation risk.
Validate social aspects of the project.
Insider debt:
Reduce information asymmetry for future capital providers.
13
13
5) Financing Choice: Sequencing
14
14
4.1.3. The Viability Gap Funding Scheme
15
15
15
4.1.4. Main Providers of PPP Finance
17
17
17
4.1.4. Potential Funders
18
18
18
4.2 Due diligence
19
19
19
20
20
20
4.3. Financial structure
Why financial structures matter?
Careful analysis of alternative financial structures is required to
establish the right financing structure for a project.
As the expected return on equity is higher than the return on debt,
the relative shares of debt and equity in the total financing package
have important implications for the cash flow of the project.
Their relative share is also important for taxation purposes.
Generally, the higher the debt, the lower the tax on return.
However, a higher proportion of debt, requires a larger cash flow for
debt servicing, which can be problematic, especially in the early years
of project operation when revenues are generally low.
This is often the case in transport and water sector projects, which
implies high risks of default.
21
21
21
4.4 Cost of Capital
22
22
22
Cost of Capital
Risk is an important element which is factored in to determine the
cost of debt and equity. Interest rate charged by lenders will
depend on the level of risk they estimate for the project.
The higher the risk perceived, the higher the interest rate will be
(interest rate can be decomposed as the sum of a risk free rate -
practically the rate at which government can borrow money from
the market - to which a risk premium is added).
Similarly, the cost of equity is defined as the risk-weighted
projected return required by investors and is established by
comparing the investment to other investments with similar risk
profiles.
Government regulators need to consider the cost of capital when
determining the appropriateness of tariff levels.
Ideally, the Internal Rate of Return of a project should be equal to
its cost of capital. If IRR is greater than the cost of capital, the
concessionaire/investor makes excess profit, and if the IRR is less
than the cost of capital, the concessionaire/investor loses money
23
23
23
and may even go bankrupt.
Cost of Capital
Why the debt - equity ratio matters
Usually, banks will be more comfortable to lend to an
entity which has a higher share of equity as it makes the
project safer while investor will try to reduce equity
investments to the minimum to increase their potential
return through higher leverage.
How the cost of capital can be lowered
The cost of capital of may be lowered through refinancing
of PPP projects after their construction phase.
Sponsors may be required to provide a significant amount
of equity capital at the beginning of a project during the
construction phase when the risk is high.
Once the construction is complete, the construction risks associated
with it have been overcome, and the cash flow begins to materialize,
the expensive equity or debt capital can be refinanced using cheaper
24
24
24 debt capital thus lowering the total cost of capital.
Cost of Capital
26
26
26
Part 4: Specify the outputs
27
27
27
Cash Flows Components
28
28
28
Components of a cash flow model
The capital investment is the cost of developing a project,
regardless of funding sources. Typical components of capital
investment cost are: land and site development costs, buildings and all
civil works, plant and machinery, and technical, engineering and other
professional service fees.
The terminal cash flow is the cash that is generated from the
sale or transfer of assets upon termination or liquidation of the PPP
contract tenure. In the case of a PPP project, the residual or
transfer price is generally negotiated and included in the contract
agreement.
The discount rate is the rate that is used to calculate the present
value of future cash flows. It is often the weighted average cost of
capital for the project from different sources.
In order to calculate the future cash flows, it is also necessary to make
assumptions for important parameter values over the project's life. The
main parameters for which values need to be assumed include:
interest and inflation rates, the pricing mechanism, demand for the goods and
services produced by the project, construction time, debt repayment method,
depreciation schedule, tax structure, and physical and technological lifetime of
29 assets.
29
29
Effects of Subordinate Debts
Revenue: $1,050
30
30
30
Subordinate Debts
On a combined claim (if the whole amount of loan was of the same type,
i.e. senior debt), the coverage ratio is 1.17, which in most circumstances
would be considered low and not qualify for cheaper credits. The
coverage ratio, however, is significantly improved if the debt is divided
into two parts: a senior debt and a subordinate debt. As the senior debt
is only a portion of the total debt and has the first claim on all the
revenues available for debt service, its coverage is increased to 1.5 and
its credit quality would be enhanced. The credit quality is very important
to debt financing. With a good credit rating the project may find cheaper
debt financing.
The availability of subordinate debt helps in reducing the risk to senior
debt lenders and allows the project sponsor to borrow at lower interest
rates. The subordinate debt provider, however, absorbs a share of the
risk if revenues fall short of debt service requirements.
Because of this feature of subordinate debt in reducing the monetary
cost of debt, some governments provide loans to implementing agencies
(under public credit assistance programmes) to improve the credit
quality of senior debt. It lowers the risk to lenders and helps the
implementing agency to obtain loans at a lower interest rate reducing
31 the debt burden on the project.
31
31
4.6. Financial Indicators
A number of financial indicators are used to assess
the financial viability of a project and alternative
financial structures for its implementation. Some of the
main indicators include:
Return on Equity (ROE)
Annual Debt Service Coverage Ratio (ADSCR)
Project Life Coverage Ratio
Payback period
Net Present Value (NPV)
Financial Internal Rate of Return (FIRR)
These are explained next:
1) Return on Equity. The net income earned on an
equity investment. It measures the investment return on
32
the capital invested by shareholders and should not be
32
32
less than the expected return on equity.
4.6. Financial Indicators
36
36
36
4.8. Compensation to project sponsor/developer
38
38
38
Land readjustment
Land readjustment is a comprehensive technique for urban
area development that provides network infrastructure and other
utility facilities and amenities in an integrated manner together
with serviced building plots.
This approach is also known as land pooling or reconstitution of
plots. It may be undertaken by a group of landowners or by a
public authority.
In this method all the parcels of land in an area are readjusted
in a way that each land owner gives up an amount of land in
proportion to the benefits received from the infrastructure which
is determined on the basis of the size and location of each site.
The provision of public facilities enhances the land value and a
sound urban area is created.
The land contributed by the landowners is used to provide
community facilities and amenities and can also be sold or
leased out to meet the project costs including those for the
infrastructure.
39
39
39
3) Cross-subsidization in PPPs
PPPs can be designed based on cross-subsidization between
project components, when excess revenues generated from one
component can be used to compensate the shortfall in another
component in order to make the whole project commercially
self-sustainable.
The rail-property development model used in Hong Kong, China
is a good example of such an arrangement. In this model, part
of the profit made from real estate development on lands at or
close to station areas, and along the right-of-way of rail transit
routes is used to partly finance the rail system.
A differential pricing policy with the objective of cross-
subsidization may be adopted in an urban utility service project.
For example, the industrial and commercial users of a water and
sanitation project in Tirupur, South India pay a higher price for
water to subsidise the residential users who are charged much
lower than the actual cost of water.
40
40
40
4) Government buys the service
on behalf of the beneficiaries
The government can make payments of periodic fixed amount or
according to use of the facility, product or service at a
predetermined agreed price. This type of arrangement is
common for social infrastructures such as school, hospital and
other public buildings.
Shadow tolling of roads is another example. Shadow tolls are
payments made by government to the private sector operator of
a road, at least in part, based on the number of vehicles using
the road.
Shadow tolling is practiced in the U.K. However, instead of
shadow pricing, the government may also make payments of
periodic fixed amount, as the National Highway Authority (NHAI)
in India pays for their PPP projects implemented under the
"annuity model".
41
41
41
5) Why grants may be considered
Grants and subsidies by the government, if available,
can be used to finance in part. Such grants and
subsidies can be justified on the following grounds:
To meet public service obligations (PSOs)
To achieve social objectives (for example, to
ensure no body is priced out in a water project)
To rectify market imperfections (that create
externalities)
To make economically viable and socially desirable
projects commercially viable
The size of government support should depend on
what extent a particular project may qualify for such
grants and subsidies considering such grounds.
42
42
42