LOTO: Lockout Tagout: & Tryout Procedure
LOTO: Lockout Tagout: & Tryout Procedure
LOTO: Lockout Tagout: & Tryout Procedure
Prepared by:
Sain Dino Latki
Objective and scope
This procedure establishes the minimum requirements for the
lockout of energy isolating devices whenever maintenance or
servicing is done on machines or equipment. It shall be used to
ensure that
The machine or equipment is stopped,
Isolated from all potentially hazardous energy sources.
Locked out before employees perform any servicing or
maintenance where the unexpected energization or start-
up of the machine or equipment or release of stored
energy could cause injury.
Fundamental Purpose
• Safeguard employees.
• Effective coordination.
LOTO:
To make sure that Electrical lockout / tag out & tryout procedure is
followed whenever a Maintenance / Electrical job is to be carried
out on equipment which requires Electrical Isolation.
Responsibilities
Overall responsibility of the Lock Out / Tag Out & Try Out
procedure lies with the area owner to ensure that all jobs are
carried out only after proper locks & tags have been applied.
Responsibilities
Locks will be installed by all work permit signing authorities (Departments) in
case of equipment requiring Lockout / Tag out & Tryout Procedure.
Only AM / Team Leader of Issuing area is allowed to write / fill the work permit as
per input / discussion with the maintenance person.
Electrical energy is a good servant but a
bad master if handled carelessly.
?
THANK YOU!