Esra Aleisa: Chapter Four - Students
Esra Aleisa: Chapter Four - Students
Esra Aleisa: Chapter Four - Students
Esra Aleisa
The work of the project can be successively
subdivided into smaller and smaller work
elements.
The outcome of this hierarchical process is
called the work breakdown structure
(WBS).
The five generic steps described herein provide a
structured approach for collecting the project
information necessary for developing a work breakdown
structure.
for example, testing complete and finished by July 1 of the same year
• Milestones should be natural, important control points in the
project.
• Milestones should be easy for all project participants to
recognize.
Technical Specifications
Survey
A project is ready to go
Scope creep can have a positive or negative effect on the project, but in most
cases scope creep means added costs and possible project delays.
Priorities
One technique found in practice that is useful for this purpose is completing
a priority matrix for the project to identify which criterion is constrained,
which should be enhanced, and which can be accepted:
Basically, the WBS is an outline of the project with different levels of detail.
Use of the WBS provides the opportunity to "roll up" (sum) the budget and
actual costs of the smaller work packages into larger work elements so
that performance can be measured by organizational units and work
accomplishment.
The WBS can also be used to define communication channels and assist in
understanding and coordinating many parts of the project. The structure
shows the work and organizational units responsible and suggests where
written communication should be directed. Problems can be quickly
addressed and coordinated because the structure integrates work and
responsibility.
It is not necessary to divide all elements of the WBS to the same level.
Each work package of the WBS should be as independent of other packages
of the project as possible.
A work package manager is responsible for seeing that the package is completed on time,
within budget, and according to technical specifications.
Practice suggests a work package should not exceed 10 workdays or one reporting period.
If a work package has a duration exceeding 10 days, check or monitoring points should be
established within the duration, say, every three to five days, so progress and problems
can be identified before too much time has passed.
For large, complex projects, the people responsible for the major
deliverables are likely to meet to establish the first two levels of
deliverables. further detail would be delegated to the people
responsible for the specific work. Collectively this information
would be gathered and integrated into a formal WBS by a project
CresautiipnpgotrhtepWWersoorkn.Breakdown Structure > work packages
review
The five generic steps described herein provide a
structured approach for collecting the project
information necessary for developing a work breakdown
structure.