Pom Notes Latest
Pom Notes Latest
Pom Notes Latest
BY Mrs P HOVE
TOPIC ONE
INTRODUCTION TO POM
Production Def
random
Inputs fluctuations
• Land Outputs
• Labour Adjustment Conversion Monitor o • Goods
needed output
• Capital process • Services
• management
Comparison:
Actual vs Desired
FEEDBACK
• The creation of goods or services involves
transforming or converting inputs into
outputs.
1. Process Planning
• The determination of where each operation
on a component part/ assembly is to be
performed results in a route for the meeting
of a manufacturing lot through the factory.
• There is need to plan the route to be taken.
2. Loading- Once the route has been established
the work required can be loaded against the
selected machine or workstation. The total
time required to perform the operation is
computed by multiplying the unit operation
times given on the standard process sheet by
the number of parts to be processed.
-This total time is then added to the work
already planned for the work station. This is
the function of loading and it results in a
tabulated list or chart showing the planned
utilization of the machines or workstation in
the plant.
3.Scheduling- Scheduling is the lot of the
planning functions it determines when an
operation is to be performed or when work is
be completed, the difference lies in detail of
the scheduling procedure.
• In centralized control situation where all
process planning loading and scheduling for
the plant are done in a central office. The
details of the schedule may specify the
starting and finishing time for an operation.
On the other hand the central schedule may
simply give a completion time for the work in
a given department
4. Combining Functions-While it is easy to
define ‘where’ as a process planning, ‘how
much work ‘as loading and when as
scheduling in actual operations these three
functions are often combined and performed
concurrently. How far in advance routes loads
and schedules should be established always
presents an interesting problem
• Obviously it is desirable that a minimum of
changes be made after schedules are
established. This objective can be approached
if the amount of work scheduled for the
factory or department is equal to or slightly
greater than the manufacturing cycle. For
optimum control, it should never be less than
the manufacturing cycle.
• Dispatching: Authorizing the start of an
operation on the shop floor is the function of
dispatching. This function may be centralized
or decentralized.
-Again using our machine shop example , the
departmental dispatcher would authorize the
start of each of the three machine operations-
those dispatch actions based on the foreman’s
routing and scheduling of the work of his
department. This is decentralized dispatching.
• Corrective action- This is the keystone of any
production planning and control activity. A
plant in which all manufacture activity runs on
schedule in all probability is not being
scheduled to its optimum productive capacity.
With an optimum schedule, manufacturing
delays are the rule, not the exceptions.
Factors affecting PP C
• Capacity
• Type of products produced
• Skilled Labor
• Availability of resources
• Legislation
Importance of Production Control
1. With the help of production and contoll the
activities of various departments are
coordinated with the help of feed back taken
from them.
2. Quality products are produced
3. It is possible to complete orders within
required time and also with less wastages.
Cont.
4. Accountability and responsibility become
more or less fixed.
5. It is possible to meet specifications.
6. Minimum investment in inventory
7.Cost production should be reduced.
8. Elimination of risky areas.
Components of Production Control
1. Control of activities
Production activity control is concerned with
converting plans into action, reporting the
results achieved ,and revising plans and
actions in order to achieve desired results.
- Thus PAC converts plans into action by
providing the required direction.
- This requires the appropriate prior master
planning of orders ,work of personnel,
materials and capacity requirements.
2.Control of inventories
-Control the wastage of inventories and
movement of inventories at shop flow.
3. Control of resources
- Optimal use of resources that is the
maximum utilization of equipment, tools and
manpower.
4.Control of management information system
- Channeling the information through proper
channels. It is the responsibility of the control
department to collect the information about
deviation of actual from standards and
provide this information to the management
for taking corrective action.
Instruments for the Control System
• Sales Order- It is a rewrite of the customer
order specifying what has been purchased-
product and quantity and authorizing
shipment of the goods to the customer.
Multiple copies are prepared and all
interested functions are furnished a copy.
Sales order may be written by marketing,
inventory control or production control.
• Stock Order
• Shop Order
• Requisition form
• Payment voucher
• Job cards
• Stock sheets
Techniques of Production Control
• In order to continually monitor the progress of
implantation, many control techniques are
applied.
1) Gantt Charts
The chart is used to organize and clarify actual
or intended use of resources within a time
framework.
It portrays planned production and control
variables that require planning and control.
• It is a rectangle chart divided by horizontal
and vertical lines generally time is represented
horizont6ally with scheduled resources listed
vertically.
• There is a load chart and a schedule chart.
• A load chart displays the loading and idle
times for machines or departments.
• This shows when certain jobs are scheduled to
start and finish and where idle time can be
expected.
• Whereas a schedule chart is used to monitor
job progress.
Cont.
• Gantt chart offers the advantage of ease and
clarity in communicating important
information.
• Gantt chart often shows who is responsible for
what task.
• It helps monitor progress as the production
will be going on.
• It gives a clear illustration of the production
status.
However
• The Gantt chart does not account for the
vagaries of equipment including breakdowns
and human performance.
• Gantt chart emphasize time rather than task
relationships.
• Gantt chart does not indicate task
dependencies that is you can not tell how one
task is falling behind schedule affects other
tasks.
Topic Four
Product Design
Understanding and Meeting
Customer requirements
- The foundations for long term success in any
type of operation can be established on the
basis of a synergistic relationship between
marketing, design and operations of an
organization.
- Good integration between these groups is
important
- Product development should be an interactive
process whereby the customer and marketing
sales product service designers purchasing
suppliers and production team work together
to develop a product that meets customer
expectations and can be generated or
produced economically.
Product Development
• Products can be developed in an organization
using one of the following ways:
Traditional Sequential Product Development
-It is a sequential process. Each member
believes the other is incompetent
-It is divided separate functions whereby:
1 Marketing passes the requirement to the
product.
2 The designers believe the requirements are
unrealistic with regard to available technology
or resource, alter the requirement and design
a product to meet the corrected market
analysis.
3 The designers pass the new product to the
process designers and purchasing.
4 The process designers believe the product
designers do not understand the real world.
They try to correct the product design so that
they it can be produced.
5 Purchasing interacts with suppliers who
indicate problems with the design and they
work with the suppliers to correct it.
6 The suppliers are contracted to be produced
what will meet the needs of the new designs
economically.
7 Operations receive the process design and the
purchased materials which all have to rush
into production whilst designing the product.
8 Operations change the market analysis and
product.
9 In a manufacturing company production past
the first few products to sales.
10 Sales receive with the product a suggested
selling price and a forecast from marketing.
• Investigations then bounce from one barrier
to another with responsibility and
accountability for the product service being
denied, unrealistic goals being claimed and
little or no feedback being given and nothing
being generated.
• In theory this approach should have led to an
understanding of the customer requirements
through the market analysis but the customer
is not really part of the traditional product
development process.
• The length of time from the initial market
analysis to the first sales is too long such that
the analysis is often invalid therefore it will not
surprise that the product does not meet the
requirements.
• The entire product development process is re-
started at each phase creating time consuming
and consuming and expensive duplication.
• Friction between departments will not be
avoided.
.
• Design is the translation of requirements into
a form suitable for all operations and
production.
• The design functions is in between marketing
and the operations functions
• Its purpose is to take the needs of the market
and translate them into that they can be
satisfied within the operating unit. The
decisions taken during the design stage can
have significant and very long effect upon the
whole organization eg a poorly designed coat
will never coat well it is made.
•
DESIGN PROCESS AND SYSTEMS
• In every project the design program will pass
through the five stages.
• 1) Conception – when a draft specification for
the product / service is laid down encoorating
the user requirements.
• It is the most important in providing the basis
for control of all subsequent design activity. A
specification must be drawn up in as much
detail as possible by marketing in discussion
with the customer and the customer and the
design group.
• The following is the minimum information that
should be given on a design specification
1The technical or performance requirements
including explicit statements on quality and
reliability.
2 Any appearance or styling requirements
3 The intended d selling price or operational cost
4 The date when product must be available.
5 The probable quantity or service usage that
will be required.
6 The max cost of designing which can be
accepted since the final products must bear
the cost of the design.
7 Information concerning any special safety legal
or quality features required by current
legislation
2) ACCEPTANCE
• Is where specification is shown to be
achievable
• It is here that tradeoffs better requirements
and achievability are made explicit and
resolved
• It is usually the 1st stage where costs for the
design work will be assigned directly to the
project.
• The draft specification is tested and when
accepted rejected or impracticable, or
modified in conjunction with marketing.
• It is important for the designer to know the
capability of the operating unit which will
carry out the final design.
3) EXECUTION
»Productivity
• Productivity is the ratio of the outputs (goods
and services) divided by the input (resources) (
such as labour and capital)
• The operations manager’s job is to enhance
the productivity ratio of outputs to inputs
• Improving productivity means improving
efficiency
• Efficiency can be improved by reducing inputs
while keeping output constant or increasing
output while keeping inputs constant.
• Measurements of productivity is good way to
evaluate a country’s ability to provide an
improving standard of living for its people
• Productivity = units produced
Input use
•
• Productivity is a common measure of how well
a country, industry or business unit is using its
resources or factors of production.
• Productivity measurement is fundamental to
understanding operations –related
performance
• Productivity is a relative measure i.e. it needs
to be compared with something else
• Comparisons can be made in two ways. A
company can compare itself with similar
operations within its industry. Or it can use
data when such data is available eg comparing
productivity among the different stores in a
franchise.
• Another approach is to measure productivity
over time within the same operation ie
comparing our productivity inone time period
with that of the next.
Factors affecting Productivity
Capital investments in
production/technology/equipment/ facilities.
e.g. Automatization & Computerization (minimizes tasks
performed by employees).
Workforce knowledge and skill
Social environment. Making employees comfortable +
work methods.
Quality of
products/processes/management
Geographic factors
201
PROCESS FLOW STRUCTURES
• A process flow structure refers to how a
factory organizes material flow using one or
more of the process technologies listed below.
• Job Shop- Production of small batches of a
large number of different products most of
which require a different set or sequence of
processing steps.
• Commercial printing firms, airplane
manufacturers, machine tool shops and plants
that make custom – designed printed circuit
boards are the examples of this type
Characteristics of Job-Shop
• 1. High variety of products and low volume.
• 2. Use of general purpose machines and
facilities.
• 3. Highly skilled operators who can take up
each job as a challenge because of
uniqueness.
4.Large inventory of materials, tools, parts.
5. Detailed planning is essential for sequencing
the requirements of each product, capacities
for each work centre and order priorities.
Advantages
• 1. Because of general purpose machines and
facilities variety of products can be produced.
• 2. Operators will become more skilled and
competent, as each job gives them learning
• opportunities.
• 3. Full potential of operators can be utilised.
• 4. Opportunity exists for creative methods and
innovative ideas.
• Limitations
• 1. Higher cost due to frequent set up changes.
• 2. Higher level of inventory at all levels and
hence higher inventory cost.
• 3. Production planning is complicated.
• 4. Larger space requirements.
• 2.Batch Shops- Such structure is employed
when a business has relatively stable line of
products each of which is produced in periodic
batches either to the customer or for
inventory. Most of these items follows the
same flow pattern through the plant examples
include heavy equipment, electronic devices
and specialty chemicals.
Characteristics of Batch
• 1. When there is shorter production runs.
• 2. When plant and machinery are flexible.
• 3. When plant and machinery set up is used
for the production of item in a batch and
change of set up is required for processing the
next batch.
• 4. When manufacturing lead time and cost are
lower as compared to job order production.
Advantages
• 1. Better utilisation of plant and machinery.
• 2. Promotes functional specialisation.
• 3. Cost per unit is lower as compared to job
order production.
• 4. Lower investment in plant and machinery.
• 5. Flexibility to accommodate and process
number of products.
• 6. Job satisfaction exists for operators.
Limitations
1. Material handling is complex because of
irregular and longer flows.
2. Production planning and control is complex
3. Work in process inventory is higher compared
to continuous production.
4. Higher set up costs due to frequent changes
in set up.
• 3.Assembly Line- Production of discrete parts
moving from work station to work stations at a
controlled rate following the sequence needed
to build the product.
Characteristics
• 1. Standardisation of product and process
sequence.
• 2. Dedicated special purpose machines having
higher production capacities and output rates.
• 3. Large volume of products.
• 4. Shorter cycle time of production.
• 5. Lower in process inventory.
• 6. Perfectly balanced production lines.
• 7. Flow of materials, components and parts is
continuous and without any back tracking.
• 8. Production planning and control is easy.
• 9. Material handling can be completely
automatic.
Advantages
• 1. Higher rate of production with reduced
cycle time.
• 2. Higher capacity utilisation due to line
balancing.
• 3. Less skilled operators are required.
• 4. Low process inventory.
• 5. Manufacturing cost per unit is low.
Limitations
• 1. Breakdown of one machine will stop an
entire production line.
• 2. Line layout needs major change with the
changes in the product design.
• 3. High investment in production facilities.
• 4. The cycle time is determined by the slowest
operation.
• Examples include manual assembly of toys
and appliances. And automatic assembly
(called insertion) of components on a printed
circuit board. When other processes are
employed in a line fashion along with
assembly, it is commonly reffered to as a
production line.
• 4.Continuous Flow- Conversion or further
processing of undifferentiated materials such
as petroleum, chemicals or beer.
• As an assembly lines production follows a pre-
determined sequence of steps, but the flow is
continuous rather than discrete such
structures are usually highly automated and in
effect constitute one integrated machine that
must be operated24 hours a day to avoid
expensive shutdowns and start ups.
Characteristics
• 1. Dedicated plant and equipment with zero
flexibility.
• 2. Material handling is fully automated.
• 3. Process follows a predetermined sequence
of operations.
• 4. Component materials cannot be readily
identified with final product.
• 5. Planning and scheduling is a routine action
Advantages
• 1. Standardisation of product and process
sequence.
• 2. Higher rate of production with reduced
cycle time.
• 3. Higher capacity utilisation due to line
balancing.
• 4. Manpower is not required for material
handling as it is completely automatic.
• 5. Person with limited skills can be used on the
production line.
• 6. Unit cost is lower due to high volume of
production.
• Limitations
• 1. Flexibility to accommodate and process
number of products does not exist.
• 2. Very high investment for setting flow lines.
• 3. Product differentiation is limited.
• Break even analysis- A standard approach in
choosing among alternative processes or
equipment. A break even chart visually
presents alternative profits and losses due to
the number of units produced or sold. The
choice obviously depends on anticipated
demand.
• The method is most suitable when processes
and equipment entail a large initial investment
and fixed cost, when variable costs are
reasonably proportional to a number of units
used.
Product Life Cycle
• Products are born they live and they die
• They cast aside by a changing society
• Product life cycles may be a matter of few
hours eg Newspaper months- fashion and P.C,
years – video tape or decades
• Regardless of the length of the cycle, the task
for the operations manager is the same to
design a system that helps introduce new
products successfully
• Just as operations managers must be prepared
to develop new products, they must also be
able to develop strategies for new and existing
products
• Periodic examination of products is
appropriate because strategies change as
products move through their life cycle
• Successful product strategies require deter
mining the best strategy for each product
based on its position in its life cycle
• A firm identifies products or families of
products and their position in the life cycle
Introductory Phase
• Because products in the introductory phase
are still being fine tuned for the market as are
their production techniques, they warrant
unusual expenditure for :
• Research
• Product development
• Process modification and enhancement
• Supplier development
• Eg when cellular phones were first provided
the features desired by the public were still
being determined. At the same time,
operation managers were still searching for
the best manufacturing techniques
2. Growth Phase- in the growth phase, product
design has begun to stabilize and effective
forecasting of capacity requirements is
necessary- Adding capacity or enhancing
existing capacity to accommodate the increase
in production demand may be necessary.
• 3. Maturity Phase
• By the time a product is mature, competitors
are established.
• high volume, innovative production maybe
appropriate.
• Improved cost control, reduction in options
and a paring down on the production line may
be effective or necessary for profitability and
market share.
4. Decline Phase
• Management may need to be ruthless with
those products whose life cycle are at an end
• Dying products are typically poor products in
which to invest resources and managerial
talent unless dying products make some
unique contribution to the firm’s reputation or
its product line or can be or can be sold with
an usually high contribution , their production
should be terminated.
TOPIC SEVEN
Plant location
Supply and distribution system
• One of the key features of the transformation
system is the efficiency with which the output
is transferred to the recipients
• Any consideration of this will include
determination of where to place the plant or
operational facility, and how much
transportation of the inputs and outputs will
be required
• The way in which the outputs are obtained
and the inputs distributed has an effect on:
The total cost of the product / service
Number of customer that can be reached
The location of the organization and its units
The design of the plant or operational
facilities
• An efficient supply distribution system will
reduce cost and lead to a more effective
service in the form of quarter deliveries and
less stock outs.
• The type of output involved is clearly a major
factor in the determination of the best
distribution system.
• Services such as salons , schools, hospitals and
churches are difficult to transport and these
organizations usually perform the service in
the customers’ vicinity.
• The supply, storage and movement of
materials, people, equipment and finished
goods and services affects not only the
number of location of units to be established
but also the design of the transformation
facilities.
• All the potentially available plant must be
considered as part of the whole supply
distribution system to devise the most
strategy for obtaining the right inputs and
desired outputs.
• Plant flexibility, efficiency, effectiveness,
capacity etc will be determined by the plant
design and constantly changing environment
may require repeated redesigns.
• The advancement in technology and the
shortages of certain materials and energy
source must also be carefully examined by the
operations management team.
•
Location strategy
• It is difficult to set down rules whereby the
problem of facilities location on the
programmed but they are a number of factors
which should be considered.
• Location is the general area and site is the
place chosen within the location.
Factors influencing the choice of location
• Proximity to market –Organization may choose
to locate facilities close to their market to
minimize transportation cost and provide
better service. The closer the plant is to the
consumer the easier it is providing better
service.
• The closer the plant is to the consumer the
easier it is provide JIT delivery and to respond
to changes in demand and to react to field or
service problems.
2.Integration with other parts of the
organization
• If the new plant is one of the number owned
or operated by a single or organization it
should be situated at its work can be
integrated with that of the associated units.
This will require that the group will be
considered as an entity not as a number of
independents units.
3.Availability of labor and skills – Labor may be
more readily available in some cases but
certain geographical areas require the
company import labor.
4.Availability of transport- It is important that
good transport facilities are readily available
5.Availability of inputs – good transport
facilities will enable goods and services to be
delivered readily but a location near main
suppliers will reduce costs and permit staff to
meet suppliers easily to discuss quality,
technical or delivery problems.
6.Availability of service –These are 6 main
services which need to be considered and vice
and these are water, electricity, drainage, gas
disposals of waste and communications. An
assessment must be made of the
requirements of these as underestimating the
needs of any of the services can be costly and
convenient.
7.Regional regulations-It is important to check
that an early stage that the proposed location
does not infringe the local regulations. A
study must be made of the appropriate by
laws and of any special regulations.
8.Suitability of land and climate-Geology of the
area need to be considered together with the
climatic conditions.
9.Room for expansion – It is most unwise to
build to the limit of any site unless the long
range forecasts in indicates very definitely that
the initial building will never be required to
increase in size.
10.Safety requirements- Some production units
may present potential dangers to the
surrounding neighborhood
11.Political, cultural and economic situation – It
is important to consider these as they can
affect the organization operation negatively.
12.Availability of amenities – A location which
provides good external amenities i.e. housing,
shops , community service , communication
system is often more attractive than one
which is remote.
LOCATION EVALUATION METHODS
• In most location problems there are some
mandatory factors which must be fulfilled eg
an oil refinery must have an excellent main
services
• Once these key factors are identified the
location problem ceases to be open and
become a choice from a number of sites.
• An evaluation technique based an ranking the
various weighted factors can be helpful
The principals of ranking are:
• Examine various factors and assign to them
weights representing their importance to the
situation being changed.
• Each of the locations is examined and ranked
each factor, this ranking being carried out
factor by factor.
• Each ranking is then multiplied by the
appropriate weighting factor and the scores
totaled for the each possible location. These
totals indicate the desirability of the possible
locations compared with each other.
Factors in the design of plant or facilities
• The detailed design of plant and facilities
should be undertaken by an operations
management team, including architect
working within a brief which indicates
• Accommodation required
• Latest possible completion date
• Life of the plant or facilities
• Proposed site
• Maximum cost
The factors which affect the design of plant or
facilities include
• Size
• No of floors
• Access
• Services
• Loads to be carried
• Lighting
• Heating and ventilation
• Disposal of waste
• Special process requirements.
TOPIC EIGHT
Layout Facilities
Strategic Layout.
• Layout is used to indicate the physical
disposition of the facilities/ Plant and of the
various parts of the plant thus the layout will
encompass both the location of equipment
using a small department and the disposition
of departments upon a site.
• It is necessary to ensure the policy decisions
concerning the organization, method and
workflow are made before the facilities are
laid out rather than to try to fit organization
method and workflow to the layout.
•
• It is particularly important area of POM’s
responsibility since we are dealing with capital
equipment of the organization which is
difficult to relocate once it has been put into
relocation.
TYPES OF LAYOUT.
• Organization usually starts with a very small
with a product / service layout and as it
increases in size they tend to move towards a
process layout in the belief that such a layout
will make better use of the physical resources
Office layout- It positions workers equipment
and spaces / offices to provide for moment of
information.
Retail Layout- Allocates shelf space and
responds to customer behavior
Warehouse Layout – Addresses trade offices
between space and material handling.
Fixed position layout.- Addresses the layout
requirement of large bulky project s such as
buildings
Process Oriented layout- Deals with low volume
and high variety production
Work sell layout- Arranges machinery and
equipment to focus on production of a single
product or group of related products.
Product Oriented Layout- Seeks the best
personnel and machine utilization in repetitive
or continuous production.
CRITERIA FOR A GOOD LAYOUT
• The techniques employed in making a layout
are normal work study or industrial
engineering techniques, the process is a
creative which can be set down with any
finality and one’s experience plays a great
role.
• It is not possible to define a good layout but
there are certain criteria which may be
satisfied by a layout a
• It is not possible to define a good layout but
there are certain criteria which may be
satisfied by a layout.
1) Maximum Coordination
• Entry into physical form any departmental or
financial area should be in such a manner that
it is most convenient to the issuing /
receiving departments
2)Maximum flexibility
• A good layout will be one which can be
rapidly modified to meet changing
circumstances.
• Attention should be paid to the supply of
service / product which should be easy to
access
3) Maximum use of volume
• Facilities should be considered as cubic
devices a maximum use made of the volume
available eg cables, pipelines and conveyers
can be run above head height and used as
moving WIP stores and or tools or equipment
can be suspended from ceiling.
4) Maximum visibility
• All the people a material should be readily
observable at all times.
• They should be no hiding places into which
goods / information can get mislaid.
5) Maximum Accessibility
• All serving an maintenance points should be
readily accessible eg equipment should not be
placed against a wall in such a manner that
necessary maintenance cannot be easily
carried out.
6) Minimum Discomfort
• Poor lighting excessive sunlight, noise
vibrations and smells should be minimized
7) Inherent Safety
• All layouts should be safe and no person
should be exposed to danger.
• Care must be taken on both the people
operating the equipment and of the
customers and any passerby
• Adequate medical facilities and services must
be provided and these must satisfy the
requirements of the healthy and safety
regulations
8) Maximum Security
• Safeguards against fire, moisture, theft and
general deterioration should be provided for
in the original layout.
9) Minimum distance
• All movements should be both necessary and
direct .There should be very little distance
between offices/buildings
•
10)Efficient process flow
• Work flow and any transport flow not cross
• Effort should be taken to ensure that paper or
material flows are in one direction only
• The use of gravitational force in certain types
of processing on leads to great saving in
energy and time.
• 11) Identification
• Wherever possible working groups should be
provided with their own working place
• The need for a defined territory is basic.
Advantages of a good layout
• The overall process time and cost will be
minimized by reducing unnecessary handling a
meeting and by generally changing the
effectiveness of and work processes
• Supervision and control will be simplified by
the elimination of hidden corners in which
both information and material can be
misplaced.
• Changes in the programmes will be most
readily accommodated.
• Total output from the given facility will be as
high as possible by making the maximum
effective use of available space and resources.
• A feeling of unity among employees will be
encouraged by avoiding unnecessary
segregation
• Quality of the product service will be
sustained by safer or more effective methods
of operation.
Planning the Layout
• The following information should be available
when planning a layout.
• The original structure
• Type of production / operating system to be
employed
• Type of quality and people involved
• Dimensional plan of the space to be laid out
• Operations to be undertaken, their
descriptions sequence and standard times.
• The equipment needed to carry out the
operations and any special requirements it
imposes such as maintenance facilities and
safety devices
• The number of movements of materials from
one work center to another during the
working period
• Volume of material required at each work
station
• Any special inspection requirements
• Any spare facilities or equipment which will
need to be stored