Styrene Vapour Release Incident at LG Polymers: Harikrishnan M
Styrene Vapour Release Incident at LG Polymers: Harikrishnan M
Styrene Vapour Release Incident at LG Polymers: Harikrishnan M
LG polymers
Harikrishnan M
AIM
• Incident analysis of Styrene vapour release at LG polymers,
Vishakhapatnam.
• Identify the root causes of the incidents.
• Analysis of Emergency Management.
• Learning from the Incidents.
• Management of Change.
Incident Description
On 7th May 2020, around 3:00 AM
uncontrolled release of Styrene vapour
occurred at LG Polymers India Pvt.
Ltd., Vishakhapatnam.
Originally, the tank was having a swing The new piping arrangement provided for the
pipe arrangement to discharge the cooled cooled Styrene monomer liquid to be
Styrene from the recirculation and delivered at the bottom of the tank through a
regeneration unit at the top of the tank dip leg arrangement.
Before
Change in Design
The Modification was done without any Risk assessment & PESO approval
was not obtained.
The top level of the Styrene monomers now experienced higher temperatures
than the lower monomers.
Temperature Monitoring
The temperature measurement in the Tank was restricted to bottom zone only.
The temperature measurement (RTD) probe was located close to the discharge
port.
The recorded temperature in the tank on the day before the incident was 16-17 C
which was normal.
The temperature measurement were confined to bottom zone and the temperatures at
bottom and middle levels were unknown.
Refrigeration system was available for the tank, but it was operated in Manual mode.
For refrigeration the suction was taken from the N13 port (which is located 100 mm
from the bottom of the tank).
The cooled styrene monomer was then introduced through the dip leg arrangement
(300 mm from the bottom)
For a location like Vizag, where the average temperature is 35°C, Continuous refrigeration
system is essential.
Preferably an Automated Refrigeration system coupled with temperature sensors are
preferred.
Refrigeration of Tank
R – 22 is difluoro, mono-chloro
methane, also known as HCFC-22 or
Freon 22. was used as the
refrigerant.
Monitoring of TBC levels is very Significant and the procedure was very irregular
in the Unit.
TBC analysis of samples from the bottom layer were only carried out. Top levels
were not analysed.
Stocks of TBC & other high temperature inhibitors like TDM & NDM were
limited.
Since TBC levels were monitored only at the bottom, the TBC stratification at the top
layers went unnoticed. The TBC levels at the top reduced to less than 4 PPM.
Safety Lapses
Company was shutdown during lock down. They did not consider the
idling conditions in the tank.
No SOP for shutdown and start-up.(NO PSSR)
Log books/Data books do not have details of activities carried out.
No daily Sampling.
No System for measurement of dissolved oxygen in the tank.
Improper Onsite emergency plan.(Styrene gas leak scenario was not
considered)
Improper Safety Management Systems, No proper Engineering drawings,
HAZOP studies etc. were available.
Incompetent top, middle and low management.
Final analysis 800 tons of styrene escaped into the
atmosphere
Temperature Monitoring
Polymerization
Catalyst
Incompetent Management
Tank Design
Execution Of Onsite & Off site Emergency plan
As per the CCTV records, Styrene vapours were first visible at 2:42 AM.
2:42 AM 2:53 AM
The 4 Gas detectors beneath got activated at 2:53 AM. The delayed response can be due to
Positioning of the Sensors.
The alarms were set for 20% of LEL.
The gas detector should have been set based on STEL limit (100PPM) down the
temperature.
Execution Of Onsite & Off site Emergency plan
The Emergency actions were initiated only after the Senior Management officials arrived
at the Spot (3:30 AM)
The Scenario became Level 3 incident at 3:30 AM and Fire tenders and district police
Failure from the First responders
The Onsite Emergency Plan of the Unit was prepared as per MSIHC rules.
The Emergency plan however did not cover Toxic gas scenarios and was based on Fighting
Fire incidents.
The First responders (Shift in charge & Night duty officer) approached the scenario like a
Fire incident. Foam Pourers, Sprinklers were used.
Addition of temperature inhibitors into the tank for controlling the polymerization reaction
was started late only after the senior management officials reached the spot.
Ethyl Benzene was available and could have been pumped to the bottom of the tank and
then started the Refrigerant system. This could have brought down the temperature.0 C.
Failed Primary Response
Change of Process/technologies
Change of Catalysts
Change of Chemicals
Change of Personnel
Change of hardware/ software
Change in operating procedures
Change in working Environment
The MOC Process
STEP 1:
STEP 2:
The Idea of MOC
Design Philosophy &
Is it necessary? Approval
Is it Economical? Process Design Mechanical Design
Block Flow Engineering
diagram/Process drawings, P&ID.
Is there a better Flow diagram
alternative? HSE analysis (PHA)
Review of standards
& regulatory
Any Impacts on requirements
External/Internal
Health, Safety & review
Environment.?
The MOC Process
STEP 3:
Execution of the MOC JOB
STEP 4:
Training of Operational/Maintenance Personal
STEP 5:
Commissioning
STEP 6:
Handing over/ take over
STEP 7:
Post Commissioning Review
Thank You