Scada/Ems Systems - Hierarchy &: by AGM
Scada/Ems Systems - Hierarchy &: by AGM
Scada/Ems Systems - Hierarchy &: by AGM
HIERARCHY &
OVERVIEW
By
A.K . Mishr a
AGM
Power Grid Corporation of India Limited
REGIONS OF INDIA
Load Despatch & Communication (LD&C) Scheme
S/S
DMS FUNCTION EMS FUNCTION AUTOMATION
FUNCTION
HIERARICHAL SETUP OF INDIAN POWER SECTOR
RLDC
STATE LDC STATE LDC STATE LDC STATE LDC STATE LDC
SUB-LDCs SUB-LDCs
SUB-LDC SUB-LDC
RTUs RTUs
NORTHERN REGION CONTROL CENTRE HIERARCHY
RTUs
38 nos RLDC
NLDC
SUB LDC SUB LDC SUB LDC SUB LDC SUB LDC
NRLDC SRLDC
AREVA SYSTEM GE SYSTEM
ERLDC
AREVA SYSTEM NLDC
AREVA
NERLDC
WRLDC
AREVA SYSTEM
GE SYSTEM
Responsibilities of SLDCs and Sub-LDCs
SLDCs
Operation, monitoring and control of state owned power system.
104 LINKS
MODEM MODEM
WORKSTATION
JUKE BASED DEVELOPMENT
BOX ICCP
SCADA /EMS ISR OPERATOR
COMMUNICATION
SERVER SERVER CONSOLE CONSOLE SERVER
WITH TWO CRT
LAN 1
SPLITTER 1
TO OTHER CONTROL CENTERS
MODEM
VIDEO PROJECTION SYSTEM CHENNEL
/
MIMIC CONTROL BOARD TO RTUs 2X64KBPS
SCADA FUNCTIONS FOR
REAL TIME MONITORING & CONTROL
RTU DATA ACQUISITION
SUPERVISORY CONTROL
DATA EXCHANGE
DATA PROCESSING
oAlarms
oSequence of Event (SOE) recording
oGeneralised Calculations
DISTURBANCE DATA COLLECTION
HISTORICAL INFORMATION STORAGE & RETRIEVAL
EMS SOFTWARE FUNCTIONS
OPERATION LOAD GENERATION POWER SYSTEM
SCHEDULING BALANCE ANALYSIS
OPERATIONS SCHEDULING
POWER SYSTEM ANALYSIS
DISPATCHER TRAINING
SIMULATOR
S/S AUTOMATION
REMOTE SCADA
CONTROL OTHER S/S
CENTRE
SUBSTATION RTU
IEC 60870-5 /DNP
IEDs AT BAY LEVEL
CPU
CPU
IEC61850
PSTN
REDUNDANT
DISTRIBUTION
BUS
S/S
TYPICAL REMOTE OPERATION SCHEME
Substation 1 Substation 2
PLCC RTU/
PLCC
PLCC
SIC
PRINTER
EXISTING
SWITCH
PLCC
From EL PC WB(FO)
MUX
MUX
PLCC
PRINTER TO EXISTING ULDC
SYSTEM
From DR PC
SCADA SYSTEM FOR REMOTE OPERATION
Pampore
Udhampur
Kishenpur
Jammu POWERGRID BROADBAND NETWORK
Pathankote Hamirpur
Jallandhar
Amritsar
Moga Shimla
Ludhiana Chandigarh
Hisar
Ambala
Bawana
Panipat
Link to Bhutan
NEW DELHI
Gurgaon
Mandola
Itanagar
Balipara
B’garh
Alwar Dadri Moradabad
Siliguri Bongaiga Tezpur
Agra Lucknow on
Guwah Misa
Kohima
Patna
Jaipur ati
Ko Varanasi Malda
Kanpur
ta Sasaram Shillon
Bhopal
Allahabad Farakk
g Imphal
Gandhinagar Ujjai B’Sharif
a
K’Ghat
n Durgapur
Vindhyachal Agartala Aizwal
Ahmedabad Itarsi Jabalpur Ranchi JamshedpurJeerat
Vadodra Indore Korba
Raipur Rourkela KOLKATA
Nagpur Talch
Surat Dhule BhilaiRengali
Cuttack
er
Nasik Chandrapur Indravati Bhubaneswar
OPGW
WRAP AROUND
ADSS
IMPLEMENTATION STATUS
OF LD&C SCHEMES
REGION STATUS COMPLETION SCHEDULE
North- 66 1 7 0 8 964 12
Eastern
3 WRLDC MUMBAI
4 SRLDC BANGALORE
5 ERLDC KOLKATA
6 NERLDC SHILLONG
BENEFITS OF LD&C SCHEME
Reduce outages Reduce loss of
energy
Quick localization of
faults Reduce operational
costs
Improve restoration
time Improve customer
service
Ensure efficient
utilization of substation Better operational and
equipments management control
Improve power quality Availability of historic
data
Reduce maintenance
cost Better load planning