Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Updates of Infra Projects 1

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 24

REGIONAL

ENGINEERING
UNIT
FLORENDO S GERDAN JR
Police Colonel
C, REU-NCR

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.


NCRPO INFRA PROJECTS
 ONGOING CONSTRUCTION PROJECTS
1. Construction of Northern Police District (NPD) Annex Building, Dagat-Dagatan
Avenue, Caloocan City, SARO Funded
2. Construction of the RDSU Covered Parking/Multi-Purpose, CBD, Taguig City, TR Fund
3. Construction of NCRPO Trainee Barracks, CBD, Taguig City, TR Fund
4. Rehabilitation and Renovation of the Southern Police District (SPD) Firing
Range (Proposed Two Storey Admin Building and Rehabilitation of SPD Firing
Range), SPD Compound, Lawton Avenue, Taguig City, TR Fund
5. Construction of Eastern Police District (EPD) Annex 1st and Last Phase, Meralco Ave., Pasig City,
TR Fund

 COMPLETED PROJECTS
1. Construction of 9 Unit 20 Footer Container Van Storage R1-R9, CBD, TR Fund
2. Completion of Southern Police District (SPD) Crime Laboratory, CBD, Taguig
City, TR Fund
3. Construction of 2-Storey Messhall and Facilitator’s Building, CBD,
Taguig City, TR Fund

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.


NAME OF PROJECT: COMPLETED
Construction of Northern Police District Building

SOURCE OF FUND: SARO-BMB-D-19-0013888

BID AMOUNT: Php 26,249,471.47

DATE STARTED: 10/5/2020

TARGET DATE OF 12/31/2021


COMPLETION:

PERCENTAGE: 55.33% as of 1/3/2022

STATUS: Ongoing

CONTRACTOR: Great Zone Enterprise

REMARKS:
Conducted Concrete Pouring of Slab and Girder at Roof Deck on
January 20, 2022

NAME OF PROJECT: ONGOING


Construction of RDSU Covered Parking/Multi-Purpose
Building Phase 1

SOURCE OF FUND: PNP TR Fund 2020

BID AMOUNT: Php 9,971,212.11

DATE STARTED: 9/21/2021

TARGET DATE: 11/20/2021

PERCENTAGE: 61.527% as of 1/3/2022

STATUS: Ongoing

CONTRACTOR: DEX-SAL Builders

REMARKS:
Ongoing
NAME OF PROJECT: ONGOING
Construction of NCRPO Trainees Barracks

SOURCE OF FUND: PNP TR Fund 2020

BID AMOUNT: Php 23,337,300.00

DATE STARTED: 09/21/2021

PERCENTAGE: 13.29% as of 1/3/2022

STATUS: Ongoing

CONTRACTOR: E.D. Libunao Construction and


Trading

REMARKS:
Ongoing installation of tie beam footing

NAME OF PROJECT: ONGOING


Rehabilitation and Renovation of The Southern
Police District (SPD) Firing Range (Proposed Two
storey Admin Building) and Rehabilitation of SPD
Firing Range

SOURCE OF FUND LGU Fund Donated to PNP

BID AMOUNT: Php 2,945,972.84

DATE STARTED: 10/19/2020

TARGET DATE: 12/28/2020

PERCENTAGE: 35.01% as of 11/11/2021

STATUS: Ongoing

CONTRACTOR: ACC CARASCO ENTERPRISE, INC.

REMARKS:
Limited manpower and materials
NAME OF PROJECT: ONGOING
Construction of Eastern Police District (EPD) Annex
1st Phase and Last Phase

SOURCE OF FUND: PNP TR Fund 2020

BID AMOUNT: Php 9,739,500.00

DATE STARTED: 09/21/2021

STATUS: Ongoing

CONTRACTOR: DEX-SAL Builders

REMARKS:
Ongoing demolition and installation of trusses

NAME OF PROJECT:
Construction of 9 Unit 20 Footer Container Van COMPLETED
Storage R1-R9

SOURCE OF FUND: PNP TR Fund 2020

BID AMOUNT: Php 1,633,500.00

DATE STARTED: 10/16/2021

TARGET DATE: 05/05/2022

PERCENTAGE: 100% as of 12/01/2021

STATUS: Completed

CONTRACTOR: Quatrix Construction and Supply Inc

REMARKS:
For final inspection
NAME OF PROJECT: ONGOING
Completion of Southern Police District Crime
Laboratory
SOURCE OF FUND: PNP TR Fund 2020

BID AMOUNT: Php9,888,065.14

DATE STARTED: 07/7/2021

TARGET DATE/ 06/28/2021


REVISED: 11/9/2021

PERCENTAGE: 100% as of 1/3/2022

STATUS: Completed

CONTRACTOR: E.D. Libunao Construction and


Trading

REMARKS:
For final inspection on January 26, 2022

NAME OF PROJECT:
Construction of 2-Storey Messhall & Facilitators
COMPLETED
Building

SOURCE OF FUND: TR FUND 3rd QUARTER 2018

BID AMOUNT: Php 10, 174,178.28

DATE STARTED: 04/13/2019

TARGET DATE: 01/13/2020

STATUS: Completed

CONTRACTOR: MR ALBERTO P CARASCO-ACC


President/CEO Carasco Enterprise,
Inc. 16A. Mabini St., Brgy. Burgos,
Rodriguez, Rizal

REMARKS:
Completed as of 03/19/2021
For blessing and inauguration
NHQ
INFRA PROJECTS
 COMPLETED PROJECTS
1. Construction of Research and Development Center Building, CBD, TR Fund

 SUSPENDED PROJECTS
1. Establishment of the Information Technology Center, CBD, SARO Fund

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.


NAME OF PROJECT: COMPLETED
Construction of PNP Research and Development
Center Building

SOURCE OF FUND: TR Fund

BID AMOUNT: Php 107,163,905.89

DATE STARTED: 12/11/2018

TARGET DATE/ 12/10/2020


REVISED: 3/11/2021

STATUS: Completed

CONTRACTOR: LV enterprise Inc/ Mamsar


Constructiion Industrial Corporation

REMARKS:
Conducted final inspection last January 20, 2022

NAME OF PROJECT:
Establishment of the Information Technology Center SUSPENDED
(NCRPO)
SOURCE OF FUND: SARO Nr BMB-D-19-0013495

BID AMOUNT: Php 107,163,905.89


DATE STARTED: 2/15/2021
TARGET DATE OF 05/05/2022
COMPLETION:

PERCENTAGE: 30.302%
STATUS: Temporarily suspended
CONTRACTOR: Global V Builders Co.
REMARKS: Suspended effective March 12, 2021
due to the changes of structural plan,
waiting for variation order from ES
DPWH INFRA PROJECTS
(NCRPO)
 ONGOING CONSTRUCTION PROJECTS
1. Construction of NCRPO Quartering Building “A”, CBD, GAA 2021
2. Construction of Moriones Police Station Building, Tondo, Manila, GAA 2020

 COMPLETED PROJECTS
1. Construction of Multi-Purpose Center Building, CBD, GAA 2020
NAME OF PROJECT: ONGOING
Construction of NCRPO Quartering Building “A”

SOURCE OF FUND: GAA 2021 (PNP-DPWH


CONVERGENCE PROGRAM)

BID AMOUNT: Php100,468,425.87

DATE STARTED: 10/12/2021

TARGET DATE: 06/07/2022

STATUS: Ongoing

CONTRACTOR: Flordes Construction and Trading


Corp

REMARKS:
Ongoing mobilization and excavation

NAME OF PROJECT: ONGOING


Construction of Moriones Police Station Building

SOURCE OF FUND: GAA 2020 (PNP-DPWH


CONVERGENCE PROGRAM)

BID AMOUNT: Php46,803,477.89

DATE STARTED: 08/15/2021


TARGET DATE/ 07/06/2021
REVISED: 1/25/2022

PERCENTAGE: 41% as of 11/09/2021


STATUS: Ongoing

CONTRACTOR: Quatrix Construction and Supply


REMARKS:
Concrete Pouring on 4th Floor Slab and Beam
NAME OF PROJECT: COMPLETED
Construction of Multi-Purpose Center Building

SOURCE OF FUND: GAA 2020 (PNP-DPWH


CONVERGENCE PROGRAM)

BID AMOUNT: Php 210,000,000.00

DATE STARTED: 02/21/2020

TARGET DATE/ 01/16/2021


REVISED: 1/23/2022

PERCENTAGE: 100%

STATUS: Completed

CONTRACTOR: A.L. SALAZAR Construction Inc.

REMARKS:
For final inspection
DONATED INFRA PROJECTS
(NCRPO)
 ONGOING CONSTRUCTION PROJECTS
1. Construction of NCRPO Medical Center, CBD, Donated by Traveler International Hotel Group Inc
and PAGCOR in coordination with Resorts World Philippine Cultural Heritage

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.


NAME OF PROJECT: ONGOING
Construction of NCRPO Medical Center

SOURCE OF FUND: Donated by Traveler International Hotel


Group Inc and PAGCOR in
coordination with Resorts World
Philippine Cultural Heritage

DATE STARTED: 08/23/2021

TARGET DATE OF 12/31/2022


COMPLETION:

STATUS: Ongoing

PERCENTAGE: 1.53% as of 01/12/2022

CONTRACTOR: Megawide Corporation

REMARKS:
Ongoing mobilization, construction of temporary facilities and
excavation
NCRPO INFRA PROJECTS (SUMMARY)
No Name of Projects Location Source of Fund Date Started Target Date Work Status
. Percentage
1 Construction of Northern Police Dagat-Dagatan SARO Funded 5-10-2020 12-31-2021 55.33% as of Ongoing
District (NPD) Annex Building Avenue, Caloocan City 01-03-2022

2 Construction of the RDSU Covered Camp Bagong Diwa, TR Fund 08/18/2021 11/20/2022 61.527% as of Ongoing
Parking/Multi-Purpose Building Taguig City 01-03-2022

3 Construction of NCRPO Trainee Camp Bagong Diwa, TR Fund 09-21-2021 13.29% as of Ongoing
Barracks Taguig City 01-03-2022

4 Rehabilitation and Renovation of SPD Compound, TR Fund 10-19-2020 12-03-2021 35.01% as of Ongoing
the Southern Police District (SPD) Lawton Avenue, 11-11-2021
Firing Range (Proposed Two Storey Taguig City,
Admin Building and Rehabilitation
of SPD Firing Range)

5 Construction of Eastern Police Meralco Ave., Pasig TR Fund 11-27-2021 Ongoing


District (EPD) Annex 1st and Last City,
Phase

6 Construction of 9 Unit 20 Footer Camp Bagong Diwa, TR Fund 09-2021 100% as of 12- For final inspection
Container Van Storage R1-R9, CBD, Taguig City 01-2021

7 Completion of Southern Police Camp Bagong Diwa, TR Fund 07-07-2021 12-03-2021 100% as of 01- For final inspection
District (SPD) Crime Laboratory Taguig City 03-2022 on 01-26-2022

8 Construction of 2-Storey Messhall Camp Bagong Diwa, TR Fund 04-13-2019 01-13-2020 100% as of 03- For blessing and
and Facilitator’s Building Taguig City 19-2021 inauguration

9 Construction of Research and Camp Bagong Diwa, TR Fund 12-11-2018 03-18-2020 100% as of 11- Conducted final
Development Center (RDC) Taguig City 30-2021 inspection last
Building January 20, 2022

10 Establishment of the Information Camp Bagong Diwa, SARO Funded 02-15-2021 5-5-2022 0.302% as of Suspended
and Technology Center (NCRPO) Taguig City 03-10-2021

11 Construction of NCRPO Quartering Camp Bagong Diwa, GAA 2021 10-12-2020 7-6-2022 Ongoing
Building “A” Taguig City Mobilization

12 Construction of Moriones Police Tondo, Manila GAA 2020 8-15-2020 7-6-2021 41% as of 11-9- Ongoing
Station Building 2021

13 Construction of Multi-Purpose Camp Bagong Diwa, GAA 2020 2-27-2020 4-16-2021 100% as of 12- For final inspection
Center Building Taguig City 21-2021

14 Construction of NCRPO Medical Camp Bagong Diwa, Donated by Traveler International 8-23-2021 12/01/2022 1.53% as of 01- Ongoing
Center Taguig City Hotel Group Inc and PAGCOR in 12-2022
coordination with Resorts World
Philippine Cultural Heritage
NEMSQ INFRA PROJECTS
(DPWH)
 ONGOING CONSTRUCTION PROJECTS
1. Construction of PNP BFP Building, Maysilo Circle, Brgy. Plainview, Mandaluyong City, GAA
DPWH
2.Construction of QCPD Multi-Purpose Building (Gymnasium), Camp Karingal, Quezon City, DPWH
GAA 2020 (MYCA)
3. Construction of Annex Building of Holy Spirit Police Station 14, Brgy Holly Spirit, Quezon City,
DPWH GAA 2020

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.


NAME OF PROJECT: ONGOING
Construction of PNP BFP Building, Maysilo Circle,
Brgy Plainview, Mandaluyong City

SOURCE OF FUND: DPWH GAA

BID AMOUNT: Php 282,236,383.22

DATE STARTED: 8/21/2018

TARGET DATE OF 5/11/2022


COMPLETION:

STATUS: Ongoing

PERCENTAGE: 73.35% as of 01/18/2022

REMARKS: Ongoing

NAME OF PROJECT: ONGOING


Construction of QCPD Multi-Purpose Building
(Gymnasium), Camp Karingal, Quezon City
SOURCE OF FUND: DPWH GAA 2020 (MYCA)

PROJECT COST: Php 27,427,250.62

DATE STARTED: 01/25/2021

TARGET DATE: 11/21/2021

NEW TAGET DATE: 1/20/2022

PERCENTAGE: 91% as of 01/19/2022

CONTRACTOR: CL Morales Construction

REMARKS: Ongoing
ONGOING
NAME OF PROJECT:
Construction of Annex Building of Holy Spirit Police
Station 14

SOURCE OF FUND: DPWH

PROJECT COST: Php 3,800,000.00

DATE STARTED: 07/30/2021

TARGET DATE OF 11/30/2021


COMPLETION:

PERCENTAGE: 71% as of 01/19/2022

REMARKS: Ongoing
NEMSQ INFRA PROJECTS
(LGU)
 ONGOING CONSTRUCTION PROJECTS
1. Construction of Bagong Silangan Police Station 13, Brgy. Bagong Silangan, Quezon City, LGU
2021
2. Construction of Kabayanan Sub-Station 3, San Juan CPS/Construction of Multi-Purpose
Building, F. Blumentrit cor. A. Bonifacio St., Brgy. Kabayanan, San Juan City, GAA 2020
3. Rehabilitation of Galas Police Station 11, Luzon Ave., Galas, Quezon City, LGU 2021
4. Electrical Reinstallation of La Loma Police Station 1, Mayon St., La Loma, Quezon City, LGU
2021
5. Rehabilitation of Electrical System of Fairview Police Station 5, Pearl St., Fairview, Quezon City,
LGU 2021
6. Renovation of Project 6 Police Station 15 PCP 2, Romblon St., Sto Cristo Bago Bantay, Quezon
City, LGU 2021
7. Construction of New Building of Project 6 Police Station 15, Road 3, Project 6, Quezon City, LGU
2021

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.


ONGOING
NAME OF PROJECT:
Construction of Bagong Silangan Police Station PS
13

SOURCE OF FUND: LGU

BID AMOUNT: Php 30,133,000.83

DATE STARTED: 01/2019

TARGET DATE 10/2020


OF/REVISED:

STATUS: Ongoing

PERCENTAGE: 97% as of 01/19/2022

REMARKS: Delayed

NAME OF PROJECT: ONGOING


Construction of Kabayanan Sub Station 3, San Juan
CPS/Construction of Multi-Purpose Building

SOURCE OF FUND: GAA

BID AMOUNT: Php 66,527,084.19

DATE STARTED: 9/25/2020


TARGET DATE OF 05/2020
/REVISED:

STATUS: Ongoing
PERCENTAGE: 99.9% as of 01/18/2022
REMARKS: Delayed
ONGOING
NAME OF Rehabilitation of Galas Police
PROJECT: Station PS 11

SOURCE OF FUND: DPWH

BID AMOUNT: Php3,242,671.01

DATE STARTED: 9/28/2021

TARGET DATE OF 11/27/2021


COMPLETION/REVISE
D:

STATUS: Ongoing

PERCENTAGE: 71% as of 01/19/2022

REMARKS: Delayed
NAME OF Electrical Reinstallation of La
PROJECT: Loma Police Station PS 1 ONGOING

SOURCE OF FUND: LGU

BID AMOUNT: Php4,700,000.00

DATE STARTED: 8/27/2021

TARGET DATE OF 11/15/2021


COMPLETION/REVISE
D:

STATUS: Ongoing

PERCENTAGE: 71% as of 01/19/2022

REMARKS: Delayed
NAME OF PROJECT: ONGOING
Rehabilitation of Electrical System of Fairview
Police Station 5

SOURCE OF FUND: LGU

BID AMOUNT: Php 3,299,516,45

DATE STARTED: 9/27/2021


TARGET 12/1/2021
DATE/REVISED:

STATUS: Ongoing
PERCENTAGE: 56% as of 01/14/2022
REMARKS: Delayed

NAME OF PROJECT: ONGOING


Renovation of Project 6 Police Station 15 PCP 2

SOURCE OF FUND: LGU

BID AMOUNT: Php 14,256,000.00

DATE STARTED: 7/1/2021

TARGET DATE OF 10/1/2021


COMPLETION/REVISED:

STATUS: Ongoing

PERCENTAGE: 41% as of 01/19/2022

REMARKS: Delayed
NAME OF PROJECT: ONGOING
Construction of New Building of Project 6 Police
Station 15
SOURCE OF FUND: LGU

BID AMOUNT: Php 5,000,000.00

DATE STARTED: 10/4/2021


TARGET DATE OF 2/28/2022
COMPLETION/REVIS
ED:

STATUS: Ongoing
PERCENTAGE: 71% as of 01/19/2022
REMARKS: Delayed
NCRPO INFRA PROJECTS (NEMSQ)
No Name of Projects Location Source of Fund Date Started Target Date Work Status
. Percentage

1 Construction of PNP BFP Building Maysilo Circle GAA DPWH 08-21-2018 05-11-2022 73.35% as of Ongoing
Brgy. Plainview, 01-18-2022
Mandaluyong City,
2 Construction of QCPD Multi- Camp Karingal, DPWH GAA 2020 (MYCA) 11-27-2020 01-20-2022 91% as of 01- Ongoing
Purpose Building (Gymnasium) Quezon City, 19-2022

3 Construction of Annex Building of Brgy Holly Spirit, DPWH GAA 2020 07-30-2021 11-30-2021 71% as of 01- Ongoing
Holy Spirit Police Station 14 Quezon City 19-2022

4 Construction of Bagong Silangan Brgy. Bagong Silangan, LGU 2021 01-01-2019 10-01-2020 97% as of 01- Ongoing
Police Station 13 Quezon City 19-2022

5 Construction of Kabayanan Sub- F. Blumentrit cor. A. GAA 2020 09-25-2020 05-01-2021 99.9% as of 01- Substantialy
Station 3, San Juan Bonifacio St., Brgy. 18-2022 Completed
CPS/Construction of Multi- Kabayanan, San Juan
Purpose Building City
6 Rehabilitation of Galas Police Luzon Ave., Galas, LGU 2021 09-28-2021 11-27-2021 71% as of 01- Ongoing
Station 11 Quezon City 19-2022

7 Electrical Reinstallation of La Loma Mayon St., La Loma, LGU 2021 08-27-2021 11-27-2021 71% as of 01- Ongoing
Police Station 1 Quezon City 19-2022

8 Rehabilitation of Electrical System Pearl St., Fairview, LGU 2021 09-27-2021 12-01-2021 56% as of 01- Ongoing
of Fairview Police Station 5 Quezon City 19-2022

9 Renovation of Project 6 Police Romblon St., Sto LGU 2021 07-01-2021 10-01-2021 41% as of 01- Ongoing
Station 15 PCP 2 Cristo Bago Bantay, 09-2022
Quezon City
10 Construction of New Building of Road 3, Project 6, LGU 2021 04-10-2021 02-28-2022 71% as of 01- Ongoing
Project 6 Police Station 15 Quezon City 09-2022
End of Presentation

“As for me and my house we will


serve the Lord”

Serbisyong TAMA: TApat, May Tapang at MAlasakit para sa mamamayan.

You might also like