Progress and Performance Measurement and Evaluation
Progress and Performance Measurement and Evaluation
Progress and Performance Measurement and Evaluation
13–2
Project Monitoring Information
System
13–3
Project Monitoring System… (cont’d)
13–4
Project Progress Report Format
Progress since last report
Current status of project
1. Schedule
2. Cost
3. Scope
Cumulative trends
Problems and issues since last report
1. Actions and resolution of earlier problems
2. New variances and problems identified
Corrective action planned
13–5
The Project Control Process
Control
◦ The process of comparing actual performance against plan to identify
deviations, evaluate courses of action, and take appropriate corrective
action.
Project Control Steps
1. Setting a baseline plan.
2. Measuring progress and performance.
3. Comparing plan against actual.
4. Taking action.
Tools
◦ Tracking and baseline Gantt charts
◦ Control charts
13–6
Baseline and Tracking Gantt Charts
FIGURE 13.1
13–7
Project Schedule Control Chart
FIGURE 13.2
13–8
Developing an Integrated Cost/Schedule System
13–9
Cost/Schedule Graph
FIGURE 13.4
13–10
Earned-Value Review Exercise
FIGURE 13.5
13–11
Indexes to Monitor Progress
Performance Indexes
◦ Cost Performance Index (CPI)
◦ Measures the cost efficiency of work accomplished to date.
◦ CPI = EV/AC
◦ Scheduling Performance Index (SPI)
◦ Measures scheduling efficiency
◦ SPI = EV/PV
◦ Percent Complete Indexes
◦ Indicates how much of the work accomplished represents of the total
budgeted (BAC) and actual (AC) dollars to date.
◦ PCIB = EV/BAC
◦ PCIC = AC/EAC
13–12
Interpretation of Indexes
TABLE 13.3
13–13
Forecasting Final Project
Cost
Methods used to revise estimates of future
project costs:
◦ EAC
re
◦ Allows experts in the field to change original baseline durations
and costs because new information tells them
the original estimates are not accurate.
◦ EAC
f
◦ Uses actual costs-to-date plus an efficiency index to project final
costs in large projects where the original budget is unreliable.
13–14
Forecasting Model: EACf
The equation for this forecasting model:
13–15
Monthly Status Report
EXHIBIT 13.1
13–16
Other Control Issues
Scope Creep
Baseline Changes
Data Acquisition
Costs and Problems
13–17
Glossary of Terms
EV Earned value for a task is simply the percent complete times its original budget. Stated differently,
EV is the percent of the original budget that has been earned by actual work completed.
PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate
of the resources scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the
work scheduled].
AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work. [ACWP
—actual cost of the work performed].
CV Cost variance is the difference between the earned value and the actual costs for the work
completed to date where CV = EV – AC.
SV Schedule variance is the difference between the earned value and the baseline line to date where
SV = EV – PV.
BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.
VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.
TABLE 13.1
13–18
13–19
Consider the table and progress report :
Activity Predeccessor Time(days) Estimated cost
A None 1 $50
B None 2 $100
C A 2 $200
D C 2 $100
13–20
Calculate:
1. Draw gantt chart
2. Calculate PV,EV,AC by considering the progress report
3. Calculate scheduled variance(SV)
4. Cost variance(CV)
5. Scheduled performance index(SPI)
6. Cost performance index(CPI)
7. Calculate estimated cost at completion (EAC)
8. DRAW cost/schedule graph showing PV,EV,AC,SV,CV,EAC,BAC
13–21
13–22
13–23
13–24
13–25
13–26