Presentation On Jamuna Bridge Project
Presentation On Jamuna Bridge Project
Presentation On Jamuna Bridge Project
PRESENTATION
MEET THE TEAM: GROUP
A
JANNATUL NAIMA HAQUE-01
ISRAT ARIF SUMAYA-11
AFROZA MAHAZABIN-24
SHEIKH MOHIUDDIN
SHAHRUJJAMAN-33
MD. ABIR ADNAN-39
CONSTRUCTION OF JAMUNA
BRIDGE IN BANGLADESH:
A CASE STUDY
BACKGROUND
The Jamuna, one of the three largest rivers in Bangladesh, runs from north to south through central
Bangladesh, dividing the country to the east and west.
The Jamuna formed a bottleneck in east-west traffic, hindering the transport of agricultural
products grown in the granaries in the west to the consumption centers in the east. In addition,
regions in the west were prevented from benefiting from infrastructure, including gas, electricity
and communications, which were concentrated in eastern Bangladesh and had been left
underdeveloped. Under these circumstances, a plan to construct a bridge across the Jamuna had
been the earnest wish of the nation since Bangladesh became independent in 1971.
OBJECTIVES
The objective of the project was to-
• connect the eastern and western halves of the country, separated by the Jamuna River
The Jamuna bridge is the most expensive and technically one of the most challenging transport infrastructure
projects ever attempted in Bangladesh. To implement the Project, the Government created the Jamuna Bridge
Multipurpose Authority (JMBA) in 1985 and assigned it the responsibility of preparing and implementing the
Project. As an integral part of the Project, ADS also financed complementary follow-on investment projects to
expand the road network on the east side of the Jamuna River and connect the separate rail networks on either side
of the river.
Study on the implementation of the project shows the following factors:
Training the river to Since the project site is in Rapidly changing river
ensure it would continue central Bangladesh, about beds, river paths and
to fl ow under the bridge 300 km from the Bay of intense heat each rainy
corridor was one of the Bengal, the supply of season create a great
most diffi cult technical necessary construction challenge for contractors
challenges of the project materials and equipment to complete the project on
and its components. has caused major time.
problems.
CHALLENGES OF THE
PROJECT
Funding for the significant government contribution to project costs was provided through a surcharge
and levy applied from 1986 to 1994 under the Jamuna Multipurpose Bridge (Surcharge and Levy)
Ordinance 1985. The surcharge was collected on rail and ferry charges, telephone bills, motor vehicle
licenses, and registration documents for land and buildings.
At appraisal, it was agreed that the Government would pursue a policy of cost recovery for the project,
setting tolls that would not discourage bridge users. Based on a study on the structure and level of
tolls,the Government set tolls that were higher than envisaged at appraisal and more than sufficient to
meet future debt-service obligations.
SUMMARY OF PROJECT COST ESTIMATES
AT APPRAISAL AND ACTUAL
EXPENDITURES:
Appraisal Estimates Actual Expenditures
300
259.61
250 244.05
220.4 222.7
200
Cost in USD
150
100
52.9 62.76
50 27 29.7
0
Main Bridge River Training Approach Roads Consulting Services
Though the estimated cost was $696 million USD, the actual cost at the end of the project was $753 million. The
actual project cost was close to the cost estimated at appraisal. This was largely due to the extensive work carried out
during the project preparation phase.
DISBURSEMENT SCHEDULE
Disbursement Details
250
198 201
200 200
200 189
178
155
150
Cost in USD
132
110
100
78
58
50
25.64
10.58
Axis Title
EFFECTIVENESS
FINANCIAL ANALYSISAND CONCERNS
Based on a study on the structure and level of tolls, completed in mid-June 1997, the Government
set tolls that were higher than planned at appraisal and more than sufficient to meet future debt-
service obligations. So far the revenues being generated from the bridge are in line with the toll
study.
Table: Comparison of ferry fares and tolls for the Jamuna bridge
Table: Comparison of Predicted/Actual Average Daily Traffic Volume for the Bridge
The PCRM (Project Completion Review Mission) recalculated the Economic Internal Rate of Return
(EIRR) following the same methodology that was used at appraisal. The estimated EIRR was 16.8
percent, which is higher than the appraisal estimate of 14.5 percent, confirming the positive effects of
the higher-than-estimated traffic on the bridge despite the higher tolls set by the Government.
Substantial development impact is expected with the Project, providing improved connection is
established to the Northwest of Bangladesh with over 30 million people, most of whom are poor. The
PCRM noted that the Project is already generating increased economic development through reduced
transport cost and improved access. Market developments were observed both on the east side of the
Jamuna River toward Dhaka, and on the west side, near the bridge site and along the access road to
the bridge.
EFFECTIVENESS
ATTAINMENT OF BENEFITAND CONCERNS
The Project achieved its objectives on time and largely within budget. The most important objective
met by the Project was to connect the eastern and western halves of Bangladesh to foster economic
development.
With continued economic growth in Bangladesh and growing sub-regional cooperation, cross-Jamuna
traffic is expected to increase further, bringing economic benefits and make sub-regional cooperation
easier and more attractive. The Project will strengthen trade opportunities and support the
development of improved transport networks for the efficient flows of services and goods, including
improved access to the northwestern region of Bangladesh.
EFFECTIVENESS
ATTAINMENT OF BENEFITAND CONCERNS
The small survey conducted by the PCRM confirmed increased travel and perceived benefits
for the poorer groups of people traveling by bus and living on both sides of the bridge.
Before the Jamuna Bridge was constructed, ferries were the only means of crossing the
Jamuna, which divides Bangladesh to the east and west. The survey conducted before the
bridge was opened to traffic indicated that the waiting time for the Aricha-Nagarbari, 75km
downstream from the bridge, and that for the Sirajganj-Bhuapur, 7km upstream, were 12-48
hours and 8-12 hours, respectively, with the time required to cross the river by ferry being
about two and half hours on both sections. By contrast, the Jamuna Bridge enabled vehicles to
cross the river in just 12-18 minutes.
IMPACTS
Implementation schedule April 1994 to November 1997 (43 months) October 1994 to June 1998 (44 months)
Project cost
Foreign currency US$600 million -
Local currency US$96 million -
Total US$696 million US$753.7 million
ODA loan portion ¥21.562 billion ¥21.29 billion