Lecture Two
Lecture Two
Lecture Two
CHAPTER 3
Quantity surveying
EYOB E. (MSc.)
4.1. Introduction
In a civil engineering activity, the owner
2
To estimate how much a civil engineering
project may cost, the actual quantities of
materials, labor & equipment etc that is
needed for the construction work must be
calculated at the beginning of the work.
Such work of calculating the amount of
3
The following tasks are covered in quantity
surveying:
1. Preparation of Specification
4
Measurement of civil works
Measurement of civil works includes the
billing of each trade of work either from
drawings or the building itself for defining
the extent of works under each trade.
The standard book, which is used in
5
Specification Worksheet (BOQ form)
It is the format which is used in a bill of
6
There are four clearly defined steps in
preparation of Bill of Quantities:
1. Taking off
2. Squaring
3. Abstracting
4. Writing the final Bill of Quantity
7
4.2.1Taking off
Is the process of measuring or scaling
8
9
10
Column 1 is used for stating the number of
times an item occurs and is called the
timising column.
Column 2 is called dimension column as it is
11
Column 3 is called squaring column. The
stated dimensions in column 2 are multiplied
to determine the quantity of the work either
in m, m2, m3 or in Pcs. or No.
Column 4 is called description column and
12
13
4.2.2. Squaring:
The process of multiplying, adding, subtracting
or dividing the recorded dimensions for the
purpose of obtaining linear measures, areas,
volumes etc
The dimensions entered in Column 2 are
14
4.2.3. Abstracting:
The squared dimensions are transferred to
15
16
A typical building project will have the
following work items.
17
Substructure
1. Excavation and earth work
1.1. site clearing
to remove the top 20-30cm soil
a working space of 1m is required on each side
Measured in m2
1.2. bulk excavation
for building underground structures
Working space of 25cm is required on each side
Measured in m3 if depth of excavation is more
than 30cm.
18
1.3. Pit excavation
For isolated footing
Expressed in m3
Working space of 25cm is required on each side
19
1.5. fill/embankment
Net volume to be filled
Working spaces need to be filled
Total excavated= site clearance+ pit excavation+
bulk excavation+ trench excavation
Cart away= total excavated – back fill
It is expressed in m3
20
2. Concrete work
2.1. lean concrete
To protect structural concrete from damage
21
2.3. formwork
A temporary structural element, which
2.4. reinforcement
measured in kg
Length of the bar is taken from the drawing
22
3. Masonry work/Stone work
For foundation wall (measured in m3)
hard core (measured in m2)
23
Superstructure
1. Concrete work
1.1. concrete
For slabs, beams, columns, staircase
Measured in m3
1.2. formwork
Measured in m2
1.3.reinforcement
Expressed in kg.
24
2. Masonry works
Measured in m3
3. Roofing
Roof cover is measured by area(m2)
Items like downpipes are measured by
length(m)
25
4. Carpentry and joinery work
work on timber intended for structural
26
5. Steel structural work
for beam, column, slab, truss, connections
etc
Usually measured in weight (kg)
6. Metal works
Includes aluminum and iron works
For door and window frames
Measured in area
27
7. finishing work
Plastering
8. Glazing
Glazing shall be measured in area(m2)
28
THANK YOU!
29