Properties and Application of High Strength Concrete: Prof. Dr. Md. Abdus Salam
Properties and Application of High Strength Concrete: Prof. Dr. Md. Abdus Salam
Properties and Application of High Strength Concrete: Prof. Dr. Md. Abdus Salam
Lecture 4
(Batching, Mixing, Transporting,
Placing, Curing, and Quality Control
Procedures of HSC)
3
Mix Design of HSC
7
Mix Design of HSC
8
Mix Design of HSC
Mixing:
HSC may be mixed entirely at the batch plant, in a
central or truck mixer, or by a combination of the
two.
Mixing follows the recommendations of ACI 304.
Reducing the batch size below the rated capacity
insure more efficient mixing.
Due to relatively low water content and high
cement content and the usual absence of large
coarse aggregate, the efficient mixing of HSC is
more difficult than conventional concrete.
9
Mix Design of HSC
10
Mix Design of HSC
11
Mix Design of HSC
12
Mix Design of HSC
13
Mix Design of HSC
Transporting:
HSC can be transported by a variety of methods
and equipment, such as truck mixers, stationary
truck bodies with and without agitators, pipeline or
hose, or conveyor belts.
Each type of transportation has specific advantages
and disadvantages depending on the conditions of
use, mixture ingredients, accessibility and location
of placing site, required capacity and time for
delivery, and weather conditions.
14
Mix Design of HSC
Transporting (Pumping):
HSC is likely to have a high cement content and
small maximum size aggregate-both factors which
facilitate concrete pumping.
Pumps are available that can handle low-slump
mixtures and provide high pumping pressure.
ACI 304 provides guidance of pumping for
transporting HSC.
In the field, the pump should be located as near to
the placing areas as practicable.
17
Mix Design of HSC
Transporting (Pumping):
Pump lines should be laid out with a minimum of
bends, firmly supported, using alternate lines and
flexible pipe or hose to permit placing over a large
area directly into the forms without re-handling.
Direct communication is essential between the
pump operator and the concrete placing crew.
Continuous pumping is desirable because if the
pump is stopped, movement of the concrete in the
line may be difficult or impossible to start again.
18
Mix Design of HSC
19
Mix Design of HSC
20
Mix Design of HSC
Placing:
Since workability time is expected to be reduced,
preparation must be made to transport, place,
consolidate, and finish the concrete at the fastest
possible rate.
Delivery of concrete to the job site must be
scheduled so it will be placed promptly on arrival,
particularly the first batch.
Equipment for placing the concrete must have
adequate capacity to perform its functions
efficiently so there will be no delays at distance
portions of the work.
21
Mix Design of HSC
Placing:
There should be ample vibration equipment and
manpower to consolidate the concrete quickly after
placement in difficult areas.
All equipment should be in the first class operating
condition.
Breakdowns or delays that stop or slow the
placement can seriously affect the quality of the
work.
Due to more rapid slump loss, the strain on
vibrating equipment will be greater.
22
Mix Design of HSC
Placing:
Provision should be made for an ample number of
standby vibrators, at least one standby for each
three vibrators in use.
Selection of equipment should be based on its
capability for efficiently handling concrete of the
most advantageous proportions that can be
consolidated readily in place with vibration.
Concrete should be deposited at or near its final
position in the placement.
Buggies, chutes, buckets, hoppers, or other means
may be used to move the concrete as required.
23
Mix Design of HSC
Placing:
Proper internal vibration is the most effective
method of consolidating HSC.
Up to 5% loss in strength may be sustained from
each 1 percent void space in concrete.
Vibration almost to the point of excess may be
required for HSC to achieve its full potential.
All columns and shear walls in any given story be
placed with the same strength concrete.
For formwork economy, no changes in column size
in the typical high rise buildings are recommended.
24
Mix Design of HSC
Placing:
In areas where two different concretes are being
used in column and floor construction, it is
important that the HSC in and around the column
be placed before the floor concrete.
An unforeseen cold joint forms between the two
concretes.
Placement at a higher temperature risks a
significant reduction in the setting time due to the
heat generated by the high cement content.
Recommended temperature is 15 to 25°C.
25
Mix Design of HSC
Placing:
Below l0°C, naphthalene superplasticizers become
viscous, causing problems with their dispersion in
water, and excessive retardation may occur.
If necessary, during placement, slump should be
maintained by re-dosing with a superplasticizer
since such additions will restore workability and
usually result in an increase in compressive
strength.
26
Mix Design of HSC
Curing:
Curing is essential in the production of quality
concrete; it is critical to the production of HSC.
HSC should be water cured at an early age since
partial hydration make the capillaries discontinuous.
“Ponding” or immersion is an excellent method
wherever a pond of water can be created by a ridge
or dike of impervious earth or other material at the
edge of the structure.
Fog spraying or sprinkling with nozzles or sprays
provides satisfactory curing when immersion is not
feasible.
27
Mix Design of HSC
Curing:
Irregular sprinkling is not acceptable if drying of the
concrete surface occurs.
Soaker hoses are useful, especially on surfaces that
are vertical.
Burlap, cotton mats, rugs, and other coverings of
absorbent materials will hold water on the surface,
whether horizontal or vertical.
Liquid membrane-forming curing compounds retain
the original moisture in the concrete but do not
provide additional moisture.
28
Mix Design of HSC
Curing:
Water curing of HSC is highly recommended due to
the low water cement ratios employed.
At water-cement ratios below 0.4, the ultimate
degree of hydration is significantly reduced if free
water is not provided.
Water curing will allow more efficient, although not
complete, hydration of the cement.
A researcher reported that for low water cement ratio
concretes it is more advantageous to supply
additional water during curing than is the case with
higher water-cement ratio concretes.
29
Mix Design of HSC
Curing:
It has been from various researches that for
concretes with water-cement ratio of 0.29, the
strength of specimens made with saturated
aggregates and cured by ponding water on top of
the specimen was 850 to 1000 psi (5.9 to 6.9 M Pa)
greater at 28 days than that of comparable
specimens made with dry aggregates and cured
under damp burlap.
Others have reported that moist curing for 28 days
and thereafter in air was highly beneficial in securing
HSC at 90 days.
30
Mix Design of HSC
Finishing:
The cohesive consistency of most HSCs often makes
it "sticky," so that it is difficult to provide a smooth
trowel finish.
The surface water evaporates and these concretes
are particularly susceptible to plastic shrinkage
cracking.
The area of placement needs to be limited, finishing
operations completed, and protective covering
provided before plastic shrinkage cracking can occur.
The use of fog spray and evaporation retardants are
advantageous in reducing the rate of evaporation.
31
Mix Design of HSC
Quality assurance:
In HSC proportioning, the concrete supplier or
sampling and testing program is recommended to
assure the physical properties required.
The use of ASTM standard method for evaluation of
cement strength uniformity from a single source
(ASTM C 917) with appropriate limits will provide the
proper basis for such uniformity.
It is desirable that the aggregates and admixtures
specified in the mixture be uniform and come from
the same source for the duration of the project.
32
Mix Design of HSC
Quality assurance:
Effective coordination and control procedures
between the supplier and the contractor are critical
to the operations.
Control of the slump, time on job, mixing, and
mixture adjustments is under the jurisdiction of the
supplier.
Cement hydration, temperature rise, slump loss, and
aggregate grinding during mixing all increase with
passage of time; thus it is important that the period
between initial mixing and delivery be kept to an
absolute minimum.
33
Mix Design of HSC
Quality assurance:
The contractor must be prepared to handle, place,
and consolidate the concrete promptly as received.
The dispatching of trucks is coordinated with the
rate of placement to avoid delays in delivery.
When elapsed time from batching to placement is so
long as to result in significant increases in mixing
water demand, or in slump loss, mixing in the trucks
is delayed until only sufficient time remains to
accomplish mixing before the concrete is placed.
34
Mix Design of HSC
Quality assurance:
Equipment for direct communication between the
supply and placement locations for use by the
inspection force is essential.
The project engineer will normally advise the
contractor of the equipment that is necessary and
require him to present plans or descriptions of the
equipment for review well in advance of the start of
placement.
A competent concrete laboratory must be available
for testing the concrete delivered to the job site.
35
Mix Design of HSC
Quality assurance:
This laboratory should be inspected regularly by the
Cement and Concrete Reference Laboratory (CCRL)
and conform to the requirements of ASTM E 329.
A minimum of one set of cylinders is normally made,
with at least two cylinders cast for each test age;
that is, 7, 28, 56, and 90 days.
Backup equipment is essential, especially vibrators.
Batch mixes are reduced if placing procedures are
slowed.
For truck mixed concrete, rush hour traffic delays
can cause serious problems.
36
Mix Design of HSC
Quality assurance:
It may be desirable to reduce the elapsed time
between contact of the cement and water (mixing
and transporting), especially during warm weather.
A maximum elapsed time of one and half hours after
the cement has entered the drum until completion
of discharge is frequently specified (see ASTM C
94).
The first consideration for selecting quality control
procedures is determining that the distribution of
the compressive strength test results follows a
normal distribution curve.
37
Mix Design of HSC
40
Mix Design of HSC
43
Mix Design of HSC
44