Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
2 views60 pages

KALANGA HPP

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1/ 60

PRE- FEASIBILITY STUDY OF

KALANGA HYDROPOWER
PROJECT
(9.672 MW)

PROJECT SUPERVISOR
ER. SATYA RAM JYAKHWA
NEPAL ELECTRICITY AUTHORITY

PROJECT GROUP MEMBER


ALISON SHILPAKAR (073BCE02)
AVISEK KOJU (073BCE06)
KAMAL KARKI (073BCE16)
MUKESH SUWAL (073BCE21)
SUJAN TYATA (073BCE48)
OUTLINES
• Objectives
• Hydropower Potential in Nepal
• Problem Definition
• Stages of Hydropower Development
• Project Site Description
• Hydrological Analysis
• Design of Components
• Economic analysis
• Financial analysis

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 2


OBJECTIVES
• To perform the hydrological analysis of the project.
• To design the hydraulic components of the hydropower plant.
• To perform quantity and cost estimate of the hydropower project.
• To check the financial analysis of the project and check viability of the
project.

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 3


HYDROPOWER POTENTIAL IN
NEPAL
Theoretical Generation 83280 MW
Capacity

Economical Feasibiltiy 44000 MW from 66 feasible


Capacity sites

Likely Annual Energy Potential 190-195 Billion units


(At 50% Load factor)

Present Hydro Installed About 1045 MW


capacity

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 4


PROBLEM DEFINITION
• Suitable RoR hydropower site
• Basin Characteristics
• Hydrology governing factors
• Topography and Geology
• Design Procedures
• Suitable Site for Components
• Rate Analysis
• Feasibility

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 5


Stages Of Hydropower Development

1. Reconnaissance studies
Planning Phase 2. Pre-feasibility study
3. Feasibility study

1. Detail design and procurement


2. Construction of civil structure
Construction 3. Installation of electromechanical
and hydro mechanical
Phase equipment

Operation 1. Commissioning and start up


Phase 2. Maintainence and operation

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 6


PROJECT SITE DESCRIPTION

• Sunkuda and Khiratadi VDCs of Bajhang district of Seti Zone of Far –


Western Region, state-6 of Nepal.

License area
80˚50’45” E to
80˚54’45”E
29˚30’41” N to
29˚34’12” N

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 7


Alignment of hydropower

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 8


Phase of pre feasibility
Hydraulic
Design

• Design of Components
• Weir
• Average Rainfall • Intake • Rate Analysis
Computation • Approach Canal • Quantity / Cost
• Flow Analysis • Gravel Trap Estimate
• Flood Analysis • Settling Basin • Financial Analysis
• Forebay/Headpond
• Tunnel
Hydrological • Surge Tank Economic
• Penstock
Analysis • Anchor Block and Support Pier Analysis
• Turbine
• Powerhouse and Tailrace
• Head Calculation
• Energy Table

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 9


Hydrological Analysis
Average
Flood
Rainfall Flow Analysis
Analysis
Computation

Instantaneous
Long Term Daily Long Term Daily
Maximum and
Precipitation Discharge
Minimum Discharge

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 10


CATCHMENT AREA
Location intake powerhouse

Precipitation(mm) 1621.72 1608.966


Catchment area(sq km) 449.868 483.033

Catchment Area At intake Catchment Area At Powerhouse


04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 11
COMPUTATION OF AVERAGE
RAINFALL

Isohyetal at head work(1621.72)mm Isohyetal at Powerhouse (1608.966)mm

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 12


Flow analysis

1. Catchment Area Ratio (CAR) method

2. Water and Energy Commission Secretariat


(WECS)/Department of Hydrology method (DHM)

Q mean(month) = C x (Area of Basin)A1 x (Area below 5000m+1)A2 x (Mean


monsoon precipitation)A3
3. MIP

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 13


Hydrograph Without ppt efffect
80.000

70.000

60.000

50.000
Discharge (m3/s)

chamelia (Nayal Badi)


Seti (gopaghat)
40.000
Sailigad (Gautada)
Langur Khola (Channa)

30.000

20.000

10.000

0.000
0 2 4 6 8 10 12 14

Months

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 14


Hydrograph
90.0

80.0

70.0

60.0

50.0
Discharge

Headwork
Powerhouse
40.0

30.0

20.0

10.0

0.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13

Month

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 15


FDC at Headwork
70

60

50

40
Discharge

Design discharge Q40=12.822


30

20

10

0
0 10 20 30 40 50 60 70 80 90 100

Percentage exceedence

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 16


FDC at powerhouse
90

80

70

60

50
Discharge

40

30

20

10

0
0 10 20 30 40 50 60 70 80 90 100 110

Percentage Exceedence

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 17


FLOOD ANALYSIS
METHODS USED FOR THE ANALYSIS
Gumbel’s Extreme value distribution
Log Pearson type III
Log Normal
Normal
Pearson III

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 18


HIGH FLOOD PROBABILTY GRAPH
HIGH FLOOD ANALYSIS AT INTAKE
350.0

300.0

250.0
Discharge (m3/s)

200.0

150.0

100.0

STANDARD ERROR
50.0 log Pearson log Pearson
gumbel normal
III normal III
6.2254 9.4180 12.3930 14.7872 8.9006
0.0
0 100 200 300 400 500 600 700 800 900 1000 1100

Time in Years
gumbel log pearson iii log normal normal pearson

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 19


HIGH FLOOD PROBABILTY GRAPH
HIGH FLOOD ANALYSIS AT POWER
350.0

300.0
Discharge (m3/s)

250.0

200.0

150.0

100.0
STANDARD ERROR
50.0 log Pearson
gumbel log normal normal
pearson III III
6.6918 10.1235 13.3214 15.8949 9.5674
0.0
0 100 200 300 400 500 600 700 800 900 1000 1100

Time in Years
gumbel log pearson iii log normal
normal pearson

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 20


LOW FLOOD PROBABILITY GRAPH
LOW FLOW ANALYSIS AT INTAKE
7.0

6.0

5.0
Discharge (m3/s)

4.0

3.0

2.0

1.0

0.0
0 100 200 300 400 500 600 700 800 900 1000 1100

Time in Years
gumbel log pearson iii log normal normal

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 21


RATING CURVES
1.6
Rating Curve at Headwork

1.4

1.2

1
Stage

0.8
River bed level= 1072 masl
0.6 Depth of River = 1.205m
HFL at intake= 1073.205 masl
0.4
Flood Discharge = 212.33 m3/s (100 years)
0.2

0
0 1 2 3 4 5 6 7 8

DIscharge

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 22


Rating curve at Power house
1.6

1.4

1.2

1
Stage

0.8

0.6
River bed level= 974 masl
0.4
Depth of River = 1.153m
HFL at power house= 975.153 masl
0.2 Flood Discharge = 228.24 m3/s (100 years)

0
50 100 150 200 250 300 350

Discharge

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 23


Hydraulic Design of Components
WEIR
DESIGN RESULTS
Type Ogee shaped
Length*Height 40*4 m
Design Discharge for the Weir 212.34 m3/s
Crest Level 1076masl
River Bed Level 1072masl

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 24


SECTION OF WEIR

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 25


UNDERSLUICE

DESIGN RESULTS OF UNDERSLICE


Gate Type Vertical
No of Opening 1
Gate Opening (B*H) 3*3m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 26


INTAKE AND TRASH RACK
INTAKE DESIGN RESULTS
Type Side Intake
Profile Bell Mouth Profile
No of Opening 3
Size of each Opening (B*H) 3m*2 m
Intake Discharge 15.384m3/s

TRASH RACK DESIGN RESULTS


Thickness 10 mm
Bar Spacing 100 mm
Inclination with Vertical 15 degree

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 27


PLAN AT HEADWORK

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 28


STILLING BASIN
DESIGN RESULTS OF STILLING BASIN
Type USBR Type II
Length 14 m
Depth before jump 0.50009 m

Depth after Jump 3.148 m


Normal depth 3.06 m
Critical Depth 1.42 m
Jump level 1074.869
Tail water level 1074.783

19/06/2077
04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 29
GRAVEL TRAP
DESIGN
CONSIDERATIONS
Particle Size to settle >2 mm
Specific Gravity 2.65
Longitudinal slope 1 in 50

DESIGN RESULTS
Type Gravity Continuous
Flushing
Size (L*B*H) 21 * 5.2 * 4m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 30


04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 31
APPROACH CANNAL
DESIGN CONSIDERATIONS
Bed slope 1 in 1000
Manning’s coefficient 0.017
Free board 0.5 m

DESIGN RESULTS
Type Rectangular Open Channel

Size (B*H) 5.2 m*3.1 m


Length 120.718 m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 32


SETTLING BASIN

DESIGN CONSIDERATIONS
Diameter of particle to be >0.2 mm
removed
Value of constant “a” 0.44

Length/ Breadth 4
Velikanov’s constant, λ 1.5

Packing factor 0.5


Sediment Concentration 5 kg/m3

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 33


SETTLING BASIN

DESIGN RESULTS
Type Hopper Bottom
Size of each bay (L*B*H) (75m*10.5m*8)m
No of bays 2
Flushing system Intermittent System
EFFICIENCY
Hazen’s Method 88.8%
Vetter’s Method 91.4%

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 34


SETTLING BASIN

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 35


HEADPOND

DESIGN CONSIDERATIONS
Construction design discharge 12.822 m3/s
Detention time 2 minutes
Limiting velocity 0.2 (0.2 -0.8)m/s
Storage depth 1m
Free board 0.5 m
RESULTS
Volume 1538.640 m3
Submergence head 1.5 m
L*B*H (13*21.5*11)m3

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 36


TUNNEL
Design Consideration
Manning's Coefficient 0.017
Project Life 30 years
Interest Rate 10%
0.16%
Bed Slope (1:600)
RESULTS
Type of flow Pressure flow
R1.45 Geometry Inverted D-shape
Length 4200m
Diameter 2.9m
1.45

Velocity 1.708m/s
2.9
04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 37
TUNNEL OPTIMIZATION
80

70

60
Incremental Cost (In Million NRS)

50

40

30

20 Optimized tunnel diameter=2.9m


10

0
0 1 2 3 4 5 6 7

Tunnel Diameter(m)

Total Construction Cost(in Miliions) Energy Loss Cost(in Miliions)


Total Cost (in Millions optimized

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 38


Cross section at tunnel alignment

Tunnel layout
04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 39
SURGE TANK
DESIGN CONSIDERATIONS
Length of tunnel 4200m
Wave velocity in 897.81m/s
penstock
Time of oscillation 399.464second
Friction factor in 0.017
tunnel
Submergence for 4.45 m
penstock
Freeboard 2m
NWL of Fore bay 1075.992 masl

RESULT
Type Vertical Cylindrical, open
Diameter 9.5 m
Height 21 m
Zmax up 9.19 m
Zmax down 4.18 m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 40


OPTIMIZATION OF PENSTOCK
DESIGN CONSIERATIONS

Penstock Optimization Pipe Roughness 0.025


90000000 Cost of pipe per kg 200 Rs/ kg
80000000 Interest rate 10%
70000000 Project life 30 years
60000000 Allowable hoop 1200 kg/cm2
50000000 stress
Cost NRs

40000000 Efficiency 0.85


30000000 Wet energy cost per 4.8 Rs./ Kwhr
unit
20000000
Dry energy cost per 8.4 Rs./ Kwhr
10000000

0
1 1.5 2 2.5 3 3.5 4 RESULT

Daiameter Optimum diameter 2.3m

Cost of penstock Thickness 1.5 cm


Energy loss cost
Velocity 3.09 m/s
Total
Length 298. 654m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 41


PENSTOCK ALIGNMENT

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 42


TURBINE SELECTION & EFFICIENCY

No of turbine Rated flow per Minimum flow Discharge ratio Turbine


turbine Efficiency
1 12.822 6.268 0.48 74
2 6.411 6.268 0.977 86
3 4.247 6.268 1.466 84

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 43


TURBINE
DESIGN CONSIDERATIONS
Type Francis, reactive
Numbers 2
No. of poles 8
Frequency 50 Hz
Width to Diameter 0.25
ratio(0.1-0.4)

Hydraulic Efficiency 0.89 RESULT


DRFT TUBE Diameter of runner 1m
Specific speed 230.259
Outlet Rectangle
Rotational speed 750
Efficiency of turbine 0.8
Setting height 3.38 m below
TWL

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 44


POWERHOUSE AND TAILRACE
POWERHOUSE

Size 29.7m*10. 6
m*20m

TAILRACE CANAL

Length of tailrace canal 140m

Flow type Open channel

Width 3.6 m

Height 2.2 m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 45


04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 46
HEAD CALCULATION

Head Calculation
NWL at Intake 1076 masl

NWL at Headpond 1075.759 masl

Tunnel Head Loss 3.824 m

Static water level at Surge Tank 1072.331 masl

Penstock Head Loss 1.23 m

Gross Head 96 m

Net Head 90.464 m

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch)


47
ENERGY TABLE

Power and Energy Details


Gross Head 96 m

Net Head at design Flow 90.464 m


Installed Capacity 9.672 MW
Dry Saleable energy 12.91 Gwhr
Wet Saleable Energy 47.90 Gwhr
Anuual Saleable Energy 60.81 Gwhr
Dry Season Revenue 108.43 NRs. in Million
Wet Season Revenue 229.94 NRs. in Million
Gross Annual Revenue 338.36 NRs. in Million

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch)


48
Economic Analysis

 Rate Analysis
 Quantity / Cost Estimate
 Financial Analysis

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 49


RATE ANALYSIS
S.N. Description Unit Rate (NRs.)
1 Earthwork in Filling cum 728.065
2 Earthwork in Excavation in Ordinary Soil cum 50.152
3 Earthwork in Excavation in Soft Rock cum 651.47
4 Earthwork in Excavation of Hard Rock cum 575.89
5 Stone Soling cum 6997.98
6 (Dry) Stone Masonry cum 9802.7
7 Plum Concrete cum 9393.33
8 Reinforcement Work MT 136017
9 Formwork sq. m 658.32
10 Filling With Gravel cum 1826.78
11 Plain Cement Concrete (P.C.C.) M10 (1:3:6) cum 28917.5
12 Plain Cement Concrete (P.C.C.) M20 (1:1.5:3) cum 11946.1
13 Plain Cement Concrete (P.C.C.) M25 (1:1:2) cum 13046.63
14 Plain Cement Concrete (P.C.C.) M15 (1:2:4) cum 10113.48
15 Reinforced Cement Concrete (R.C.C.) M25 cum 13329.38
16 Reinforced Cement Concrete (R.C.C.) M35 cum 13705.99
17 Supply and Laying of Boulder Riprap cum 1936.6
18 12.5 mm thick plaster work Sq. m 3752.79
19 First Class Brick Work cum 13979.05
20 Stone Masonary with Cement cum 10378.62
04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch)
50
BOQ
Summary
Description Amount
Amount
Weir 119172957.7
Undersluice 936810.9442
Intake 7348249.24
Weir
Flood Protection work 50410127.38 1% Undersluice
6% Intake
12% 0%
Gravel Trap 6650139.158 4%
1% Flood Protection work
Gravel Trap
Approach Canal 13507446.85 7%
5% Approach Canal
1%
Settling Basin
Settling Basin 116619505.7 3%
1%
Headpond
2%
Tunnel
Headpond 14191513.71 Surge Tank
12% Penstock
Tunnel 424512196.7 Anchor Block and support
piers
Surge Tank 15618093.09 Powerhouse
Tailrace
Penstock 32662854.15 1%
Total Earthwork
Anchor Block and support piers 73009821.7
43%
Powerhouse 35914890.32
Tailrace 7552190.47
Total Earthwork 60393663.84
TOTAL IN NRS. 978500460.9
KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 51
04/03/2021
BOQ
Results

Sector Amount (NRs.) Remarks

Total Civil Cost 978500460.9

Hydromechanical Cost 78631702.6 5% of base cost 12%


2
Electromechanical Cost 333684000 Dollar 300 per KW % 4%
Total Civil Cost
Transmission and
9785004.609 1% of Civil Cost Hydromechanical Cost
Substation 8% Electromechanical Cost
Transmission and Substation
Contingencies 157263405.2 10% of base cost 1 52% Contingencies
%
EIA
Sub-Total Cost 1557864573 Development and Super-
vision
18% VAT Amount (13%)
2% of Sub-total
EIA 31157291.47
Cost
Development and 5% of Sub-total 4%
77893228.66
Supervision Cost
Total Cost 1666915093

VAT Amount (13%) 216698962.1

Total Financial Cost 1883614056

KHWOPA COLLEGE OF ENGINEERING (073BCE Batch)


04/03/2021 52
FINANCIAL ANALYSIS
Basic Data
Basic Data Value Unit Remarks
Installed Capacity 9.672 MW MW
Salable Dry Energy 12.91 Gwhr
Salable Wet Energy 47.9 Gwhr
Total Salable Energy 60.81 Gwhr
Total Equity 565084217 NRs.
Total Debt 13185298.39 NRs.
Total Financial Cost 1883614056 NRs.
Bank Fee 13185298.39 NRs. 1% of Debt Cost
Interest During Construction 1331852984 NRs.
Grand Total 2028652338 NRs.
Construction Period 3 Years
Dry Season Energy Sale Price 8.4 NRs.
Wet Season Energy Sale Price 4.8 NRs.
Escalation Parameter
Inflation of Foreign Currency 3%
Inflation of Local Currency 3.50%
Escallation on Dry Season Benefit 3% upto 1st 8 years
Escallation on Wet Season Benefit 3% upto 1st 8 years
04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 53
FINANCIAL ANALYSIS
Basic Data
Financial Parameter
Interest Rate on Debt 10%
Expected Rate of Return 12%
Equity Investment 30%
Loan Duration 12 Years
Financial Analysis Duration 30 Years
Tax Parameter
0% for 7 years
Corporate Tax 12.50% for next 3 years
25% after first 10 years
Operation and Maintenance 1.50% of total construction
Insurance Cost 0.50% of total cost
Bonus and Welfare Fund 3% of Net Profit
150 NRs./KWfor 1-15 years
Royalty on Capacity
1200 NRs./KWfor 16-30 years
1.85% for 1-15 years
Royalty on Revenue
10% for 16-30 years
Increment on O/M cost 5%

KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 54


04/03/2021
FINANCIAL ANALYSIS
Description Value Unit
Internal Rate of Return (IRR) 18.01%
Simple Payback Period 5.76 Years
NRs. In
Net Present Value of the Project 547.44
Million
NRs. In
PW of O& M 312.72
Million
NRs. In
PW of Revenue 2516.70
Million
NRs. In
PW of Expenses 1408.65
Million
Simple B/C ratio 1.26
Modified B/C ratio 1.41
NRs. In
Cost per MW Power Generation 211.7
Million

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 55


SENSITIVITY ANALYSIS
Total Cost Total Cost
Annual Revenue IRR Annual Revenue NPV
Interest Rate
Interest Rate 1,200.00
30.00%
1,000.00
25.00%
800.00

NPV variation
20.00%
600.00
IRR variation

15.00% 400.00

10.00% 200.00

5.00% 0.00
-25% -20% -15% -10% -5% 0% 5% 10% 15% 20% 25%
-200.00
0.00%
-25% -20% -15% -10% -5% 0% 5% 10% 15% 20% 25% Percentage change
Percentage change
Total Cost
Annual Revenue B/C Ratio Total Cost
Interest Rate Annual Revenue
Payback Period
2.50 Interest Rate
14.00
2.00 12.00
Payback period variation
B/C ratio variation

10.00
1.50
8.00
1.00 6.00

4.00
0.50
2.00
0.00
-25% -20% -15% -10% -5% 0% 5% 10% 15% 20% 25% 0.00
-25% -20% -15% -10% -5% 0% 5% 10% 15% 20% 25%
Percentage change
Percentage change

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch)


56
CONCLUSION
• Design Discharge(Q40) = 12.822m3/s
• High Flood Discharge (100 years) = 212.34 m3/s
• Tunnel Length = 4200m of 2.9m diameter Inverted-D with 1
audit tunnel at midway of same diameter
• Surge tank = 21 m ht. of 9.5m diameter
• Penstock length = 298.654m of 2.3m diameter
• Net head = 90.464m
• Turbine = francis, 2 units
• Power generated = 9.6 MW
• Overall project cost = 2047885163NRs.
• Project feasibility = Feasible with modified B/C ratio of 1.32
• Project highly sensitive towards change in revenue generation.
04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch)
57
RECOMMENDATION
• Surface geological mapping and sub-surface geological investigation
should be carried out.
• A physical hydraulic modeling of the head work, its performance in
all different flow condition.
• EIA should be carried out for project more than 5 MW. So EIA must
be conducted in this project.
• Local Participation should be encouraged.
• Rain gauge and discharge measurement instrument should be set up

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 58


REFERENCES

• Keshav Prasad Sharma and Naba Raj Adhikari, Hydrological Estimations in Nepal
Main Report and Appendix I, His Majesty Government of Nepal, Department of
Hydrology and Meterology, June 2004

• Dulal, Dr. K.N, Baral, Er. Sanjeeb, Engineering Hydrology, 1st edition, Engineering
and Educational Services Pvt. Ltd., Kathmandu

• Subramanya, K. (2011). Engineering Hydrology. New Delhi: Tata McGraw Hill


EducationPrivate Limited.

• DHM (Department of Hydrology and Metrology ), Nagpokhari ,Kathmandu Nepal

• Civil works guidelines for micro hydropower in Nepal - Practical Action

• Micro-Hydro design manual, Adam Harvey


04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 59
Thank you!!

04/03/2021 KHWOPA COLLEGE OF ENGINEERING (073BCE Batch) 60

You might also like