Unit Overhaul
Unit Overhaul
Unit Overhaul
NTPC/VINDHYACHAL
TYPE OF OVERHAUL
PERIOD OF OVERHAUL
FREQUENCY
A X D
20 DAYS 21 DAYS
GENERATOR ROTOR THREAD OUT BOILER & AUX. 35 DAYS ALL TURBINE CYLINDERS O/H GENERATOR ROTOR THREAD OUT
NTPC/VINDHYACHAL
TYPE OF OVERHAUL
PERIOD OF OVERHAUL
FREQUENCY
E F G
BOILER & AUX. TUR. BRGS. INSPECTION BOILER & AUX. LP TURBINE INSPECTION
15 DAYS 25 DAYS
BOILER & AUX. 35 DAYS HPT / IPT O/H GENERATOR ROTOR THREAD OUT
NTPC/VINDHYACHAL
TO CONTROL THE O&M COST FOLLOWING ARE THE ACTIONS: SEQUENCE OF O/H FOR THE STATION ARE SO ADJUSTED THAT NOT MORE THAN TWO MAJOR O/Hs (TYPE D) TAKEN UP IN A YEAR. WHENEVER TWO MAJOR O/H COMMENCES IN A STATION IN A YEAR, SITE TAKES DECISION, DEPENDING ON BOILER CONDITIONS, TO RESTRICT THE O/H DURATION OF BOILER SUITABLY TO 17 DAYS AND 15 DAYS FOR 200 MW AND 500 MW UNITS RESPECTIVELY.
NTPC/VINDHYACHAL
TO MINIMIZE MAINTENANCE COST THROUGH OPTIMIZATION OF RESOURCE UTILIZATION TO CREATE SAFETY IN WORK, EQUIPMENT AND ENVIRONMENT
NTPC/VINDHYACHAL
TO IMPROVE AVAILABILITY OF EQUIPMENT & SYSTEM TO IMPROVE QUALITY & INSPECTION OF MAINTENANCE JOBS TO IMPROVE MONITORING & REPORTING OF O/H PROGRESS TO REDUCE OVERHAUL DURATION
TO IMPROVE THE RE-COMMISSIONING INTERFACE TO PROVIDE A RECORD OF WORK CARRIED OUT TO MINIMIZE ISOLATION RESTRICTIONS TO REDUCE DUPLICATION OF ENGINEERING EFFORTS TO ENSURE STATUTORY REQUIREMENT OF BOILER LICENCE
NTPC/VINDHYACHAL
PLANNING UNIT SHUT DOWN COOLING DOWN OF MACHINES DISMANTLING INSPECTION FOR CONDITION REPAIR & RECTIFICATION ASSEMBLY TESTING & INSPECTION REVIVAL OF EQUIPMENT & SYSTEM REVIVAL & RECOMMISSIONING OF UNIT
NTPC/VINDHYACHAL
ULTIMATELY LEADING TO IMPROVEMENT IN PLANT AVAILABILITY, RELIABILITY & REDUCTION OF O&M COST
NTPC/VINDHYACHAL
NTPC/VINDHYACHAL
PRE OVERHAUL
ACTIVITIES
NTPC/VINDHYACHAL
NTPC/VINDHYACHAL
CONTD
IDENTIFICATION OF CRITICAL MATERIALS REQUIRED FOR UNIT OVERHAULS AND REVIEW ON MONTHLY BASIS. PREOVERHAUL MEETING FOR REVIEW OF CONSTRAINTS & PREPAREDNESS INVOLVING ALL. PRE OVERHAUL CONDITION MONITORING REPORT PREOVERHAUL UNIT SURVEY UNIT OUTAGE ANALYSIS FROM LAST OVERHAUL FEED BACK OF UNIT FROM FIRST SYNCHRONIZATION REVIEW OF STATUS & COORDINATION OF WELDING SUPPLY, LIGHTING, LIFTS, HOISTS, CRANES ETC.
NTPC/VINDHYACHAL
CONTD
PAST OVERHAULS AT A GLANCE (HISTORY OF UNITS) PREPARATION OF MILESTONES (PLANNED) COMPILATION OF UNIT DEFECT LIST PRE OVERHAUL SPRAY VALVES CHARACTERISTICS
OPERATION REQUIREMENT EFFICIENCY REQUIREMENT CHEMISTRY REQUIREMENT TRIPPING COMMITTEE RECOMMENDATIONS C&I REQUIREMENT
NTPC/VINDHYACHAL
CONTD
BOILER TUBE LEAKAGE COMMITTEE RECOMMENDATIONS OS RECOMMENDATIONS CONDITION MONITORING GROUP RECOMMENDATIONS
SAFETY REQUIREMENT
R&M REQUIREMENT
PREPARATION OF:
PTW & CLEARANCE BOOKS FOR BOILER & AUX.
PTW & CLEARANCE BOOKS FOR TG & AUX. CLEARANCE & RECOMMISSIONING BOOK FOR VALVES, DAMPERS, IGVs, SOOT BLOWERS & LRSBS
NTPC/VINDHYACHAL
CONTD... CHECK SHEET FOR MOTOR TRIALS, EQUIPMENT RECOMMISSIONING & PROTECTION CHECKING CHECK SHEET FOR VALVES REQUIRED FOR CONDENSER FLOOD TEST CHECK SHEET FOR VALVES REQUIRED FOR BOILER HYDRO TEST COMMUNICATION LOG BOOK
NTPC/VINDHYACHAL
PREPARATION OF DISPLAY BOARD FOR COMMUNICATION OF OVERHAUL PLANNING COORDINATION IN ISSUE OF PERMITS
NTPC/VINDHYACHAL
MONITORING & REVIEW OF CRITICAL VALVES STATUS AS PER CHECK SHEETS REQUIRED FOR CONDENSER FLOOD TEST & BOILER HYDRO TEST MONITORING & REVIEW OF CLEARANCES AVAILABLE & RECOMMISSIONING PROGRESS ( MOTORS TRIALS / EQUIPMENT TRIALS) COORDINATION IN FURNACE AIR TIGHTNESS TESTS CONDENSER FLOOD TESTS BOILER HYDRO TESTS
NTPC/VINDHYACHAL
PREPARATION OF UNIT-WISE UNIT OVERHAUL REPORT IN BOOK FORM HARD COPY FOR LIBRARY & ISO PREPARATION OF UNIT OVERHAUL REPORT IN CDFORMAT
NTPC/VINDHYACHAL
PROCESS IMPROVEMENTS
BOILER EXTERNAL WATER WASHING WAS CAUSING DAMAGE TO INSULATION AND DELAY IN START OF OVERHAUL ACTIVITIES, DRY BOILER CLEANING STARTED. QUICK ERECT SCAFFOLDING IS BEING USED FOR BOILER INTERNAL CLEANING & INSPECTION
NTPC/VINDHYACHAL
PROCESS IMPROVEMENTS
CONDENSER TUBE CLEANING IS BEING DONE USING CONCO BULLETS INVOLVEMENT OF FQA IS INCREASED IN MAIN TURBINE & GENERATOR AREA
NTPC/VINDHYACHAL
ADDITIONAL RESPONSIBILITIES
DRAWING SECTION: O&M DRAWING SECTION IS PIONEER IN DEVELOPMENT OF DRAWINGS IN AUTO CAD. MANPOWER : TWO DRAFTMENTRAINED IN AUTO-CAD PRINT ROOM: O&M PRINT ROOM COPE UP THE DAY TO DAY REQUIREMENT OF PHOTCOPYING, CYCLOSTYLLING & AMMONIA PRINTING OF DRAWINGS REQUIRED FOR INDENTING PURPOSES. MANPOWER: ONE ATTENDANT
NTPC/VINDHYACHAL
UNIT OVERHAUL REPORTS: INSPITEOF ALL BEST POSSIBLE EFFORTS, PROBLEM IS BEING FACED TO GET THE FEEDBACK FROM OTHER DEPARTMENTS FOR THE JOBS COMPLETED, MEASUREMENTS TAKEN AND EXPENDITURE INCURRED DURING UNIT OVERHAULS, WHICHCAUSES DELAY IN COMPILATION OF UNIT OVERHAUL REPORTS. OVERHAUL COST: PRESENTLY IT IS DIFFICULT TO GET THE FINANCIAL DATA i. e. UNIT OVERHAULS COST (THE EXPENDITURE INCURRED DURING RESPECTIVE UNIT OVERHAULS). CONTINUOUSLY THESE DATA ARE BEING ASKED BY CC & WR. ISSUE OF MATERIALS: MATERIALS PROCURRED FOR UNIT OVERHAULS MUST BE TAGGED BY STORES AND NOT TO BE ISSUED TO ANY OTHER DEPARTMENT WITHOUT CONSENT.
NTPC/VINDHYACHAL