Armin Krimpmann

1
Progress and Cost Monitoring Process
Case Study: BARWA Commercial Avenue

1. Project Key Facts
2. Data Processing Concept
3. Monitoring Process
4. Visualization
5. Conclusion

2

Armin Krimpmann

2
Barwa Commercial Avenue
8.5 km long
912,000 m2
18,500 rooms
Schedule has
30,000 activities
• BOQ for the
finishing works has
600,000 entries
•
•
•
•

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

3
Data Handling
Client

Subcontractor

PM/CM

Data

Project

Project Key Facts

Other
Stakeholders

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

4
Data Processing

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

5
3.

Data Flow

Bill of
Quantity

Room
Quantities

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

6
Weekly Progress Monitoring Finishing

BIS
GIS
Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

7
Payment / Cost Loading

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

8
Performance Values

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

9
Quantities

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

10
Quantities assigned to Activities

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

11
Quantities over Time

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

12
Visualization

Project Key Facts

Data Process Concept

Monitoring

Visualization

Conclusion
Armin Krimpmann

13
Conclusion

Armin Krimpmann

14