Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
SlideShare a Scribd company logo
A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Bull Neck Run Stream Restoration Project
Pardon Our Dust Meeting
May 2, 2018
Stormwater Planning Division
Community Meeting: Pardon our Dust
• Project Background
– Background
– Major Project Elements
• Construction Timeline Summary
• Project Schedule/Phasing, Site Access, Construction Equipment
• Example photos
• Safety During Construction
• Q&A
2
Stormwater Planning Division
Project Location
3
Stormwater Planning Division
Project Limits
4
Restoration Reach:
• 1,910 Linear Feet
• Extends to pedestrian
bridge
• Runs through FCPA and
Spring Hill Farm HOA
property
Stormwater Planning Division
Project timeline
5
• Fall, 2013: Project initiated
• Winter, 2013: Surveys and assessment completed
• April, 2014: Pre-concepts submitted
• June 18, 2014: First public meeting
• October, 2014: Final concept submitted
• April, 2015: Additional scope for final design developed and approved
• June 15, 2015: Second public meeting
• March, 2016: Final design completed
• November, 2017: Project authorized for construction
• March, 2018: Bid Opening – awarded to Resources Environmental Services, LLC
• July, 2018: Anticipated construction start date
• July, 2019: Anticipated substantial completion date
6
Scope of Work
Stormwater Planning Division
Stormwater Planning Division
Construction Entrance and Access
7
• Existing Gated Areas
• Cross Existing Spillway
• Upslope of Soccer Field
• Existing Cleared Area
Stormwater Planning Division
Construction Access
8
• Upslope of
Soccer Field
• Existing Cleared
Area
• Staging and
Stockpile
Stormwater Planning Division
Construction Access
9
• Timber matting
along the
length of the
access route
• Orange fencing
around the site
Stormwater Planning Division
Reach 1 Upper (Existing)
10
Stormwater Planning Division
Reach 1 Upper (Proposed)
11
• Tie into stable
reach
• Regenerative
Design
• Restore Historic
Fill
CONSTRUCTION ACCESS
Stormwater Planning Division
Step Pool and Cascade (Proposed)
12
Stormwater Planning Division
Tributary 3 and 4 (Existing)
13
Stormwater Planning Division
Tributary 3 and 4 (Proposed)
14
• Removal of Fill
• Regenerative Design (Trib 3)
– Grade Control
• Fill on Grade (Trib 4)
• Connect to Main Stem
Stormwater Planning Division
Regenerative Stormwater Conveyance
15
Stormwater Planning Division
Reach 2 (Existing)
16
Stormwater Planning Division
Reach 2 (Proposed)
17
• Downstream of
Tributary 3&4 Tie In
• Extend to Tributary 1
Confluence
• Bridge and Trail to
remain open outside
of active construction
hours
BRIDGE AND TRAIL
Stormwater Planning Division
Tributary 1 (Proposed)
18
• Step Pool System with Grade Control
• Trail to be temporarily closed when work is
done for Trib 1, otherwise it will remain open
BRIDGE AND TRAIL
Stormwater Planning Division
Reach 3 (Existing)
19
SPRINGHOUSE
Stormwater Planning Division
Reach 3 (Existing)
20
Stormwater Planning Division
Reach 3 (Proposed)
21
• Access Along Left Bank to Crossing Point
• One Pattern Realignment Section
• Bankfull Channel Shaping with Instream Structures
Stormwater Planning Division
Reach 4 (Existing)
22
Stormwater Planning Division
Reach 4 (Proposed)
23
• Toe Protection
and Bench at
Existing Rip Rap
• Boulder Toe Fill
at Downstream
Steep Bank
• Temporary trail
to be installed
during active
construction
NEW TRAIL ALIGNMENT
Stormwater Planning Division
Boulder Toe (Proposed)
24
DPWES Stormwater Planning Division
Stream Structures and Bed Reinforcement
25
Reinforced Bed
Step Pools Cross Vanes
Stormwater Planning Division
Revegetation - Trees
26
Stormwater Planning Division
Revegetation – Native Seed Mix
27
Stormwater Planning Division
Proposed Schedule
• Notice to proceed expected to be issued to Resources Environmental Services,
LLC. in June, 2018
• Project duration: 365 calendar days (<12 months)
• Example construction schedule above
• Contractor will submit final schedule for approval
• Permit required stream restoration monitoring by County: 3 Years
• Vegetation Monitoring and Maintenance by County: 3 Years
28
Stormwater Planning Division
Construction Access Photos
29
Access road with timber
matting and tree
protection area
Stockpile area
Stormwater Planning Division
Construction Equipment Examples
30
Track truck
Excavator
Stormwater Planning Division
Construction Times
• Our construction times comply with the Code of Fairfax Noise
restrictions (Section 108-4)
• No construction activities:
– Between 9:00 pm and 7:00 am
– Before 9:00 am on Sundays
– Before 9:00 am on Federal holidays
31
Stormwater Planning Division
Dead Run – Stream Restoration
32
Stormwater Planning Division
Dead Run –Stream Restoration
33
August 2014
January 2010
Pre-Construction Construction
Post Construction After plant establishmentPost-Construction
Stormwater Planning Division
Examples – Big Rocky Run Tributary
34
Stormwater Planning Division
Examples – Rabbit Branch
35
Pre-Construction Construction
Post-Construction 8 Months After Construction
36
Safety During Construction
• Contractor is required to comply with Fairfax County’s
Construction Safety Resolution.
• For all residents, keeping safe means following two
simple rules:
1. Please stay outside the construction limits at all times!
2. Observe construction activities from a safe distance.
Stormwater Planning Division
Additional Information
For additional information, please contact
www.fairfaxcounty.gov/dpwes
Stormwater Planning Division 37
Vivian Bui, Project Manager
Matt Meyers, Branch Chief
Watershed Projects implementation Branch - North
703-324-5500
Vivian.Bui@fairfaxcounty.gov
Matthew.Meyers@fairfaxcounty.gov
703-324-5500, TTY 711
www.fairfaxcounty.gov/publicworks/stormwater

More Related Content

Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018