Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
SlideShare a Scribd company logo
Earned Value Management
Make critical project decisions
utilising the “early warning” signs
based on data, variances & trends
Anand Subramaniam
2
“Be not afraid of flying. Angels live in the
clouds and the devil on the earth.”
- Greg Evans
3
Highlights
 Current Project Challenges
 Earned Value – Overview
 Earned Value – Definitions
 Earned Value – Metrics
 Earned Value - Variance & Management Reserve
 Earned Value – Examples (including Revised Estimates)
 Earned Value – Criteria
Current Project Challenges
5
Current Project Management - Challenges
Project
Challenges
Project
Challenges
Whether the
project funds
were spent on
the right tasks
Whether the
project funds
were spent on
the right tasks
Project status
with regard to
cost & schedule
Project status
with regard to
cost & schedule
Ahead or
behind
schedule
Ahead or
behind
schedule
Apportioned effort
due to another
work package
Apportioned effort
due to another
work package
Value for
money
Value for
money
Estimated
elapsed time
Estimated
elapsed time
Cost and
schedule
variance over
time
Cost and
schedule
variance over
time
The budgeted cost
of the work
quantifies the
accomplishment
The budgeted cost
of the work
quantifies the
accomplishment
Level of effortLevel of effort
Know over or
under spent
Know over or
under spent
Earned Value - Overview
7
EV - Why & What
Why
Provides an “early warning” signs
for prompt corrective action
Provides an uniform unit of measure
(dollars or work-hours)
Requires different measures of
progress for different types of tasks
Need to consolidate progress of
many tasks into an overall project
status
Why
Provides an “early warning” signs
for prompt corrective action
Provides an uniform unit of measure
(dollars or work-hours)
Requires different measures of
progress for different types of tasks
Need to consolidate progress of
many tasks into an overall project
status
What
Utilising Project Management
methods, practices, process & tools
Accurate definition of the defined
deliverable(s), timeframe & total
cost (direct & indirect) to deliver the
product
Detailed tasks / activities and work
not in the WBS is out-of-scope
Baseline of budget control a/c,
schedule, work measurement by
Control Account (hours, $, unit)
What
Utilising Project Management
methods, practices, process & tools
Accurate definition of the defined
deliverable(s), timeframe & total
cost (direct & indirect) to deliver the
product
Detailed tasks / activities and work
not in the WBS is out-of-scope
Baseline of budget control a/c,
schedule, work measurement by
Control Account (hours, $, unit)
8
EV – Benefits
Benefits
Helps to make critical project
decision based on actual vs.
budget cost, variance, trends & to
predict future performance
Helps to make critical project
decision based on actual vs.
budget cost, variance, trends & to
predict future performance
Provides infor about the project in
terms of accomplishment as well as
how much has been spent to-date
Provides infor about the project in
terms of accomplishment as well as
how much has been spent to-date
Project’s final cost
and delivery date
with certainty
Project’s final cost
and delivery date
with certainty
Improves vendor /
customer relations
Improves vendor /
customer relations
Useful to make
prediction based on
comparative analysis
Useful to make
prediction based on
comparative analysis
Improves project
performance
Improves project
performance
Identifies the problem,
by analysing the data
captured
Identifies the problem,
by analysing the data
captured
Creates a culture
of openness, trust
and honesty
Creates a culture
of openness, trust
and honesty
Value for moneyValue for money
9
EV – Criticism
 Time required for data measurement and
manipulation can be considerable
 Quantifying / measuring work-in-progress
(WIP) can be challenging
 Integration of financial expenditure
information with schedule status
10
Note…
 Adhere to Project Management Best-Practices
 Baseline your schedule
 Analyse variance from your expectations
 Diligently update your schedule and expenditure
 Understand work products produced by the project
 Organize your estimation and schedule around work
products
 Do not re-baseline unless there is a formal,
approved change in scope
EV – Definitions
12
Definition
Planned Value
(PV)
Planned expenditure
cash flows based on
the completion of
tasks in accordance
with the project’s
budget and schedule
Planned cost of the
total amount of work
scheduled to be
performed by the
milestone date
Actual Cost
(AC)
Actual Project
Expense based on
completed tasks
Cost incurred to
accomplish the work
that has been done
to date
Earned Value
(EV)
The amount of the
budget that should
have been spent for
a given amount of
work completed
The planned (not
actual) cost to
complete the work
that has been done
13
Definition
How much
was planned to
have been
accomp-lished
at a given point
in time?
Planned
Value (PV)
How much value
(person-hours)
in terms of base
budget & what
has been
accomplished at
a given point in
time?
Earned
Value (EV)
How much was
actually spent
at a given point
in time?
Actual Cost
(AC)
14
Definition (Contd.)
What is the
total project
expected to
cost?
Estimate at
Completion (EAC)
or revised
estimate (LRE)
EAC = AC + ETC
What is the
expected
under / over
spend?
Variance at
Completion (VAC)
VAC = BAC - EAC
What is the
expected to
complete
the project?
Estimate to
Completion
(ETC)
What was the project supposed to cost = Budget at Completion (BAC)
15
Earned Value – AC, PV, EV
Cost
Time
A
ctual
Planned
Earned
Planned Value: what the
plan called for on the tasks
planned to be completed by
this date
Planned Value: what the
plan called for on the tasks
planned to be completed by
this date
Today
Earned Value: value (cost) of
what has been accomplished
to date, per the base plan
Earned Value: value (cost) of
what has been accomplished
to date, per the base plan
Actual Cost: what has
been actually spent to
this point in time
Actual Cost: what has
been actually spent to
this point in time
16
Earned Value – Cost / Schedule + or -
Cost
Time
Actual
Planned
Earned
Over BudgetOver Budget
Behind ScheduleBehind Schedule
Today
EV – Metrics
18
Cost Metrics
Cost Variance (CV)
Difference between a task’s
estimated cost and its actual cost
CV = EV – AC or BCWP –
ACWP
Negative Value = over budget
and / or behind schedule (vice
versa)
Deviations from the budget –
not a measure of work
scheduled vs. work completed
Cost Variance (CV)
Difference between a task’s
estimated cost and its actual cost
CV = EV – AC or BCWP –
ACWP
Negative Value = over budget
and / or behind schedule (vice
versa)
Deviations from the budget –
not a measure of work
scheduled vs. work completed
Cost Performance
Index (CPI)
Percentage of work completed per
dollar spent
CPI = EV ÷ AC or BCWP ÷
ACWP
Ratio > 1 = ahead of schedule
and / or under budget
(exceptional performance) –
vice versa
Cost Performance
Index (CPI)
Percentage of work completed per
dollar spent
CPI = EV ÷ AC or BCWP ÷
ACWP
Ratio > 1 = ahead of schedule
and / or under budget
(exceptional performance) –
vice versa
19
Schedule Metrics
Schedule Variance
(SV)
Difference between the current
progress and originally
scheduled progress
SV = EV – PV or BCWP –
BCWS
A negative variance means the
project is behind schedule
Deviations from work planned –
not a measure of changes in
cost
Schedule Variance
(SV)
Difference between the current
progress and originally
scheduled progress
SV = EV – PV or BCWP –
BCWS
A negative variance means the
project is behind schedule
Deviations from work planned –
not a measure of changes in
cost
Schedule Performance
Index (SPI)
Ratio of the work performed to
the work scheduled
SPI = EV ÷ PL or BCWP ÷
BCWS
Ratio > 1 = ahead of schedule
and / or under budget (vice
versa)
Schedule Performance
Index (SPI)
Ratio of the work performed to
the work scheduled
SPI = EV ÷ PL or BCWP ÷
BCWS
Ratio > 1 = ahead of schedule
and / or under budget (vice
versa)
20
Earned Value Metrics
 Minimum funds needed if things do not get
worse
 Minimum funds = Original total budget ÷ CPI
 Funds needed if things continue to get
worse at the same level of slippage
 Funds needed = Original total budget ÷ (CPI x
SPI)
EV – Variance & Management
Reserve
22
Variance – SV & CV illustration
Cost
Time
actual
schedule
earned
CV
SV
23
Variance - Do you know
 What is the problem causing the variance?
 What is the impact on other efforts, if any?
 What corrective action is planned or under way?
 What is the impact on time, cost & performance?
 What are the expected results of the corrective
action?
24
Variance – Depends on…
 Estimate type
 Life-cycle phase
 Length of project
 Accuracy of estimate
 Length of life-cycle phase
25
Management Reserve
 The padding added to a project for
unexpected costs that are within project
scope
 NOT an allowance for changes to scope
 NOT part of the cost estimate
 Added by upper management, NOT the
project manager
EV – Example
27
Example - Budget, Schedule, Tasks
 Project Budget = $40,000
 Schedule = 4 months
 Tasks = 20 Tasks (evenly divided over 4
months)
 $2,000 per task
 5 tasks per month
 Planned Value or BCWS = $10,000 / month
28
Example - Budget, Schedule, Tasks
 Invoice – 1st
Month Payment = $8,000
Actual Cost or ACWP
 Work Completed – 1st
Month, 3 tasks
costing= $8,000 as against $6,000
($2,000 x 3)
 Earned Value or BCWP = $6,000
29
Comparison – PV, AC & EV
30
Cost Performance Indicators
1 month
$1000
Scheduled / Budgeted
to do $10,000 work over
5 tasks in a month
window
BCWS = $10,000
PV / BCWS
1 month
$6000 $4000
EV / BCWP
Schedule slippage
permits only
3 tasks/$6,000
work to be
performed
BCWP = $6,000
Schedule variance = $4,000
1 month
$8000 $2000
AC / ACWP
Actual cost of
work performed = $8,000
ACWP = $8,000
Actual cost
variance = $2,000
EV – Example (utilising Revised
Estimates)
32
Example - Latest Revised Estimate
 Total budget (BAC) = $ 5,000
 Work scheduled (PV) = $ 2,000
 Work accomplished (EV) = $ 1,800
 Actual cost (AC) = $ 2,400
 Latest Revised Estimate (LRE) = $ 5,600
33
Example – LRE (Contd.)
 TCPI (To Complete Cost Performance Index)
 CPI = EV / AC ($ 1,800 / $ 2,400) = 0.75
 TCPI (at BAC) = Work Remaining (BAC – EV) / Budget Remaining (BAC – AC)
 TCPI (at BAC) = ($5,000 - $1,800) / $5,000 - $2,400) = 1.23
 TCPI (at LRE) = Work Remaining (BAC – EV) / Estimate Remaining ( LRE – AC)
 TCPI (at LRE) = ($5,000 - $1,800) / $5,600 - $2,400) = 1.00
 Based on the LRE ($ 5,600), the project will come on budget (1.00)
& revised estimate appears reasonable
Earned Value - Success Criteria
35
Criteria
Organisation
Detailed WBS &
OBS prepared
Use RASCI chart &
integrate OBS &
WBS & provide
infor to finance
WBS & OBS
utilised (plan,
budget, authorise
work schedule,
perform
measurement and
cost accumulation
Org responsible for
overhead control
Budgets and
Schedule
Detailed schedule
include
interdepen-
dencies, milestone
Phased budgets at
the a/c code / cost
element to capture
work complete,
WIP & O/H
Performance mea-
surement baseline,
Mngt reserve (MR),
(Un) distributed
budget maintained
Accounts /
Finance
Direct and indirect
costs are captured
at the lowest level
of the WBS / OBS
Cost elements
including coding
are in line with the
organisation’s
accounting system
EV Management
and Reporting
Mgt reports
highlight schedule
cost performance,
actual vs. budget,
variance &
reasons
Utilise WBS & OBS
for Mngt attention
(EV Management)
Prepare Latest
Revised Estimates
(LRE) utilising
EAC, VAC, ETC &
BAC for further
funding / project
cancellation
36
“The three great essentials to achieve
anything worth while are, first, hard work;
second, stick-to-itiveness; third, common
sense.”
- Thomas Edison
37
Good Luck
http://www.linkedin.com/in/anandsubramaniam

More Related Content

Earned Value Management

  • 1. Earned Value Management Make critical project decisions utilising the “early warning” signs based on data, variances & trends Anand Subramaniam
  • 2. 2 “Be not afraid of flying. Angels live in the clouds and the devil on the earth.” - Greg Evans
  • 3. 3 Highlights  Current Project Challenges  Earned Value – Overview  Earned Value – Definitions  Earned Value – Metrics  Earned Value - Variance & Management Reserve  Earned Value – Examples (including Revised Estimates)  Earned Value – Criteria
  • 5. 5 Current Project Management - Challenges Project Challenges Project Challenges Whether the project funds were spent on the right tasks Whether the project funds were spent on the right tasks Project status with regard to cost & schedule Project status with regard to cost & schedule Ahead or behind schedule Ahead or behind schedule Apportioned effort due to another work package Apportioned effort due to another work package Value for money Value for money Estimated elapsed time Estimated elapsed time Cost and schedule variance over time Cost and schedule variance over time The budgeted cost of the work quantifies the accomplishment The budgeted cost of the work quantifies the accomplishment Level of effortLevel of effort Know over or under spent Know over or under spent
  • 6. Earned Value - Overview
  • 7. 7 EV - Why & What Why Provides an “early warning” signs for prompt corrective action Provides an uniform unit of measure (dollars or work-hours) Requires different measures of progress for different types of tasks Need to consolidate progress of many tasks into an overall project status Why Provides an “early warning” signs for prompt corrective action Provides an uniform unit of measure (dollars or work-hours) Requires different measures of progress for different types of tasks Need to consolidate progress of many tasks into an overall project status What Utilising Project Management methods, practices, process & tools Accurate definition of the defined deliverable(s), timeframe & total cost (direct & indirect) to deliver the product Detailed tasks / activities and work not in the WBS is out-of-scope Baseline of budget control a/c, schedule, work measurement by Control Account (hours, $, unit) What Utilising Project Management methods, practices, process & tools Accurate definition of the defined deliverable(s), timeframe & total cost (direct & indirect) to deliver the product Detailed tasks / activities and work not in the WBS is out-of-scope Baseline of budget control a/c, schedule, work measurement by Control Account (hours, $, unit)
  • 8. 8 EV – Benefits Benefits Helps to make critical project decision based on actual vs. budget cost, variance, trends & to predict future performance Helps to make critical project decision based on actual vs. budget cost, variance, trends & to predict future performance Provides infor about the project in terms of accomplishment as well as how much has been spent to-date Provides infor about the project in terms of accomplishment as well as how much has been spent to-date Project’s final cost and delivery date with certainty Project’s final cost and delivery date with certainty Improves vendor / customer relations Improves vendor / customer relations Useful to make prediction based on comparative analysis Useful to make prediction based on comparative analysis Improves project performance Improves project performance Identifies the problem, by analysing the data captured Identifies the problem, by analysing the data captured Creates a culture of openness, trust and honesty Creates a culture of openness, trust and honesty Value for moneyValue for money
  • 9. 9 EV – Criticism  Time required for data measurement and manipulation can be considerable  Quantifying / measuring work-in-progress (WIP) can be challenging  Integration of financial expenditure information with schedule status
  • 10. 10 Note…  Adhere to Project Management Best-Practices  Baseline your schedule  Analyse variance from your expectations  Diligently update your schedule and expenditure  Understand work products produced by the project  Organize your estimation and schedule around work products  Do not re-baseline unless there is a formal, approved change in scope
  • 12. 12 Definition Planned Value (PV) Planned expenditure cash flows based on the completion of tasks in accordance with the project’s budget and schedule Planned cost of the total amount of work scheduled to be performed by the milestone date Actual Cost (AC) Actual Project Expense based on completed tasks Cost incurred to accomplish the work that has been done to date Earned Value (EV) The amount of the budget that should have been spent for a given amount of work completed The planned (not actual) cost to complete the work that has been done
  • 13. 13 Definition How much was planned to have been accomp-lished at a given point in time? Planned Value (PV) How much value (person-hours) in terms of base budget & what has been accomplished at a given point in time? Earned Value (EV) How much was actually spent at a given point in time? Actual Cost (AC)
  • 14. 14 Definition (Contd.) What is the total project expected to cost? Estimate at Completion (EAC) or revised estimate (LRE) EAC = AC + ETC What is the expected under / over spend? Variance at Completion (VAC) VAC = BAC - EAC What is the expected to complete the project? Estimate to Completion (ETC) What was the project supposed to cost = Budget at Completion (BAC)
  • 15. 15 Earned Value – AC, PV, EV Cost Time A ctual Planned Earned Planned Value: what the plan called for on the tasks planned to be completed by this date Planned Value: what the plan called for on the tasks planned to be completed by this date Today Earned Value: value (cost) of what has been accomplished to date, per the base plan Earned Value: value (cost) of what has been accomplished to date, per the base plan Actual Cost: what has been actually spent to this point in time Actual Cost: what has been actually spent to this point in time
  • 16. 16 Earned Value – Cost / Schedule + or - Cost Time Actual Planned Earned Over BudgetOver Budget Behind ScheduleBehind Schedule Today
  • 18. 18 Cost Metrics Cost Variance (CV) Difference between a task’s estimated cost and its actual cost CV = EV – AC or BCWP – ACWP Negative Value = over budget and / or behind schedule (vice versa) Deviations from the budget – not a measure of work scheduled vs. work completed Cost Variance (CV) Difference between a task’s estimated cost and its actual cost CV = EV – AC or BCWP – ACWP Negative Value = over budget and / or behind schedule (vice versa) Deviations from the budget – not a measure of work scheduled vs. work completed Cost Performance Index (CPI) Percentage of work completed per dollar spent CPI = EV ÷ AC or BCWP ÷ ACWP Ratio > 1 = ahead of schedule and / or under budget (exceptional performance) – vice versa Cost Performance Index (CPI) Percentage of work completed per dollar spent CPI = EV ÷ AC or BCWP ÷ ACWP Ratio > 1 = ahead of schedule and / or under budget (exceptional performance) – vice versa
  • 19. 19 Schedule Metrics Schedule Variance (SV) Difference between the current progress and originally scheduled progress SV = EV – PV or BCWP – BCWS A negative variance means the project is behind schedule Deviations from work planned – not a measure of changes in cost Schedule Variance (SV) Difference between the current progress and originally scheduled progress SV = EV – PV or BCWP – BCWS A negative variance means the project is behind schedule Deviations from work planned – not a measure of changes in cost Schedule Performance Index (SPI) Ratio of the work performed to the work scheduled SPI = EV ÷ PL or BCWP ÷ BCWS Ratio > 1 = ahead of schedule and / or under budget (vice versa) Schedule Performance Index (SPI) Ratio of the work performed to the work scheduled SPI = EV ÷ PL or BCWP ÷ BCWS Ratio > 1 = ahead of schedule and / or under budget (vice versa)
  • 20. 20 Earned Value Metrics  Minimum funds needed if things do not get worse  Minimum funds = Original total budget ÷ CPI  Funds needed if things continue to get worse at the same level of slippage  Funds needed = Original total budget ÷ (CPI x SPI)
  • 21. EV – Variance & Management Reserve
  • 22. 22 Variance – SV & CV illustration Cost Time actual schedule earned CV SV
  • 23. 23 Variance - Do you know  What is the problem causing the variance?  What is the impact on other efforts, if any?  What corrective action is planned or under way?  What is the impact on time, cost & performance?  What are the expected results of the corrective action?
  • 24. 24 Variance – Depends on…  Estimate type  Life-cycle phase  Length of project  Accuracy of estimate  Length of life-cycle phase
  • 25. 25 Management Reserve  The padding added to a project for unexpected costs that are within project scope  NOT an allowance for changes to scope  NOT part of the cost estimate  Added by upper management, NOT the project manager
  • 27. 27 Example - Budget, Schedule, Tasks  Project Budget = $40,000  Schedule = 4 months  Tasks = 20 Tasks (evenly divided over 4 months)  $2,000 per task  5 tasks per month  Planned Value or BCWS = $10,000 / month
  • 28. 28 Example - Budget, Schedule, Tasks  Invoice – 1st Month Payment = $8,000 Actual Cost or ACWP  Work Completed – 1st Month, 3 tasks costing= $8,000 as against $6,000 ($2,000 x 3)  Earned Value or BCWP = $6,000
  • 30. 30 Cost Performance Indicators 1 month $1000 Scheduled / Budgeted to do $10,000 work over 5 tasks in a month window BCWS = $10,000 PV / BCWS 1 month $6000 $4000 EV / BCWP Schedule slippage permits only 3 tasks/$6,000 work to be performed BCWP = $6,000 Schedule variance = $4,000 1 month $8000 $2000 AC / ACWP Actual cost of work performed = $8,000 ACWP = $8,000 Actual cost variance = $2,000
  • 31. EV – Example (utilising Revised Estimates)
  • 32. 32 Example - Latest Revised Estimate  Total budget (BAC) = $ 5,000  Work scheduled (PV) = $ 2,000  Work accomplished (EV) = $ 1,800  Actual cost (AC) = $ 2,400  Latest Revised Estimate (LRE) = $ 5,600
  • 33. 33 Example – LRE (Contd.)  TCPI (To Complete Cost Performance Index)  CPI = EV / AC ($ 1,800 / $ 2,400) = 0.75  TCPI (at BAC) = Work Remaining (BAC – EV) / Budget Remaining (BAC – AC)  TCPI (at BAC) = ($5,000 - $1,800) / $5,000 - $2,400) = 1.23  TCPI (at LRE) = Work Remaining (BAC – EV) / Estimate Remaining ( LRE – AC)  TCPI (at LRE) = ($5,000 - $1,800) / $5,600 - $2,400) = 1.00  Based on the LRE ($ 5,600), the project will come on budget (1.00) & revised estimate appears reasonable
  • 34. Earned Value - Success Criteria
  • 35. 35 Criteria Organisation Detailed WBS & OBS prepared Use RASCI chart & integrate OBS & WBS & provide infor to finance WBS & OBS utilised (plan, budget, authorise work schedule, perform measurement and cost accumulation Org responsible for overhead control Budgets and Schedule Detailed schedule include interdepen- dencies, milestone Phased budgets at the a/c code / cost element to capture work complete, WIP & O/H Performance mea- surement baseline, Mngt reserve (MR), (Un) distributed budget maintained Accounts / Finance Direct and indirect costs are captured at the lowest level of the WBS / OBS Cost elements including coding are in line with the organisation’s accounting system EV Management and Reporting Mgt reports highlight schedule cost performance, actual vs. budget, variance & reasons Utilise WBS & OBS for Mngt attention (EV Management) Prepare Latest Revised Estimates (LRE) utilising EAC, VAC, ETC & BAC for further funding / project cancellation
  • 36. 36 “The three great essentials to achieve anything worth while are, first, hard work; second, stick-to-itiveness; third, common sense.” - Thomas Edison