The document outlines a marketing project proposal for Airtel Company Ltd. It includes:
1. Details on the project team members and their goals to increase Airtel's popularity and quality of service through marketing planning and forecasting.
2. An overview of the project proposal which includes conducting a survey, analyzing the results, creating a schedule, assigning staff, and developing a budget.
3. A risk management plan identifying political, budget, data, and public engagement risks and outlining responses to mitigate those risks.
1 of 21
More Related Content
Marketing planning and forecasting of airtel company ltd
2. Group Name
INFORMATION OF GROUP MEMBERS
NAME OF MEMBER ID
MD. AMZAD HOSSAIN 15102225
RIFAT AHMED 15102183
JESMIN AKTER 15102190
AZIZUR ROHMAN SHAWON 15102164
2
4. Project define
4
We selected this topic because we think it’s a very important part of Airtel
Company Ltd. Through which we can make some improvement of
communication. We all know that your tele-communication company is
renowned company in India and in Bangladesh. But your tele-communication
is not getting that much popularity like the others are getting.
The goal of this project is to increase the popularity of your tele-
communication company and concerning people about the quality of service of
Airtel.
6. 6
Survey
Airtel Bangladesh Ltd. formerly known as Warid Telecom. With a customer base of more
than 10 million, Airtel Bangladesh is the most preferred youth brand of the country that
thrives on excellent data service. Airtel is the sixth mobile phone carrier to enter the
Bangladesh market, and originally launched commercial operations under the brand
name Warid on May 10, 2007. Airtel Bangladesh has 7.97 million subscribers with 7.3% of
market share.
7. 7
Analysis
To analysis the problem I make a survey with different questionnaires. Survey data will
be analyzed by social segment, cultural segment, and demographic segments, such as
customer society type, age, and gender. Then I analysis those data with MS Excel and
compare different variable with some statistical tools like Z test, standard deviation. This
project is mainly evaluated based analysis. All the data are used here by the interview
with survey. They people engaged here customers and some staff.
9. Schedule
9
Questionnaire development and mailing 9 June -14 June
Deadline for returning questionnaire 31 June
Data tabulation and processing 3 July- 16 July
Completion of final report 10. August
Total Duration of this project is almost three month which is started from 9th January 2016. In that project,
the total time line is like that:
10. 10
Staffing
We are 4 member of our company will handle this project. For the data
collection part we need 5 executives and to collect the questionnaires. All the
data will be designed, analyzed by my members.
11. Responsibility management
TASK AMZA
D
RIFAT SHAWON JESMIN EX-1 EX-2 EX-3 Ex-4 EX-5
Questionnaire
development
R R S S
Questionnaire
mailing
R R S S
Data processing and
tabulation
R R S S
Analysis of findings R R S S
Recovery R R S S
Preparation of final
report
R R R S S S
11
12. 12
Professional &
administrative time
Estimated
hours
Rate Total
Questionnaire
development
5 Tk. 200/hr. Tk. 1000
Questionnaire mailing 6 100/hr. 600
Data processing and
tabulation
4 200/hr. 800
Analysis of findings 21 250/hr. 5250
Preparation of final report 4 300/hr. 1200
Mailing cost 200
400 copies of
questionnaires
400
In this project, there is a small budget analysis. That is given bellow:
Budgeting
13. AON Network
13
0 1 4
0
0 4 4
4 4 8
4
8 4 12
4 2 3
16
20 4 24
24 7 28
0
24 4 28
12 6 24
0
12 12 24
4 3 12
0
4 8 12
A
B
C
D
E F
15. 15
Risk Management of This Project
Step 1: Risk Identification:
Political obstacles
Budget distribution
Quality checking of survey
Public harassment
Weather
Data margining
Public requirements
16. 16Step 2: Risk Assessment form
likelihood to occurring (0 to 10)
Risk Event Likelihood Impact Difficulty
Detection
Activity Time
Political
Obstacle
8 2 7 All
Budget
Distribution
5 4 3 All
Quality and
checking of
survey
7 5 5 All
Public
Harassment
6 8 4 All
Weather 8 8 7 All
Data
Margining
4 5 All
Public
Requirement
4 3 3 All
18. 18
Step 4: Risk Respond Development
Political obstacles Accept
Budget distribution Expert to manage the budget
Quality checking of survey work Project Manager
Public harassment Avoid
Weather Fulfill by next working day
Data margining Expert executives
Public requirement Distribution of policies
19. Conclusion
19
Here in this project all the data and information is collected by us.
Here we have tried to collect data and information that will make
this project successful project. So, all the authorization of this
project goes to us. And all the scheduling and budgeting have done
from our practical point of view. So, we think this proposal will make
some better effect in your company’s marketing planning and
forecasting .