Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
This document provides an overview of an oil and gas engineering training program. It covers topics like project engineering, design basis, engineering disciplines, process design, equipment, piping and instrumentation, civil works, and health and safety. The training aims to give participants a detailed understanding of the engineering activities in various disciplines and show sample deliverables. It also explains the challenges of oil and gas engineering projects. The document contains several figures to illustrate engineering workflows, project organization, and more.
The document provides a method statement for piping installation works at the Dabbiya site for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project. It outlines the scope of works, sequence of activities, resources, HSE requirements, and emergency contacts. Piping works will involve transporting prefabricated spools to site, lifting them into position, welding field joints, installing valves, and testing. Welding will follow approved procedures and NDT testing. HSE precautions like PPE and fire safety will be enforced during the medium risk work.
Raghavendran V is seeking a challenging career as a Piping Supervisor with over 7 years of experience in construction projects. He has worked on oil and gas plants, refineries, and pipelines in Kuwait and Iraq. Raghavendran has a Diploma in Mechanical Engineering and experience in AutoCAD, PRO-E, piping fabrication, erection, and project management. He is proficient in English, Hindi, Tamil, Telugu, and Malayalam.
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
Successful commissioning new or starting-up revised equipment and systems requires meticulous planning, organizing and controlling. Careful methodical, detailed planning – early – is the key to the success of any commissioning.
This document provides procedures for the fabrication, installation, and erection of piping. It outlines responsibilities for construction management, engineering, quality control, and health and safety. It also describes procedures for receiving and storing materials, pre-fabrication including cutting, beveling and fit-up, welding, testing, and installation of underground and erected piping. Attachments include job safety analyses, work flows, lifting plans, and inspection forms. The goal is to ensure compliance with contractual and health, safety, and environmental requirements for piping work.
Metode Konstruksi Offshore Platform_2016_2_18.pptMFaridGeonova
This document discusses the construction of fixed offshore platforms using steel tubular structures. It describes the key phases of fabrication and installation including fabrication of small structural units, jacket structure fabrication, jacket erection, deck fabrication, and lifting and installation of the deck and jacket. Steel tubular joints are welded together during fabrication. The jacket and deck are assembled onshore then transported offshore for installation by lifting with crane vessels. Piles are driven into the seabed to secure the jacket structure.
Introduction to offshore oil and gas surface facilities, including drilling rig types, topside and substructures, jacket, compliant tower, jack up, gravity based structure, fpso, fso, semi submersible, tlp, spar, wellhead platform, processing platform, pipeline, and surface facilities selection
Quality Control & Quality Assurance of MS pipelineIEI GSC
This presentation re. QC & QA of M S pipelines was made at Gujarat State Centre of the Institution of Engineers (India) at Ahmedabad by Er. Manoj Raghavan of SGS (India) Ltd.
The document outlines the process for executing a project design from start to finish. It involves creating 3D models for all disciplines, setting up interference management and design reviews. As the design progresses, more elements are added to the models like piping, equipment, ductwork, and architectural details. Reviews are conducted at 25%, 50%, 75% and 90% completion milestones. Deliverables include plots, drawings, specifications and manuals to support construction, commissioning and validation.
Senior Supervisor Piping & Mechanical
Piping &Pipe Line Fabrication/Erection&/ Hydro test /Mechanical Completion Pre-Commissioning
I have around17+, years ‘work experience I have done three years diploma inMechanical engineering,
I have worked as a Piping supervisor in Oil, Gas, power plant & Petro-chemical.
The document discusses engineering management in the EPC (engineering, procurement, and construction) industry. It outlines the typical project phases and risks involved in EPC contracts. It also identifies common challenges such as scope changes, commodity price volatility, and ensuring vendor and subcontractor quality. The presentation emphasizes the importance of effective engineering management throughout the project lifecycle from bidding through construction and commissioning. Key focus areas include integrated planning, competency of resources, communication, and change management. Success relies on collaboration, responsiveness, contingency planning, and working as a cohesive team.
This document is a curriculum vitae for James C., a mechanical supervisor with over 17 years of experience in petrochemical, oil and gas, and power plant engineering projects in the Middle East. He holds a diploma in mechanical engineering and various safety certifications. His experience includes supervising piping, mechanical, fabrication and erection work for numerous companies and projects in Bahrain, Saudi Arabia, the UAE, and India. He is seeking new opportunities as a mechanical engineer.
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
The document provides an overview of plant commissioning and start-up procedures. It discusses the commissioning process which includes preparation and planning, mechanical completion and integrity checking, pre-commissioning and operational testing, start-up and initial operation, performance and acceptance testing, and post-commissioning. It then goes into more detail on specific aspects of the commissioning process such as developing start-up procedures, commissioning utilities, pressure testing, cleaning and flushing, and pre-commissioning operational testing.
Amol Sawant (Piping Engineer with 10 years experience) docxAmol Sawant
Amol Sawant is a senior piping engineer with 10 years of experience in refineries, oil and gas, and fertilizer projects. He has experience managing teams of 5-8 people and fulfilling roles such as layout designer, PMC engineer, and ISO coordinator. He is proficient in SmartPlant Review, Navisworks, PDS, Caesar II, and other piping software. His most recent roles include working as a piping engineer for Medgulf Construction in Qatar and Tecnimont ICB in India.
This document outlines the key milestones and deliverables in a process plant design project from conceptual design through detailed design and construction. It includes milestones for various disciplines like process, mechanical, piping, civil/structural, instrumentation and control, and electrical. The milestones range from developing preliminary design criteria and equipment lists to issuing design packages, finalizing vendor data, and completing construction drawings.
Cost Estimating for Offshore Oil & Gas Facility DecommissioningDonnie Miller
This paper reviews the process of decommissioning offshore oil and gas facilities in the US Gulf of Mexico. It discusses the typical cost elements of decommissioning including planning, well plugging and abandonment, platform preparation, topsides and jacket removal, and site clearance. It provides details on the costs and time required for various tasks such as pipeline abandonment, conductor removal, and cutting and removing the platform jacket. The paper also gives an example cost estimate for decommissioning a typical 4-pile drilling/production platform and compares actual costs to estimated costs for several projects to evaluate estimate accuracy.
The document provides a method statement for piping works at the Dabbiya site for new piping installations at five clusters as part of the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project. It outlines the scope of work, references, responsibilities, sequence of works including safety setup, field joint welding, pipe support welding, valve installation and quality control requirements. The piping installations will include welding field joints and assembling prefabricated pipe spools delivered from the workshop.
The document defines mechanical completion and commissioning. Mechanical completion involves checking equipment is installed correctly and ready for commissioning. Commissioning verifies systems function as intended. Key activities for mechanical completion include inspections, testing, and documentation. Commissioning activities include system testing, instrumentation calibration, and verifying equipment and systems meet objectives. The document provides details on planning, executing, and documenting mechanical completion and commissioning.
- Constructability refers to how well a design can be built according to specifications, on time, and within budget. Ensuring constructability involves early contractor involvement in design, design quality reviews, and consideration of construction methods and materials.
- Effective methods for identifying and preventing constructability problems include assigning a "constructability champion," using BIM with clash detection, collecting lessons learned, and conducting design reviews with contractors. Early contractor involvement in design-build projects also helps address constructability.
- Field experience is important for designers to understand construction realities. Regular site visits and communication between designers and contractors can help address issues early. Formal constructability reviews at 30%, 60%, and 90% design stages with contractor input can further
The document discusses oil and gas production and surface facilities. It begins with an introduction to the upstream, midstream, and downstream sectors of the oil and gas industry. It then covers well types at the production phase, including oil, gas, and water injection wells. It describes key wellhead components like the casing head, tubing head, Christmas tree, and safety control subsurface safety valve. It provides details on various artificial lift methods and their relative advantages and disadvantages. It concludes with descriptions of hook-up and flow line components used to transport oil and gas from wells.
For innovation in construction, use video presentations with 3D animations to plan and communicate how a project will be carried out and the timeline. This presentation can be used to communicate with the Client, Stakeholders and Site Team.
Project Execution Plan for High Rise BuildingDavid H Moloney
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan for Bridge ConstructionDavid H Moloney
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an insitu concrete bridge.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
Motorway Construction, Project Execution PlanDavid H Moloney
The document provides details on constructing a motorway, including sequencing of earthworks, roads and paving, bridges, culverts, pilings, and other structures. It discusses health and safety measures, site facilities, quality assurance, and project monitoring. The construction process and use of plant and equipment is explained through diagrams and images. Progress is tracked through dashboards, charts, and time-location diagrams.
The document describes the process of tunnel construction using a Tunnel Boring Machine (TBM). A TBM excavates underground and installs precast concrete segments to form rings that line the tunnel. As the TBM advances, it removes excavated material on a conveyor belt and installs ring segments that are 1.5 meters long to form the tunnel walls and structure. On average, a TBM can progress 15 meters per day of tunneling.
The document provides details on the construction of the Metro Route 2020 project in Dubai, which has a budget of $2.9 billion. It includes key project facts such as a route length of 10.5km for viaducts and 4km for tunnels. There will be 7 underground and elevated stations serving a capacity of 46,000 passengers per hour. Construction will involve tunnelling, precast segment erection, bridge and viaduct construction using methods such as diaphragm walls, secant piles and slipforming. The project execution plan outlines the construction process and measures to ensure safety, quality and environmental protection.
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an Airport.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Site Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD).
This Video Presentation is innovative and has many beneficial uses.
Can be used for Tender Presentations and to substantiate entitlement for additional payments.
Sea Port Construction, Project Execution PlanDavid H Moloney
Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
The document outlines a 7 step project execution process (PEP) that includes project planning, engineering, procurement & logistics, installation, integration, start-up, and operation & handover. The project planning step involves presales meetings with the customer, internal project analysis, and a final sales meeting. Internal project analysis delivers documents to various groups covering figures, plans, quality, procurement, and more. The PEP is used to develop company-specific tools and techniques to implement projects, track them, identify bottlenecks, and ensure successful outcomes.
This document provides details on the construction methodology for the deck of Bridge 182, including an 11-step process:
1) Erecting falsework and soffit formwork
2) Fixing reinforcement, ducts for stressing strands, and void formers
3) Pouring the deck concrete and stressing the strands to pre-compress the deck
4) Removing falsework and formwork after construction is complete
Over 1,200 cubic meters of concrete will be pumped into place over 12 hours using 4 concrete pumps with 42-meter booms. Pre-stressing the deck with 420 meters of high-tensile strands reduces the structure's dead weight and cracking.
The document provides details on the construction methods and sequence for building a new runway at Heathrow Airport. It discusses the various stages of earthworks, including excavation, filling and compaction. It also outlines the processes for constructing the asphalt pavement, installing airfield ground lights, building associated structures like tunnels and culverts, and performing quality control checks before opening the new runway. The presentation is intended to explain the runway construction process to stakeholders and train site workers.
Dart Underground, Dublin - Light Rail Network in TunnelsDavid H Moloney
The Dart Underground is a proposed underground rail system that will run under the city centre, and connect Heuston Station with Pearse Station a distance of 4 kilometres. At the proposed St Stephen’s Green interconnection Station, on the route, passengers will be able to transfer to the Metro North and go to the Airport.
The document introduces project execution and the need to develop a Project Execution Plan to outline responsibilities and procedures for delivering agreed upon project outputs, as the plan expands on the Project Business Plan by specifying day-to-day management controls. A Project Execution Plan is developed when a project proposal is approved, and requires knowledge of developing detailed project plans, schedules, quality procedures, reporting, purchasing if needed, risk management, and cost control. The main outputs of project planning include the project execution plan and controls, progress reports, action item logs, project cost control, training plans, risk logs, and lessons learned.
This presentation provides an overview of construction methods and sequencing using 3D animations and images. It aims to help stakeholders understand projects and engage site teams. The presentation covers general site facilities, temporary works like sheet pile walls, dewatering, traffic management, and more. Construction methods for various elements like diaphragm walls, vibro compaction, piling, and more are presented. The sequencing of activities like bridge construction, reinforced concrete works, and steel erection are also demonstrated.
1) The document discusses the gauge conversion project between Mehsana, Gujarat and Ajmer, Rajasthan including preliminary work organizing maintenance and site management.
2) It describes an incident where the author conducted a controlled rock blast that ended up blocking the tracks longer than planned, but impressed inspectors anyway.
3) It provides background on the author's career starting as a clerk and rising to Assistant Engineer with Western Railway through hard work and commitment to his roles.
The document provides a checklist of items to ensure project execution and control. It includes questions to check that change management, communications management, contract management, financial management, issue management, implementation and transition, lessons learned, meeting management, quality assurance management, risk management, schedule and task management, staffing management, test management, training management, and status reporting processes are being followed properly. The checklist aims to help projects stay on track to meet objectives.
1) High rise buildings are becoming more common due to scarcity of land and demand for space. They are defined differently but generally refer to buildings over 15 meters tall.
2) Foundations for high rise buildings include shallow foundations like spread footings and mat foundations, and deep foundations like piles. Piles transfer load through end bearing or friction along their length.
3) Structural systems for high rise buildings must resist both gravity and lateral loads. Interior systems include rigid frames and shear walls. Exterior systems such as tube and diagrid systems resist loads along the building perimeter.
Construction Project Management Class Project PresentationWayne Holley
John and Jane Doe have contracted to purchase a manufactured home to be installed on their 4.95 acre property in Santa Ysabel, California. The project will involve developing the land, installing utilities like a well and septic system, preparing the home site, and fully setting up and landscaping the home. Key risks include finding an adequate water source from a well and finding an acceptable location for the septic system leach field. The targeted completion date is November 5, 2012.
Bar Bending Schedule (BBS) is a chart which gives a clear picture of bar length, diameter of bar ,bar mark ,location of bar.
It allow workers to place steel properly.
This document provides a summary of a presentation on the construction of Muscat Airport. It outlines various construction methods and sequences used including setting up temporary site facilities, installing sheet pile shafts for deep excavations, dewatering methods, constructing reinforced concrete structures, and post-tensioning of bridge decks. The presentation aims to engage stakeholders and share knowledge on the airport construction process.
This document provides details on the proposed Metro North project in Dublin, Ireland, including a €2.4 billion budget. It outlines the 18km route, which includes 7.5km of tunnels, 2.7km of cut-and-cover tunnels, 2.25km of viaducts, and 5.5km at road level. There will be 15 stations, with 9 underground and 6 at road level. The presentation aims to provide an understanding of the construction, costs, and timeline to stakeholders and politicians. It includes information on tunnel boring machines, station excavation, concrete works, viaduct construction, and other aspects of the large infrastructure project.
The document provides an overview of the construction of various buildings and structures at Muscat Airport. It includes 3-6 sentence descriptions of the construction process for airport terminal piers using tower cranes, the jack-up method for constructing the airport terminal building roof in 5 steps, constructing fuel storage tanks by lifting in chillers and pipe spools, and laying 132kV electricity cables by pulling 800m long cables from drums using a winch. It also details constructing a road bridge deck using post-tensioned concrete with void formers in 11 steps and includes diagrams.
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDWater Birds (Ali)
This document provides an overview of the civil construction and structures at Fatima Fertilizer's plant. It discusses the project overview including key features and timelines. It then describes the civil engineer's role in establishing projects like Fatima Fertilizer which includes various complex structures from foundations to buildings. It highlights the use of steel and concrete frame structures. The document also outlines the author's work areas including roads, a weigh bridge, and the Nitro Phosphate plant. It provides details on constructing roads using rigid pavement and the weigh bridge. For the NP plant, it discusses the prilling tower construction using slip forming and strengthening of columns.
The document discusses the design and construction of a 4-lane 90m railway over bridge in Chand Sarai, Lucknow. Key steps in the construction process include surveying, engineering design, laying pile foundations, installing bearings and girders, shuttering, and concreting. Tests were conducted on materials and foundations to ensure quality. The bridge was designed to allow road traffic to safely pass over the railway line.
The document summarizes a site visit to a construction site at Jaypee Wish Town in Noida. It describes some of the key equipment observed on site including a tower crane used to lift materials for tall buildings, a concrete pump machine consisting of an axle boom and pipe to pour concrete, and a batch mixer to fill concrete into the pump. Process steps of pouring concrete are outlined. Other equipment mentioned include a mobile crane, static batch plant to mix concrete ingredients, and pile foundations with reinforcement laid on site.
Internship project Report Gammon India pvt. ltd.SHWETABH SINHA
This document provides an overview of the construction of an elevated road corridor from AIIMS to Digha in Patna, Bihar, India. The 11.9 km project involves constructing a 2-lane semi-elevated structure and an 8.5 km 4-lane elevated structure. It will include bridges, culverts, intersections and other infrastructure. The project is being executed using an EPC model and will help reduce traffic congestion and travel times in the area once completed.
The document outlines the planning and approval process for a water distribution network project. It lists the various materials, designs, engineering drawings and approvals required. It then lays out the civil works and construction activities needed to build pump houses, electrical buildings, surge vessels, pipelines and other infrastructure. These include tasks like excavation, foundation work, structural elements, mechanical, electrical and plumbing installations. The program shows the sequence and durations for each stage from initial submissions and approvals through to completion of construction.
An engineering company is investigating a low-cost option to develop marginal oil and gas fields in the Dutch North Sea between 20-35 meters depth. They select a self-installing platform concept called SIP3 that can be installed without a heavy lift vessel, support a 400 tonne topside, and has low decommissioning costs. The SIP3 concept involves a barge-installed monopile substructure with an attached topside that can be transported and installed without heavy lifting equipment.
Marginal offshore production platform feasibilityguest651e92c
Final presentation of a feasibility study performed this year (2009) covering many aspects of marginal platform design, fabrication, transport and installation.
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
This document provides an overview of an industrial training presentation on a redevelopment project by NBCC Limited in New Delhi, India. It summarizes the project details including the construction being divided into 5 packages, methodology used such as site clearance, excavation, laying of concrete, and quality control testing. The presentation also includes photos from the construction site and details of structural elements like columns, beams, and lifts.
This document provides an overview of petroleum drilling fundamentals, including different types of rigs used for offshore drilling. It discusses jack-up rigs, semi-submersible rigs, drill ships, condeep platforms, jacket platforms, and tension leg platforms. It also covers well planning, designing the well, drilling operations, completions, new technologies, and structural geology. Key steps in drilling include obtaining licenses, exploration, appraisal, development, maintenance, and abandonment of oil and gas fields. Safety and monitoring drilling progress are also emphasized.
The document provides a summary of Satyavir Singh's work experience and qualifications. He has over 30 years of experience working on structural and civil engineering projects for oil, gas and industrial facilities. His recent roles have included designing steel and concrete structures, foundations, and details for projects in Abu Dhabi and other locations in the Middle East. He is proficient in AUTOCAD and MicroStation and has experience working on projects according to various international standards.
Dave Chase has over 30 years of experience as a mechanical fitter and welder across various industries including civil, commercial, automotive, marine, and resources. He has extensive experience in fabrication, installation, welding, project supervision and management. He owns his own engineering company, Chase Engineering, and has worked on many high-risk projects using rope access techniques. He has the necessary qualifications and certifications for welding, heights work, confined spaces, rescue, and first aid.
Matthew McAbee is a Civil/Structural Designer with over 10 years of experience designing pipe racks, foundations, and other steel structures for petrochemical plants. He has worked on projects for companies like Valero, Sunoco, Enterprise, and Imperial Oil. His experience includes 3D modeling, detailing, retrofitting designs, and using software like AutoCAD, Cadworx, and Tekla. Representative projects include designing a fin fan platform, brine suction line support, and electrical support foundations.
The document summarizes a technical seminar presentation on Accelerated Bridge Construction techniques. It discusses how ABC uses innovative methods to reduce mobility impacts during bridge replacement or rehabilitation. Key benefits of ABC include improved constructability, reduced construction time, higher quality materials, and increased work zone safety. The presentation outlines various prefabricated bridge elements and structural placement methods used in ABC, such as full depth and partial depth precast bridge decks, precast pier elements, spread footings, pile caps, and precast pier box cofferdams. Placement methods covered include horizontal skidding, use of self-propelled modular transporters, longitudinal launching, and heavy lifting equipment.
The document discusses the design and construction challenges of the Deh Cho Bridge in the Northwest Territories of Canada. Some key points:
- The bridge crosses the Mackenzie River and connects Yellowknife to Highway 1, replacing a ferry. Its remote northern location and extreme winter conditions of -40°C posed challenges.
- An innovative extradosed bridge design was used with a 1045m continuous superstructure and expansion joints only at the abutments.
- Construction methods like incremental launching and extensive prefabrication were employed to minimize field work during the short construction season.
- Rigorous shop trial assembly and quality control processes were required given the remote site and need to minimize repairs.
This document provides details about the construction of a railway overhead bridge by the U.P. State Bridge Corporation Ltd. It discusses the project details, including specifications of the bridge which is 911.506 meters long with 20 circular piers. It outlines the various steps of construction including surveying, laying reinforcement, shuttering, concreting, and removing shuttering after setting. Suggestions are provided for bridge maintenance and monitoring.
Similar to Oil & Gas Plant Construction, Project Execution Plan (20)
Farm life in early 1900s Ireland is described, including typical farm layout and routines. Farmers followed an organic mixed farming system with crops, vegetables, dairy cows, pigs, chickens and a work horse. The staple diet was homegrown foods. Milk was delivered daily to local creameries, which operated as small factories producing butter for export. Rural electrification in the mid-1900s began modernizing farm life with new technologies and laborsaving devices. Community was important, with social events like the annual agricultural show.
The document describes a book of maps from 1824 depicting the Earl of Derby's landed estate in Ballykisteen, Limerick-Junction, Ireland. The estate consisted of 20 maps showing the fields, roads, buildings and tenants of the various townlands. Each field number, acreage and land use. A table provided details of tenant farmers' names and fields. The estate was later owned by the O'Brien O'Connor family in 1873 before being sold. The maps provide a record of landed estates and tenant farming in Ireland during this time period.
This document provides COSHH assessments for various hazardous substances used in construction. It lists 97 substances across various categories like concreting, waterproofing, asphalt paving, plant and equipment, paints and coatings, plaster and render, roof waterproofing, sealants, tiling adhesives, and sundry items. For each substance, it provides information on the supplier, use, storage precautions, disposal procedure, spillage procedure, health effects, required controls, and first aid measures in case of emergencies. The aim is to ensure safe handling and use of these substances through proper assessments, precautions, controls and emergency response procedures.
This document contains a risk assessment for various construction activities. It identifies 96 potential hazards and proposes control measures to reduce the risks. The activities assessed include general site activities, use of abrasive wheels, working near aircraft, buried services, handling cement and concrete, concreting, use of compressors and air tools, and more. Control measures proposed include use of PPE, training, inspections, exclusion zones, noise monitoring, and following method statements and risk assessments. Implementing the controls aims to reduce severity and likelihood of risks to achieve adequately controlled or trivial residual risks for all activities.
The photo album documents the reconstruction of the runway at Cork Airport that took place in October 2021. Over 100 photos show the various stages of the project from demolition of the old runway surface to repaving and remarking the new runway surface. The reconstruction updated the runway and brought it up to current aviation standards and regulations.
This document provides details on the expansion of Muscat Airport in Oman, including the construction of a new 4.3 km runway, taxiways, and other infrastructure by Consolidated Contractors Company and TAV Construction in a joint venture. It discusses the scope of works, resources and facilities used, construction methods and technologies such as Superpave asphalt and slipform concrete paving. Safety achievements and challenges on the large project are also summarized.
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
The document is a project execution plan for runway construction at an airport. It includes 3 sentences:
It outlines the sequence of work activities, resources needed like quarries for aggregate production, and methods for different construction tasks such as installing drainage culverts, constructing precast elements, and laying crushed aggregate base courses, asphalt, and concrete pavement. Precise control of levels, grades, and joint patterns is described for pavement construction along with compaction methods and testing. The plan provides details on plant and equipment used, output rates expected, and control of mix properties and temperatures during paving.
This safety risk assessment document identifies 14 hazards associated with airside construction work. For each hazard, it lists the potential effects if no controls are in place, analyzes the initial risk level, and proposes control measures to reduce the risk. It then re-analyzes the risk level with the proposed controls and categorizes the residual risk. The document provides a risk analysis matrix to define risk levels and determine if further action is required.
Construction Environmental Awareness and Training POSTERDavid H Moloney
This document discusses environmental management measures for a construction project. It identifies various pollutants that can be caused by construction activities, including pollution to air from dust, pollution to land and water from materials like concrete washout or fuel. It provides preventative measures to address each type of pollution such as covering materials, using settlement ponds, enforcing speed limits, and ensuring proper storage and disposal of hazardous waste. Responsibilities are identified for project managers, site managers, and environmental staff to implement measures and monitor compliance.
Show how different projects were constructed, generally the construction methods, sequence and plant are included. The information is presented in a way that is easily understood and explained.
Project Planning Organising Tracking ConstructionDavid H Moloney
The aim of this book is to show construction information relevant to planning, organising and tracking progress, graphically, focusing on the essential facts that can be easily discussed, communicated and implemented.
Regarding the illustrations showing construction sequences (storyboards), the approach is to find the easiest, quickest and safest way to execute a project with maximum utilisation of the employed resources also ensuring that executed work is right first time.
Gantt type chart programmes show the sequence and durations. Storyboards can show the sequence, durations along with how to build an operation graphically in a way that all team members along with operatives on site can understand leading to a collaborative effort.
This book deals mainly with heavy Civils and structures, the details and outputs are for guidance, each case should be evaluated separately allowing for particular site conditions.
Rock excavability, drill & blast, marine & haulageDavid H Moloney
Infographics showing methods for excavation of Rock and its excavability.
Included is the dredging of rock in a marine situation by drilling and blasting.
Also are the loading and haulage outputs.
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdfAsiimweJulius2
This lecture will equip students with basic electrical engineering knowledge on various types of electrical and electronics drawings, different types of drawing papers, different ways of producing a good drawing and the importance of electrical engineering drawing to both engineers and the users.
By the end of this lecture, students will be to differentiate between different electrical diagrams like, block diagrams, schematic diagrams, circuit diagrams among others.
WhatsApp: +852 56142185
Buy a fake University of Washington diploma. Get a fake UW diploma. Get a fake University of Washington degree. UW degree.
Skype: adolph.863
QQ/WeChat: 648998850
Email: buydocument1@gmail.com
https://www.buydocument.net
https://www.buyfastdegree.com
https://www.getadiploma9.com
https://www.diploma999.com
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...Fady M. A Hassouna
Permeable pavement is considered one of the sustainable management
options for roadway networks, which mitigates a number of problems associated with
stormwater, ground water pollution, and traffic safety. In this study, the economic
feasibility, vehicle operation, and environmental implications of implementing permeable
pavement in Nablus, Palestine have been determined by selecting the local roadways that
satisfy the permeable pavement requirement, such as low traffic volume, grade less than
5%, speed limit up to 50 km/h, and subgrade with good permeability. The total costs of
construction and maintenance for both conventional asphalt and permeable pavement have
also been compared based on the life cycle cost analysis (LCCA). Finally, the
environmental implications such as the expected increase in the amount of ground water
and the reduction in water pollutants have been investigated. The results of the analysis
show that the permeable pavement is applicable for the local roadways that have satisfied
the requirements, which are 61 roadways. Furthermore, it could lead to an annual
significant increase in ground water by 107,404.7 m3 and slightly reduce the cost of
construction and maintenance by up to 1,912,000 ILS during its life period compared to
conventional asphalt pavement. Moreover, applying porous asphalt could enhance
vehicular traffic safety by improving skid resistance.
The Control of Relative Humidity & Moisture Content in The AirAshraf Ismail
To many of us Relative Humidity (RH%) & Moisture Content (g/ kg) are confusing terms & we often don't know which one of them to choose in order to highlight our "Humidity" issues!
This post is to briefly address the definition of Relative Humidity, Moisture Content , Moisture Load Sources & Humidity Control Hazard!
If we're running two pumps, why aren't we getting twice as much flow? v.17Brian Gongol
A single pump operating at a time is easy to figure out. Adding a second pump (or more) makes things a bit more complicated. That complication can deliver a whole lot of additional flow -- or it can become an exercise in futility.
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...John Gallagher
Rails apps can be a black box. Have you ever tried to fix a bug where you just can’t understand what’s going on? This talk will give you practical steps to improve the observability of your Rails app, taking the time to understand and fix defects from hours or days to minutes. Rails 8 will bring an exciting new feature: built-in structured logging. This talk will delve into the transformative impact of structured logging on fixing bugs and saving engineers time. Structured logging, as a cornerstone of observability, offers a powerful way to handle logs compared to traditional text-based logs. This session will guide you through the nuances of structured logging in Rails, demonstrating how it can be used to gain better insights into your application’s behavior. This talk will be a practical, technical deep dive into how to make structured logging work with an existing Rails app.
I talk about the Steps to Observable Software - a practical five step process for improving the observability of your Rails app.
the potential for the development of autonomous aircraft
Oil & Gas Plant Construction, Project Execution Plan
1. Oil & Gas Plant Construction
Project Execution Plan
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to
ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/oil-gas-plant-construction-project-execution-plan
https://www.youtube.com/watch?v=PiRY0ERoXfI
6avid H Moloney
4th August 2016
Brief Description
The purpose of this presentation is to give an understanding of
the Methods, Plant and Sequence to construct a Gas & Oil Plant
.
This presentation can be used to engage Stakeholders and to get
the Site Teams commitment to the programme. Also can be
used for Induction Training and as a way to capture and share
knowledge.
Project Execution Plan (PEP) details how a project will be
executed, monitored and controlled.
High in Educational Value and easily understood. Recommended
for Continuing Professional Development (CPD)
This Video Presentation is innovative and has many beneficial
uses.
15. Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
16. CABC ( Crushed aggregate base course )
Earthworks
Mixing Plant
Testing Compaction
Site Trial
21. Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
23. Insitu Piling Construction - Plant & Methods
3D image to show Plant.
For construction details see my YouTube Channel
Plant & Equipment
Crawler Crane
Piling Hammer
Casing
Piling Rig
Concrete Pump
Concrete Mixer Trucks
Tremie Pipe
Reinforcement Cage
27. Sheet Pile Shaft Temporary to Support Excavation
Drive Sheet Piles Excavate & install bracing
Construct Concrete Structure Backfill, remove bracing & sheet piles
ⓒ David H Moloney
28. Sheet pile Temporary Shaft
ⓒ David H Moloney
GeneralItems
3D Animation to show Sequence
29. Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
30. Diaphragm Wall Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
59. Piping Spool Fabrication
Piping Spools are pre-fabricated from pipes and pipe fittings in fabrication shops to
reduce on site fabrication costs and provide better quality.
74. Flares / Columns / Vessels Erection
Path of Construction 74
Demag CC180-1 300 t crawler crane
72m boom & 42m luffing jib
Tandem Lift to tilt flare
from horizontal to vertical
Trunnions
Main
Lift
Crane
Tail
Crane
80. Structural Steel Building Single Storey
3D images to show Construction Sequence.
ⓒ David H Moloney
Step 1 Set-out Grid Lines Step 2 Holding Down Bolts Step 3 Erect 1st Bay
Step 4 Erect 2nd Bay Step 5 Erect following Bays
82. Structural Steel Building Multi Storey
ⓒ David H Moloney
Step 1 Set-out Grid Lines Step 2 Holding Down Bolts Step 3 Erect 1st level use core for stability
Step 4 Complete 1st Level Step 5 Erect following Levels Step 6 Plumb & Align Structure
3D images to show Construction Sequence.
83. Roof Covering
ⓒ David H Moloney
StructuralSteel
Brief Description
Sequence is
Fix bottom sheet
Fix Vapour barrier
Fix Top Hat section and clips
Fit Insulation
Fix top sheet
89. Construction of Azerbaijan Oil Pipeline 42” by 450km.
Overview Construction Sequence
A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the
route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and
reinstating the land to its original condition.
.
Crossing Railway, Roads, Rivers, etc.
Pump Station
90. Oil Pipeline 42”
Contents
Overview
Surveying & Setting Out
Clearing & Grading
Double Jointing i.e. welding 2 pipes together
Stringing out Pipes
Bend Pipes for changes in direction sideways and up & down
Welding Pipes into a string, Test Weld by X Ray.
Anti-corrosion Coat to Joints
Trenching i.e. excavate trench
Lowering pipe string into trench
Backfilling Trench
Reinstatement of Pipeline ROW (Right-of-Way)
Reinstatement of River Banks
Crossing - Horizontal Directional Drilling
Crossing - Thrust Boring
Crossing - River
Hydrotest & Pigging
Tie-in i.e. connect to existing pipeline
Miscellaneous
Pause Slides to Read
98. Horizontal Directional Drilling
Pipework
Brief Description
Horizontal Directional Drilling under a taxiway.
Process
1. A pilot hole id drilled to the designed profile
2. A reamer is pulled back through the hole to enlarge it
3. A pipe string is pulled into the hole.
119. HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Health,Safety&Environment
121. Safety Documents
Health,Safety&Environment
Safe System of Work.
To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a
job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe
and he is unlikely to be injured or cause damage by carrying out the assigned task.
Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)
The Project HSSE Management Plan details how safety on site will be managed.
Project Procedures for Health, Safety, Security & Environment
Details the safe way to undertake a task
Methods Statements
Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The
contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities
of Staff. Resources, Work Methodologies and Risk Assessment.
Slide 1 of 2
122. Safety Documents
Health,Safety&Environment
Safety Risk Assessments
Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.
COSHH Sheet
The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control
workers exposure to hazardous substances.
Permit to Work.
Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting
work.
Types of work for which permits will be required include:
Excavation and the digging of trenches.
Working at height, including on roofs.
Working in confined spaces, for example entering a manhole.
Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.
Slide 2 of 2
123. Safety Training on Site
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
131. Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
138. Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
139. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
147. Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
149. Primary Substation-
Chiller Plant
Pump House
IRRIGATION WATER TANKS
Irrigation Pump House-
POTABLE/FIRE WATER TANK
Programme using Timeline & 3D Images
Airport Central Utility Yard
156. Time Chainage Diagram The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Sample Only
157. Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
160. Temporary Contractors Site Facilities
ⓒ David H Moloney
Brief Description
Site Offices, Camp Accommodation for
1,250 workers, Canteen, Recreation,
Fabrication shops, Stores, Plant Yard. In five
locations along the route.
161. Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
166. Weighbridge & Sheeting Access
ⓒ David H Moloney
GeneralItems Access tower for covering tipper truck bodies to
prevent air pollution.
167. Dust Suppression
ⓒ David H Moloney
GeneralItems
Wetting the ground to prevent dust blowing in the wind
168. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
170. Quarry & Aggregate Production
3D image to show Sequence, Method & Plant. ⓒ David H Moloney
Rock is blasted free from a
quarry face and fragmented.
The blasted rock is crushed and
screened to produce different
size ranges of aggregates
172. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
175. Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
176. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site