Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
SlideShare a Scribd company logo
Oil & Gas Plant Construction
Project Execution Plan
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to
ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/oil-gas-plant-construction-project-execution-plan
https://www.youtube.com/watch?v=PiRY0ERoXfI
6avid H Moloney
4th August 2016
Brief Description
The purpose of this presentation is to give an understanding of
the Methods, Plant and Sequence to construct a Gas & Oil Plant
.
This presentation can be used to engage Stakeholders and to get
the Site Teams commitment to the programme. Also can be
used for Induction Training and as a way to capture and share
knowledge.
Project Execution Plan (PEP) details how a project will be
executed, monitored and controlled.
High in Educational Value and easily understood. Recommended
for Continuing Professional Development (CPD)
This Video Presentation is innovative and has many beneficial
uses.
Table of Contents
Contents
Gas Processing Facility
Earthworks includes Excavation, Trenches, Haulage, Grading Backfilling, Filling & Compaction
Earthworks
Excavate & Load Tipper Trucks
Trench Excavation with Stepped Faces
Trench Excavation with Battered Faces
Tipper Trucks Unloading
Spreading & Compaction Clay fillEarthworks
Spreading & Compaction Clay fillEarthworks
Backfill TrenchEarthworks
Dozer Pushing ClayEarthworks
Dozer Ripping GroundEarthworks
Excavator with Hydraulic RockbreakerEarthworks
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
CABC ( Crushed aggregate base course )
Earthworks
Mixing Plant
Testing Compaction
Site Trial
Mixing CABCEarthworks
Spreading & Compaction CABC ( Crushed aggregate base course )
Earthworks
Spreading & Compaction CABC ( Crushed aggregate base course )Earthworks
Spreading & Compaction CABC ( Crushed aggregate base course )Earthworks
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Contents
Insitu Piling Construction - Plant & Methods
3D image to show Plant.
For construction details see my YouTube Channel
Plant & Equipment
Crawler Crane
Piling Hammer
Casing
Piling Rig
Concrete Pump
Concrete Mixer Trucks
Tremie Pipe
Reinforcement Cage
Piling Construction - Plant, Methods & SequencePiling
Piling Construction - Plant & MethodsPiling
Pile Load Test
ⓒ David H Moloney
Piling
Sheet Pile Shaft Temporary to Support Excavation
Drive Sheet Piles Excavate & install bracing
Construct Concrete Structure Backfill, remove bracing & sheet piles
ⓒ David H Moloney
Sheet pile Temporary Shaft
ⓒ David H Moloney
GeneralItems
3D Animation to show Sequence
Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Diaphragm Wall Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Contents
Jetty for Oil Tankers
ⓒ David H Moloney
Marine
Quay Wall
ⓒ David H Moloney
Marine
Breakwater
ⓒ David H Moloney
Marine
Dredging & Reclamation
ⓒ David H Moloney
Marine
Contents
Reinforced Wall Construction Sequence
3D image to show Sequence, Method & Plant.
ⓒ David H Moloney
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Reinforced Structure Construction Sequence
ⓒ David H Moloney
Concrete
Reinforced Construction Tank Sequence David H Moloney
ⓒ David H Moloney
Oil Interceptor
Miscellaneous
Used to capture oil / fuel from leaks or spillages that are washed down
drains every time it rains.
Oil Interceptor
Concrete
Excavation for Underground Pump stationEarthworks
Brief Description
Faces of excavation Stepped &
Well-point Dewatering used.
Contents
Main Equipment
Path of Construction 45
Slug Catcher
Generators – Gas Turbine Flares
Liquid Train Gas Train Compressors
The Pipe Racks carries pipes and cables.
The pipes contain gas and liquids that are transported to and from the
different processes.
Pipe Rack
Piperack Construction Animation
The Pipe Racks carry pipes and cables
between the different processes..
Pipe Rack
Pipe Rack - Expansion Loop
49
Gas Processing Facility
Hanging Scaffold
Stairway Tower
Pipe Rack – Scaffold Underslung
Pipe Rack under construction
The slug catcher buffers the incoming gas and liquid, from the wellheads, it
also separates the gas from the liquid.
Slug Catcher
Slug Catcher Construction Sequence Animation
Separates the Gas from the Oil & Water
Also to dissipate any pressure surges
Slug Catcher
Storage of Oil & Water
Steel Circular Tanks Construction
Steel Storage Tank
ⓒ David H Moloney
StructuralSteel
Steel Circular Storage Tank – Construction ⓒ David H Moloney
Contents
Piping Spool Fabrication
Piping Spools are pre-fabricated from pipes and pipe fittings in fabrication shops to
reduce on site fabrication costs and provide better quality.
Spool Fabrication in Workshop
Pipework
Pipe Spools examples
Spool Fabrication on site
Pipework
Post Weld Heat
Treatment
Non Destructive
Testing
Cut
Bevel
Fit-up
Weld
NDT
PWHT
Blasting
Painting
Spool Fabrication Steps
Welding Trials
Welding
Fit up Clamp
Spool Fabrication - Pipe Rolling & Cutting Table
Pipework
Spool Fabrication Spool Rolling & Welding
Pipework
W. Soule & Company USA
Spool Fabrication - Automatic Welding with Pipe Rolling
Pipework
W. Soule & Company USA
Welding Positioner / Turntable
Pipework
Anyeke.com.my
Contents
Erect Flares / Columns & Vessels
Cranes Heavy Lift Animation
Lift column from the horizontal and
rotate into the vertical
Gas Processing Facility
Erect Flares / Columns & Vessels - 3D Simulation
Flares / Columns / Vessels Erection
Path of Construction 74
Demag CC180-1 300 t crawler crane
72m boom & 42m luffing jib
Tandem Lift to tilt flare
from horizontal to vertical
Trunnions
Main
Lift
Crane
Tail
Crane
Contents
Electrical Sub Station 3D Model
3D Model – Used to provide a better understanding
Main Substation Horizontal Cross section
Transformer Bays
HVAC Room
Heat, Ventilation, & Air Conditioning
Battery Room
UPS
Room
Local
Equipment
Room
Chillers
Electrical Sub Station
3D Model - Horizontal cross sections moving upwards
Electrical Sub Station
3D Model - Vertical cross sections moving along building
Structural Steel Building Single Storey
3D images to show Construction Sequence.
ⓒ David H Moloney
Step 1 Set-out Grid Lines Step 2 Holding Down Bolts Step 3 Erect 1st Bay
Step 4 Erect 2nd Bay Step 5 Erect following Bays
Steel Building Single Storey
ⓒ David H Moloney
StructuralSteel
Structural Steel Building Multi Storey
ⓒ David H Moloney
Step 1 Set-out Grid Lines Step 2 Holding Down Bolts Step 3 Erect 1st level use core for stability
Step 4 Complete 1st Level Step 5 Erect following Levels Step 6 Plumb & Align Structure
3D images to show Construction Sequence.
Roof Covering
ⓒ David H Moloney
StructuralSteel
Brief Description
Sequence is
Fix bottom sheet
Fix Vapour barrier
Fix Top Hat section and clips
Fit Insulation
Fix top sheet
Roof Covering
ⓒ David H Moloney
StructuralSteel
Roof Covering
ⓒ David H Moloney
StructuralSteel
Roof Covering
ⓒ David H Moloney
StructuralSteel
Contents
Onshore Gas Pipeline Construction Sequence
Gas Processing Facility
Construction of Azerbaijan Oil Pipeline 42” by 450km.
Overview Construction Sequence
A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the
route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and
reinstating the land to its original condition.
.
Crossing Railway, Roads, Rivers, etc.
Pump Station
Oil Pipeline 42”
Contents
Overview
Surveying & Setting Out
Clearing & Grading
Double Jointing i.e. welding 2 pipes together
Stringing out Pipes
Bend Pipes for changes in direction sideways and up & down
Welding Pipes into a string, Test Weld by X Ray.
Anti-corrosion Coat to Joints
Trenching i.e. excavate trench
Lowering pipe string into trench
Backfilling Trench
Reinstatement of Pipeline ROW (Right-of-Way)
Reinstatement of River Banks
Crossing - Horizontal Directional Drilling
Crossing - Thrust Boring
Crossing - River
Hydrotest & Pigging
Tie-in i.e. connect to existing pipeline
Miscellaneous
Pause Slides to Read
Overview Pipeline Construction Animation
To see animations, view YouTube film.
Cable laying 132KVa Electric
Cable Laying
Pipework
Brief Description
132 kVa Cable laying .
Cable Laying
Pipework
Cable Laying
Pipework
Cable Laying
Pipework
Contents
Horizontal Directional Drilling
Pipework
Brief Description
Horizontal Directional Drilling under a taxiway.
Process
1. A pilot hole id drilled to the designed profile
2. A reamer is pulled back through the hole to enlarge it
3. A pipe string is pulled into the hole.
Horizontal Directional Drilling
Pipework
Crossings – River, Motorway & Rail
Pipework
Overview Pipeline Crossings Construction Animation
Micro Tunnelling
Tunnels
Micro Tunnelling Sequence David H Moloney
ⓒ David H Moloney
Tunnels
Contents
Includes Sequence, Methods & Equipment
Road Construction
Road Construction Sequence Animation
Asphalt Pavement
Includes Sequence, Methods & Equipment
Fencing & Gates
Fencing
ⓒ David H Moloney
Sequence of Construction
Clear Scrub & Grade ground
Fix Corner & Strainer Posts
Fix Intermediate Posts
Fix Line Wire, Chain-link & Razer wire
Concrete ground beam
Fencing
Miscellaneous
Fencing
Miscellaneous
Fencing
Miscellaneous
Fencing
Miscellaneous
Contents
Setting out & Surveying
Setting out & Surveying
Contents
Emergency Phone Numbers & Response
Health,Safety&Environment
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Health,Safety&Environment
Safety Precautions
Health,Safety&Environment
Safety Documents
Health,Safety&Environment
Safe System of Work.
To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a
job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe
and he is unlikely to be injured or cause damage by carrying out the assigned task.
Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)
The Project HSSE Management Plan details how safety on site will be managed.
Project Procedures for Health, Safety, Security & Environment
Details the safe way to undertake a task
Methods Statements
Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The
contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities
of Staff. Resources, Work Methodologies and Risk Assessment.
Slide 1 of 2
Safety Documents
Health,Safety&Environment
Safety Risk Assessments
Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.
COSHH Sheet
The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control
workers exposure to hazardous substances.
Permit to Work.
Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting
work.
Types of work for which permits will be required include:
Excavation and the digging of trenches.
Working at height, including on roofs.
Working in confined spaces, for example entering a manhole.
Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.
Slide 2 of 2
Safety Training on Site
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Safety Training Matrix
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Emergency Response Drill
HSE
Drills and exercises are used to rehearse anticipated emergency scenarios
Exposed Existing Underground Utilities
ⓒ David H Moloney
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Trench - Safety Measures
Health,Safety&Environment
Trench - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Site Safety Posters examples
Health,Safety&Environment
Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
Environmentally Friendly Site Air, Noise, Water & Soil PollutionHealth,Safety&Environment
Water Pollution PreventionHealth,Safety&Environment
Segregation of WasteHealth,Safety&Environment
Segregation of waste for proper disposal and
recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Putting Waste Concrete to use
ⓒ David H Moloney
Health,Safety&Environment Precast bases for signs and hoarding,
Precast blocks for walls.
Contents
Staff Directory
Brief Description
List of staff and their
contact details
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Filing System
Quotations Comparison Sheet
Staff Responsibility Matrix
Contents
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
Site Laboratory
Generalitems
Contents
Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
Programme for Construction
Gantt Charts to plan and schedule projects
Primary Substation-
Chiller Plant
Pump House
IRRIGATION WATER TANKS
Irrigation Pump House-
POTABLE/FIRE WATER TANK
Programme using Timeline & 3D Images
Airport Central Utility Yard
Pump House
Piling
Primary Substation-711
Chiller Plant-714
Pump House-
715
Irrigation Pump House-
716
Primary Substation-711
Chiller Plant-714
Pump House-
715
IRRIGATION WATER TANK
Irrigation Pump House-
716
Primary Substation-711
Chiller Plant-714
Pump House-
715
IRRIGATION WATER TANK
Irrigation Pump House-
716
Primary Substation-711
Chiller Plant-714
Pump House-
715
IRRIGATION WATER TANK
Irrigation Pump House-
716
Primary Substation-711
Chiller Plant-714
Pump House-
715
IRRIGATION WATER TANK
Irrigation Pump House-
716
POTABLE/FIRE WATER TANK
Time Chainage Diagram The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Sample Only
Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Contents
Temporary Contractors Site Facilities
ⓒ David H Moloney
Brief Description
Site Offices, Camp Accommodation for
1,250 workers, Canteen, Recreation,
Fabrication shops, Stores, Plant Yard. In five
locations along the route.
Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
GeneralItems
Wheel Wash Drive-through
ⓒ David H Moloney
GeneralItems
Used to wash the wheels of trucks prior to leaving site.
Wheel Wash Drive-throughGeneralItems
Weighbridge & Sheeting Access
ⓒ David H Moloney
GeneralItems Access tower for covering tipper truck bodies to
prevent air pollution.
Dust Suppression
ⓒ David H Moloney
GeneralItems
Wetting the ground to prevent dust blowing in the wind
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant. ⓒ David H Moloney
Rock is blasted free from a
quarry face and fragmented.
The blasted rock is crushed and
screened to produce different
size ranges of aggregates
Quarry & Aggregate ProductionGeneralItems
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
Concrete Batching Plant
ⓒ David H Moloney
Concrete
Concrete Batching Yard 3 Nr MixersGeneralItems
Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Contents
Notes
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
ⓒ David H Moloney

More Related Content

What's hot

oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
Mario Fonseca
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
Surya Kant
 
PIPING SUPERVISOR RESUME
PIPING SUPERVISOR RESUME  PIPING SUPERVISOR RESUME
PIPING SUPERVISOR RESUME
Raghavendra Velayutharaja
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
MDAbdullah621330
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
MFaridGeonova
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
Ir. Puput Risanto, IPM, PMP, PMI-RMP, ASEAN Eng
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
IEI GSC
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
TW Carl
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malik
MOHAMAD ANWAR MALIK
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
James Ct
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
HIMADRI BANERJI
 
Amol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docxAmol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant
 
Milestone checklist
Milestone checklist   Milestone checklist
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility DecommissioningCost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
Donnie Miller
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
Shaik Mohsin
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
OGDoilandgasdocs
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
Sunil Manjeri
 
Oil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesOil & Gas Production and Surface Facilities
Oil & Gas Production and Surface Facilities
Mohamed Elnagar
 

What's hot (20)

oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
PIPING SUPERVISOR RESUME
PIPING SUPERVISOR RESUME  PIPING SUPERVISOR RESUME
PIPING SUPERVISOR RESUME
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malik
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Amol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docxAmol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docx
 
Milestone checklist
Milestone checklist   Milestone checklist
Milestone checklist
 
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility DecommissioningCost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
 
Oil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesOil & Gas Production and Surface Facilities
Oil & Gas Production and Surface Facilities
 

Viewers also liked

Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
David H Moloney
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
David H Moloney
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
David H Moloney
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
David H Moloney
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
David H Moloney
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
David H Moloney
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
David H Moloney
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
David H Moloney
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
David H Moloney
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
C K Vishwakarma
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
David H Moloney
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
David H Moloney
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
David H Moloney
 
Project Execution
Project ExecutionProject Execution
Project Execution
megat zainurul anuar
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
David H Moloney
 
Project Execution
Project ExecutionProject Execution
Project Execution
railengineer011
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
Anand Subramaniam
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
Construction Tech. and Mgmt., VNIT Nagpur
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
Wayne Holley
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
Lamdade Akhil
 

Viewers also liked (20)

Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 

Similar to Oil & Gas Plant Construction, Project Execution Plan

Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
David H Moloney
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
David H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
David H Moloney
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
Water Birds (Ali)
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
SaurabhSingh20590
 
Construction site visit
Construction site visitConstruction site visit
Construction site visit
Shailja km
 
Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.
SHWETABH SINHA
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
Marginal satellite study Noordzee
Marginal satellite study NoordzeeMarginal satellite study Noordzee
Marginal satellite study Noordzee
Sander_van_oirschot
 
Marginal offshore production platform feasibility
Marginal offshore production platform feasibilityMarginal offshore production platform feasibility
Marginal offshore production platform feasibility
guest651e92c
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 
Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
Sigve Hamilton Aspelund
 
Satyavir-Resume_01
Satyavir-Resume_01Satyavir-Resume_01
Satyavir-Resume_01
SATYAVIR SINGH
 
number 1. pro cv
number 1. pro cvnumber 1. pro cv
number 1. pro cv
Dave Chase
 
Well Workover
Well Workover Well Workover
Well Workover
Christian Akhilome
 
Resume M McAbee
Resume M McAbeeResume M McAbee
Resume M McAbee
Matthew Mcabee
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
Korutla Harish
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
Matthias Schueller
 
presentation
presentationpresentation
presentation
Shivam Upadhyay
 

Similar to Oil & Gas Plant Construction, Project Execution Plan (20)

Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
Construction site visit
Construction site visitConstruction site visit
Construction site visit
 
Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
Marginal satellite study Noordzee
Marginal satellite study NoordzeeMarginal satellite study Noordzee
Marginal satellite study Noordzee
 
Marginal offshore production platform feasibility
Marginal offshore production platform feasibilityMarginal offshore production platform feasibility
Marginal offshore production platform feasibility
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
 
Satyavir-Resume_01
Satyavir-Resume_01Satyavir-Resume_01
Satyavir-Resume_01
 
number 1. pro cv
number 1. pro cvnumber 1. pro cv
number 1. pro cv
 
Well Workover
Well Workover Well Workover
Well Workover
 
Resume M McAbee
Resume M McAbeeResume M McAbee
Resume M McAbee
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
presentation
presentationpresentation
presentation
 

More from David H Moloney

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
David H Moloney
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
David H Moloney
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
David H Moloney
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
David H Moloney
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
David H Moloney
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
David H Moloney
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
David H Moloney
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
David H Moloney
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
David H Moloney
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
David H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
David H Moloney
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
David H Moloney
 

More from David H Moloney (12)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
 

Recently uploaded

UNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.ppt
UNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.pptUNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.ppt
UNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.ppt
shanmugamram247
 
LOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdf
LOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdfLOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdf
LOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdf
jellyjm
 
Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...
Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...
Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...
singharadhana4778
 
AFCAT STATIC Genral knowledge important CAPSULE.pdf
AFCAT STATIC Genral knowledge important CAPSULE.pdfAFCAT STATIC Genral knowledge important CAPSULE.pdf
AFCAT STATIC Genral knowledge important CAPSULE.pdf
vibhapatil140
 
AI chapter1 introduction to artificial intelligence
AI chapter1 introduction to artificial intelligenceAI chapter1 introduction to artificial intelligence
AI chapter1 introduction to artificial intelligence
GeethaAL
 
Indian Railway Signalling concepts and basics.pdf
Indian Railway Signalling concepts and basics.pdfIndian Railway Signalling concepts and basics.pdf
Indian Railway Signalling concepts and basics.pdf
princeshah76
 
AI INTRODUCTION Artificial intelligence.ppt
AI INTRODUCTION Artificial intelligence.pptAI INTRODUCTION Artificial intelligence.ppt
AI INTRODUCTION Artificial intelligence.ppt
GeethaAL
 
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf
AsiimweJulius2
 
Buy a fake University of Washington diploma
Buy a fake University of Washington diplomaBuy a fake University of Washington diploma
Buy a fake University of Washington diploma
College diploma
 
Girls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in City
Girls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in CityGirls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in City
Girls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in City
sunnuchadda
 
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...
Fady M. A Hassouna
 
The Control of Relative Humidity & Moisture Content in The Air
The Control of Relative Humidity & Moisture Content in The AirThe Control of Relative Humidity & Moisture Content in The Air
The Control of Relative Humidity & Moisture Content in The Air
Ashraf Ismail
 
Red Hat Enterprise Linux Administration 9.0 RH134 pdf
Red Hat Enterprise Linux Administration 9.0 RH134 pdfRed Hat Enterprise Linux Administration 9.0 RH134 pdf
Red Hat Enterprise Linux Administration 9.0 RH134 pdf
mdfkobir
 
Red Hat Enterprise Linux Administration 9.0 RH124 pdf
Red Hat Enterprise Linux Administration 9.0 RH124 pdfRed Hat Enterprise Linux Administration 9.0 RH124 pdf
Red Hat Enterprise Linux Administration 9.0 RH124 pdf
mdfkobir
 
If we're running two pumps, why aren't we getting twice as much flow? v.17
If we're running two pumps, why aren't we getting twice as much flow? v.17If we're running two pumps, why aren't we getting twice as much flow? v.17
If we're running two pumps, why aren't we getting twice as much flow? v.17
Brian Gongol
 
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...
John Gallagher
 
charting the development of the autonomous train
charting the development of the autonomous traincharting the development of the autonomous train
charting the development of the autonomous train
huseindihon
 
Lab session on Robot Control using teach pendant.pptx
Lab session on Robot Control using teach pendant.pptxLab session on Robot Control using teach pendant.pptx
Lab session on Robot Control using teach pendant.pptx
KPavanKumarReddy4
 
Cisco Intersight Technical OverView.pptx
Cisco Intersight Technical OverView.pptxCisco Intersight Technical OverView.pptx
Cisco Intersight Technical OverView.pptx
Duy Nguyen
 
the potential for the development of autonomous aircraft
the potential for the development of autonomous aircraftthe potential for the development of autonomous aircraft
the potential for the development of autonomous aircraft
huseindihon
 

Recently uploaded (20)

UNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.ppt
UNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.pptUNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.ppt
UNIT 1 - INTRODUCTION ON DISASTER MANAGEMENT.ppt
 
LOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdf
LOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdfLOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdf
LOCAL-BUDGET-CIRCULAR-NO-158-DATED-JULY-11-2024.pdf
 
Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...
Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...
Girls call Service Ludhiana 000XX00000 Provide Best And Top Girl Service And ...
 
AFCAT STATIC Genral knowledge important CAPSULE.pdf
AFCAT STATIC Genral knowledge important CAPSULE.pdfAFCAT STATIC Genral knowledge important CAPSULE.pdf
AFCAT STATIC Genral knowledge important CAPSULE.pdf
 
AI chapter1 introduction to artificial intelligence
AI chapter1 introduction to artificial intelligenceAI chapter1 introduction to artificial intelligence
AI chapter1 introduction to artificial intelligence
 
Indian Railway Signalling concepts and basics.pdf
Indian Railway Signalling concepts and basics.pdfIndian Railway Signalling concepts and basics.pdf
Indian Railway Signalling concepts and basics.pdf
 
AI INTRODUCTION Artificial intelligence.ppt
AI INTRODUCTION Artificial intelligence.pptAI INTRODUCTION Artificial intelligence.ppt
AI INTRODUCTION Artificial intelligence.ppt
 
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf
1. DEE 1203 ELECTRICAL ENGINEERING DRAWING.pdf
 
Buy a fake University of Washington diploma
Buy a fake University of Washington diplomaBuy a fake University of Washington diploma
Buy a fake University of Washington diploma
 
Girls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in City
Girls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in CityGirls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in City
Girls Call Chennai 000XX00000 Provide Best And Top Girl Service And No1 in City
 
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...
ECONOMIC FEASIBILITY AND ENVIRONMENTAL IMPLICATIONS OF PERMEABLE PAVEMENT IN ...
 
The Control of Relative Humidity & Moisture Content in The Air
The Control of Relative Humidity & Moisture Content in The AirThe Control of Relative Humidity & Moisture Content in The Air
The Control of Relative Humidity & Moisture Content in The Air
 
Red Hat Enterprise Linux Administration 9.0 RH134 pdf
Red Hat Enterprise Linux Administration 9.0 RH134 pdfRed Hat Enterprise Linux Administration 9.0 RH134 pdf
Red Hat Enterprise Linux Administration 9.0 RH134 pdf
 
Red Hat Enterprise Linux Administration 9.0 RH124 pdf
Red Hat Enterprise Linux Administration 9.0 RH124 pdfRed Hat Enterprise Linux Administration 9.0 RH124 pdf
Red Hat Enterprise Linux Administration 9.0 RH124 pdf
 
If we're running two pumps, why aren't we getting twice as much flow? v.17
If we're running two pumps, why aren't we getting twice as much flow? v.17If we're running two pumps, why aren't we getting twice as much flow? v.17
If we're running two pumps, why aren't we getting twice as much flow? v.17
 
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...
Fix Production Bugs Quickly - The Power of Structured Logging in Ruby on Rail...
 
charting the development of the autonomous train
charting the development of the autonomous traincharting the development of the autonomous train
charting the development of the autonomous train
 
Lab session on Robot Control using teach pendant.pptx
Lab session on Robot Control using teach pendant.pptxLab session on Robot Control using teach pendant.pptx
Lab session on Robot Control using teach pendant.pptx
 
Cisco Intersight Technical OverView.pptx
Cisco Intersight Technical OverView.pptxCisco Intersight Technical OverView.pptx
Cisco Intersight Technical OverView.pptx
 
the potential for the development of autonomous aircraft
the potential for the development of autonomous aircraftthe potential for the development of autonomous aircraft
the potential for the development of autonomous aircraft
 

Oil & Gas Plant Construction, Project Execution Plan